Required for new commercial construction in Tooele City, regulated by the state-mandated 2024 IBC (Utah Code § 15A-2-103, effective 7/1/2026; Tooele City's own Building Codes and Design Criteria sheet still lists the 2021 IBC as of live re-check 2026-07-16). The Building Permit Fee is valuation-based per IBC rate tables (same mechanism as residential); Tooele City's current Fee Schedule page separately lists Commercial plan review at the 'IBC Rate,' and commercial sites are subject to a distinct Site Plan Review fee tied to site acreage.
Verified 2026-07-19 · Source
When you need this permit
- New commercial construction regulated by the state-mandated 2024 IBC (Tooele City's own sheet still lists the 2021 IBC as of live re-check 2026-07-16 — see codesAdopted)
- Site plan showing property size, existing building locations, and the proposed structure location
- Complete construction documents showing structural and physical elements of the project
- State of Utah licensed contractors listed on the application (General, Electrical, Mechanical, Plumbing) Contractor
- Site Plan Review required for commercial sites, scaled to site acreage
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour, per standard IBC inspection sequence; all inspections require 1 working day advance notice.
- 2
Structural / Framing
Framing and structural connections verified against submitted structural drawings.
- 3
MEP Rough-In
Electrical, mechanical, and plumbing rough-in verified against submitted plans.
- 4
Final / Certificate of Occupancy
Final inspection required before occupancy.
See the full Tooele inspection guide — scheduling & re-inspection fees →
Tips
- Commercial sites require a separate Site Plan Review with its own fee (scaled by acreage: $1,500 under 1 acre, $2,000 for 1.0–3.0 acres, $2,000 + $500/acre over 3 acres) — this is distinct from and in addition to the Building Permit Fee and Plan Review fee.
- Two different Tooele City sources describe the Plan Review/Plan Check fee differently: the current Fee Schedule page states 'IBC Rate' for Commercial (and every other use type), while the older Building Permit Fees Information Sheet (March 2015) describes a flat 65%-of-permit-fee calculation without a use-type split — confirm which applies with Community Development, (435) 843-2132.
- Public Safety Impact Fees for commercial construction are assessed per 1,000 square feet of building ($187.40 Fire + $164.70 Police), not per dwelling unit as with residential.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Tooele building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Tooele.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Tooele
Commercial Building Permit in other cities
Compare commercial building permit fees across Utah →