Lindon building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Lindon, Utah.
Verified 2026-07-13 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 100 North State Street, Lindon, UT 84042
- Phone
- (801) 785-7687
- building@lindon.gov
- Office hours
- Website
- Official site
Published scheduling rules
- Every required inspection must be scheduled a minimum of 24 hours in advance, per Lindon's official Residential Single-Family Dwelling Building and Site Inspections checklist. (Residential Building Permit (New SFD, Townhome, Duplex, ADU))
- Temporary and permanent power inspections require direct coordination with Rocky Mountain Power, (888) 221-7070 — this is separate from the city's own inspection line. (Residential Building Permit (New SFD, Townhome, Duplex, ADU))
- The signal transmission test verifies monitoring through Metro Dispatch, (801) 854-6211 — schedule inspections through Orem's online inspections system (orem.gov/inspections-and-permits/). (Fire Alarm System Permit)
Inspection sequence
Applies to: Residential Building Permit (New SFD, Townhome, Duplex, ADU)
- 1
Sediment Control
Must pass prior to footing inspection. Administered by Public Works. Per Lindon's official Residential Single-Family Dwelling Building and Site Inspections checklist.
- 2
Building Clearance
After survey property pins are in place; may be completed with the footing inspection. Building Department.
- 3
Temporary Power
Request service from Rocky Mountain Power, (888) 221-7070.
- 4
Footing Inspection
After footings are dug, formed, and steel is in place, prior to pouring concrete. Soil report must be submitted to the Building Department 24 hours prior to inspection.
- 5
Foundation Inspection
After forms and steel are in place, prior to pouring concrete.
- 6
Foundation Drain and Waterproofing
Prior to backfilling.
- 7
Under-Slab Heating and Plumbing / Rebar (suspended slab) / Shear Inspection
Shear inspection can be completed before or with the 4-way rough inspection.
- 8
4-Way Rough Inspection (Framing, Electrical, Mechanical, Plumbing)
May be combined into a single 4-way inspection, per Lindon's official inspection checklist.
- 9
Insulation and Weather Barrier
Weather barrier inspection required prior to installing exterior finishes; stucco lath must be installed with tears and penetrations sealed.
- 10
Drywall Nailing (fire-rated assemblies), Permanent Power, Gas Line/Pressure Test, Gas Meter Mechanical
Permanent power requires separate inspection by Rocky Mountain Power for all underground service. Gas meter requires two inspections (line/pressure test, then mechanical).
- 11
Final Building Inspection
Building Department final sign-off. Public Works also finals Water Service, Sewer Lateral, Drive Approach and Sidewalk, Pressurized Irrigation, Land Drain, and SWPPP as applicable.
Applies to: Commercial Building Permit
- 1
Foundation / Footing Inspection
After footings are dug, formed, and steel is in place, prior to pouring concrete, per standard IBC inspection sequence enforced by the Building Department, (801) 785-7687.
- 2
Framing Inspection (Structural, Rough Electrical/Plumbing/Mechanical)
After framing, structural connections, and rough MEP are in place, prior to enclosing walls or ceilings.
- 3
Fire Sprinkler and/or Fire Alarm Rough-In
Required where a fire sprinkler or alarm system is part of the project scope, per the Commercial Plan Submittal Checklist.
- 4
Insulation and Energy Compliance Inspection
After insulation is installed, prior to drywall/finish, verifying energy compliance documentation submitted with plans.
- 5
Final Building Inspection
Building Department final sign-off required before occupancy.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Structural Rough-In
Walls, partitions, and ceiling-support framing verified against submitted plans before close-in, per standard commercial inspection sequence enforced by the Building Department, (801) 785-7687.
- 2
Plumbing, Mechanical, and Electrical Rough-In
Rough plumbing, mechanical (ductwork, combustion air), and electrical (panel, wiring, outlets) verified prior to enclosing walls or ceilings.
- 3
Fire Sprinkler and/or Fire Alarm Rough-In
Required when a sprinkler or alarm system is part of the project scope, per the Tenant Improvement Checklist's 'additional plans' section.
- 4
Final Building Inspection
Building Department final sign-off required before occupancy of the completed tenant space.
Applies to: Fire Alarm System Permit
- 1
24-Hour Battery Test
Battery backup test for the fire alarm system panel.
- 2
Notifier Activation, Flow Switch Test, Tamper Test, Smoke Detector Test
Device-level activation and function testing, per Orem Fire Prevention's Contractor's Corner guidance for new-construction alarm systems.
- 3
Address Verification and Signal Transmission Test
Confirms the monitored alarm signal reaches Metro Dispatch, (801) 854-6211.
- 4
Alarm Final
Performed in conjunction with the sprinkler final inspection where both systems are present — both the alarm and sprinkler contractors should be present, per Orem Fire Prevention's guidance.
Applies to: Fire Sprinkler System Permit
- 1
Riser Flush
Bacteria test does not fulfill this requirement, per Orem Fire Prevention's Contractor's Corner guidance for new-construction sprinkler systems.
- 2
Above Grade / Rough Hydrostatic Pressure Test
Verifies piping integrity above grade before concealment.
- 3
Flow Sensors and Tampers
Flow sensor and tamper switch verification.
- 4
Sprinkler Final
Performed in conjunction with the fire alarm final inspection — both the sprinkler and alarm contractors should be present, per Orem Fire Prevention's guidance.
Applies to: Change of Use / Change of Occupancy (Business License Application)
- 1
Building Department On-Site Inspection
Confirms ordinance compliance and zoning-district conformance for the business location, per Lindon's Business License FAQ.
- 2
Fire Inspection (Orem City Fire Prevention Division)
Required for all commercial businesses, and for any Home Occupation that is a manufacturing business, will have clients, customers, children, or employees on the premises at any time, or stores flammable or hazardous materials. Scheduled through Orem Fire Prevention (previously coordinated via named Orem Fire Department contact per Lindon's Business Licensing page).
Applies to: Residential Addition / Remodel / Basement Finish Permit
- 1
Rough Framing, Electrical, Mechanical, Plumbing
May be combined into a single inspection depending on scope, per Lindon's standard residential inspection sequence.
- 2
Final Building Inspection
Building Department final sign-off required before occupancy of the completed addition or remodeled/finished space.
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lindon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Lindon building permits
Get alerts for Lindon
We'll email you when Lindon's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.