Lindon does not publish a distinct solar or solar-PV permit application, checklist, or fee. Solar installations (rooftop or ground-mounted) are explicitly named within the same 'Other Residential' Building Permit Application Fee category used for pools, additions, detached garages, sheds, and retaining walls — the city's 2025-2026 Fee Schedule (FY2025-26 Final Budget) lists this category's parenthetical as '(Pools, additions, detached garages, sheds, retaining walls, solar)' at a flat $100.00. A full-text search of the Building & Inspection department page and the site found zero dedicated solar checklist, application form, or solar-specific requirements published by the city.

Verified 2026-07-21 · Source

When you need this permit

  • Building permit application submitted through Lindon's online CivicReview portal, same as other 'Other Residential' permit types (no solar-specific application form is published)
  • Electrical plan showing PV system components (panels, inverter(s), disconnects, conductor sizing) sufficient for the Building Department's standard electrical review, since Lindon has no separate solar checklist to define scope-specific submittal requirements
  • Site plan showing panel/array location for roof-mounted systems, or location and setbacks for ground-mounted arrays
  • Utility interconnection agreement with Rocky Mountain Power for grid-tied systems — coordinated directly with the utility, (888) 221-7070, separately from the city building permit, consistent with how Lindon handles other utility-coordinated electrical work (temporary/permanent power)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Application Fee (Other Residential)Lindon City 2025-2026 Fee Schedule (FY2025-26 Final Budget Fee Schedule), 'Building Permit Application Fee,' 'Other Residential' line (last updated 6/03/2024 with Ordinance 2024-8-O): '$100.00 (Pools, additions, detached garages, sheds, retaining walls, solar)' — solar is explicitly named in this category's own parenthetical list, confirmed via direct text extraction of the fee schedule PDF fetched 2026-07-21.
$100.00
Building Permit Fee — valuation-based (1997 UBC Table 1-A)Lindon City 2025-2026 Fee Schedule, 'Building Permit' line — same valuation-based method applied to all building permit types, not split out separately for solar.
Determined using 1997 Uniform Building Code, Table 1-A, applied to project valuation
Plan Review Fee (residential)Lindon City 2025-2026 Fee Schedule, 'Plan Review Fee' line, 'Residential' rate — applies to 'Other Residential' category permits including solar.
25% of permit fee
Building Permit State FeeLindon City 2025-2026 Fee Schedule, 'Building Permit State Fee' line item — statewide surcharge applied to all building permits.
1% of Building Permit Fee
Public Improvement Repair Assurance (refundable, Other Residential) — applicability to solar not explicitly confirmedLindon City 2025-2026 Fee Schedule, 'Public Improvement Repair Assurance,' 'Other Residential' line: '$2,500.00 (Such as pools, additions, detached accessory structures, retaining walls, or any other project that could damage public improvements).' Unlike the Building Permit Application Fee's 'Other Residential' category, this bond line does not explicitly name solar — it may apply to ground-mounted systems that disturb public improvements, but this has not been confirmed by the city for solar specifically. Confirm with the Building Department, (801) 785-7687, before budgeting for a bond on a solar project.
$2,500.00

Review timeline

Plan review
Not published — contact the department

How long did your Solar / Solar PV Installation Permit permit actually take in Lindon?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Trade-Specific Final Inspection (Electrical / Building)

    Final inspection scheduled with the Building Department, (801) 785-7687, at least 24 hours in advance, per Lindon's standard inspection-scheduling requirement. No solar-specific inspection checklist is published by the city.

See the full Lindon inspection guide — scheduling & re-inspection fees →

Tips

  • Lindon has no distinct solar or solar-PV permit type, application, or fee — solar is one of six project types explicitly grouped under the flat $100 'Other Residential' Building Permit Application Fee, alongside pools, additions, detached garages, sheds, and retaining walls.
  • Because Lindon has no separate electrical-permit category (see this file's EV-charger entry), a solar installation's electrical scope is reviewed as part of the same general building permit rather than a standalone electrical permit.
  • Grid-tied systems require a separate utility interconnection agreement directly with Rocky Mountain Power, (888) 221-7070 — this is independent of, and in addition to, the city building permit.
  • The $2,500 'Other Residential' Public Improvement Repair Assurance bond does not explicitly name solar in its own fee-schedule parenthetical (unlike the Application Fee's parenthetical, which does) — confirm with the Building Department whether it applies to your specific installation, especially for ground-mounted arrays.

Frequently asked questions

Lindon requires a solar / solar pv installation permit for: Building permit application submitted through Lindon's online CivicReview portal, same as other 'Other Residential' permit types (no solar-specific application form is published); Electrical plan showing PV system components (panels, inverter(s), disconnects, conductor sizing) sufficient for the Building Department's standard electrical review, since Lindon has no separate solar checklist to define scope-specific submittal requirements; Site plan showing panel/array location for roof-mounted systems, or location and setbacks for ground-mounted arrays; Utility interconnection agreement with Rocky Mountain Power for grid-tied systems — coordinated directly with the utility, (888) 221-7070, separately from the city building permit, consistent with how Lindon handles other utility-coordinated electrical work (temporary/permanent power). If your project isn't listed, confirm with Lindon City Building Department (Community Development) at (801) 785-7687 before starting work.

The Building Permit Application Fee is a flat $100.00 under the 'Other Residential' category, which explicitly lists solar in its fee-schedule parenthetical. The underlying Building Permit Fee is valuation-based (1997 UBC Table 1-A) and the Plan Review Fee is 25% of the permit fee for residential projects. A $2,500 refundable Public Improvement Repair Assurance bond may also apply, though solar is not explicitly named in that bond's category — confirm with the Building Department.

Lindon does not publish a plan-review timeline for this permit. Contact Lindon City Building Department (Community Development) at (801) 785-7687 for current turnaround.

You'll need: Building Permit Application. See the required-documents checklist on this page for details on each.

Lindon requires 1 inspection(s) for a solar / solar pv installation permit, in order: Trade-Specific Final Inspection (Electrical / Building). Schedule each through Lindon City Building Department (Community Development) ((801) 785-7687).

Apply through Lindon City Building Department (Community Development) at 100 North State Street, Lindon, UT 84042. Phone: (801) 785-7687, email: building@lindon.gov. Official information: https://www.lindon.gov/251/Building-Inspection.

Lindon, Utah has adopted: 2021 International Residential Code (IRC), as amended by the State of Utah — adopted statewide under Utah Code Title 15A (State Construction and Fire Codes Act), § 15A-2-103. No Lindon-specific code-edition statement was found on lindon.gov's Building & Inspection page, Building Department Forms & Applications page, or in the current Fee Schedule; Lindon has not published a local amendment opting out of the statewide code, so the statutory statewide edition is used here rather than invented city-specific text.; 2024 International Building Code (IBC), as amended by the State of Utah — effective statewide July 1, 2026 per Utah Code § 15A-2-103 (2026 General Session update); no Lindon-specific IBC edition statement found on the city's own site.; 2023 National Electrical Code (NEC) — adopted statewide under Utah Code § 15A-2-103; no Lindon-specific NEC edition statement found on the city's own site.; 2015 International Plumbing Code (IPC), Table 403.1 — cited by name in Lindon City's own current Fee Schedule (Sewer Utility Fee and Water Utility Fee sections: 'Based on Table 403.1 in 2015 International Plumbing Code as currently adopted or as may be amended'), effective 07/01/2026 fee schedule. This is Lindon's own published reference to a specific plumbing-code edition/table used for utility base-rate sizing, distinct from the statewide construction-code IPC edition.; Other 2024 International Codes (IMC, IEBC, IECC) — adopted statewide alongside the 2024 IBC per Utah Code § 15A-2-103, effective July 1, 2026; not individually itemized by name on Lindon's own Building & Inspection page.. Local amendments apply — see the Lindon overview page for the full list.

No. Lindon's 2025-2026 Fee Schedule does not publish a distinct solar permit, application, or fee line. Solar is explicitly grouped into the same 'Other Residential' Building Permit Application Fee category as pools, additions, detached garages, sheds, and retaining walls, at a flat $100.00, plus the standard valuation-based Building Permit Fee (1997 UBC Table 1-A), a 25% residential Plan Review Fee, and a 1% state surcharge.