Required for installation of an automatic fire sprinkler (fire protection) system for new construction or a tenant improvement in Lindon. Lindon City does not employ its own fire-prevention plan reviewers or publish its own sprinkler-system fee table: since 2008, Lindon has contracted Fire/EMS response to Orem City, and Lindon has separately 'partnered with Orem City Fire Prevention and Inspection to perform inspections on new construction and business license inspections' (Lindon's official Fire/EMS page). Orem's Fire Prevention Division serves Orem, Lindon, and Vineyard for plan review, permits, and inspections. Lindon's own 2025-2026 Fee Schedule reflects this directly: its 'Plan Review Fee' section lists a distinct 'Fire Sprinkler and/or Fire Alarm Plan Review' line item priced 'As per Orem City Fee Schedule' — a genuinely governing, city-published cross-reference rather than an invented figure. Orem's own currently-adopted FY 2025-2026 Adopted Budget Fee Schedule (Exhibit B) prices Sprinkler System Inspections (office plan check, hydro test, flush, and final inspection) by project square footage; this is the figure Lindon's own schedule points to.

Verified 2026-07-21 · Source

When you need this permit

  • Automatic fire sprinkler (fire protection) system installation for new construction, or modification/extension of an existing system for a tenant improvement, in a building located in Lindon
  • Sprinkler system plans submitted directly to the Orem City Fire Prevention Division (fireprevention@orem.gov) for plan review — separate from, but coordinated with, the Lindon Building Department's own building-permit plan review
  • Third-party code compliance review is required for any new-construction or tenant-improvement sprinkler project involving 20 or more heads, per Orem Fire Prevention's published Contractor's Corner guidance
  • Complete set of fire sprinkler plans included with the Lindon Commercial Plan Submittal Checklist or Tenant Improvement Checklist submittal where a sprinkler system is part of the project scope, per this file's commercial-building-permit and commercial-tenant-improvement-permit entries
  • For a tenant improvement to a building with an existing fire suppression system, any modification to the existing floor plan requires updated coverage plans submitted to Orem Fire Prevention before work begins

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Fire Sprinkler and/or Fire Alarm Plan ReviewLindon City 2025-2026 Fee Schedule, 'Plan Review Fee' section (last updated 6/03/2024 with Ordinance 2024-8-O): lists 'Fire Sprinkler and/or Fire Alarm Plan Review — As per Orem City Fee Schedule' as its own line item, distinct from the Residential (25%) and Commercial (65%) Plan Review Fee percentages. Confirmed via direct full-text extraction of the fee schedule PDF, lindon.gov/DocumentCenter/View/199, fetched 2026-07-21.
As per Orem City Fee Schedule
Sprinkler System Inspections (Orem City Fire Prevention Division) — Additions, Remodels, or New Construction, under 3,000 sq. ft.City of Orem FY 2025-2026 Adopted Budget (Exhibit B Fee Schedule, FIRE section, 'SPRINKLER SYSTEM INSPECTIONS'), page 213: 'Under 3,000 sq. ft. — $260.00.' Footnote: 'Includes flush, office plan check, hydro and final inspections. Does not include required third-party technical review.' This is the fee Lindon's own Plan Review Fee line item references. Source fetched and full-text extracted 2026-07-21: orem.gov/wp-content/uploads/2025/07/Adopted-Budget-FY-2025-2026.pdf.
$260.00
Sprinkler System Inspections (Orem City Fire Prevention Division) — 3,001 to 8,000 sq. ft.City of Orem FY 2025-2026 Adopted Budget (Exhibit B Fee Schedule, 'SPRINKLER SYSTEM INSPECTIONS'), page 213: '3,001 to 8,000 sq. ft. — $384.80.'
$384.80
Sprinkler System Inspections (Orem City Fire Prevention Division) — 8,001 sq. ft. and aboveCity of Orem FY 2025-2026 Adopted Budget (Exhibit B Fee Schedule, 'SPRINKLER SYSTEM INSPECTIONS'), page 213: '8,001 sq. ft. and above — $384.00 + $0.01/sq. ft.'
$384.00 + $0.01/sq. ft.

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler System Permit permit actually take in Lindon?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Riser Flush

    Bacteria test does not fulfill this requirement, per Orem Fire Prevention's Contractor's Corner guidance for new-construction sprinkler systems.

  2. 2

    Above Grade / Rough Hydrostatic Pressure Test

    Verifies piping integrity above grade before concealment.

  3. 3

    Flow Sensors and Tampers

    Flow sensor and tamper switch verification.

  4. 4

    Sprinkler Final

    Performed in conjunction with the fire alarm final inspection — both the sprinkler and alarm contractors should be present, per Orem Fire Prevention's guidance.

See the full Lindon inspection guide — scheduling & re-inspection fees →

Tips

  • Lindon has no fire-sprinkler plan-review staff or fee schedule of its own — plans go directly to the Orem City Fire Prevention Division (fireprevention@orem.gov), which serves Orem, Lindon, and Vineyard, per Orem's official Fire Prevention & Inspections page.
  • Projects with 20 or more sprinkler heads require third-party code compliance review in addition to Orem Fire Prevention's own plan review, per Orem's Contractor's Corner guidance.
  • Schedule sprinkler inspections through Orem's online inspections system (orem.gov/inspections-and-permits/); the sprinkler final is performed jointly with the fire alarm final, so both contractors should be present.
  • Lindon's own Building Permit Fee (1997 UBC Table 1-A valuation) explicitly excludes fire sprinkler and fire alarm systems from the valuation — those systems are priced separately through this Fire Sprinkler and/or Fire Alarm Plan Review line item instead.

Frequently asked questions

Lindon requires a fire sprinkler system permit for: Automatic fire sprinkler (fire protection) system installation for new construction, or modification/extension of an existing system for a tenant improvement, in a building located in Lindon; Sprinkler system plans submitted directly to the Orem City Fire Prevention Division (fireprevention@orem.gov) for plan review — separate from, but coordinated with, the Lindon Building Department's own building-permit plan review; Third-party code compliance review is required for any new-construction or tenant-improvement sprinkler project involving 20 or more heads, per Orem Fire Prevention's published Contractor's Corner guidance; Complete set of fire sprinkler plans included with the Lindon Commercial Plan Submittal Checklist or Tenant Improvement Checklist submittal where a sprinkler system is part of the project scope, per this file's commercial-building-permit and commercial-tenant-improvement-permit entries; For a tenant improvement to a building with an existing fire suppression system, any modification to the existing floor plan requires updated coverage plans submitted to Orem Fire Prevention before work begins. If your project isn't listed, confirm with Lindon City Building Department (Community Development) at (801) 785-7687 before starting work.

No. Lindon's 2025-2026 Fee Schedule lists 'Fire Sprinkler and/or Fire Alarm Plan Review' as billed 'As per Orem City Fee Schedule,' because Lindon contracts fire-prevention plan review and inspection to the Orem City Fire Prevention Division. Orem's own FY 2025-2026 Adopted Budget prices sprinkler system inspections (plan check, hydro, flush, and final) at $260.00 under 3,000 sq. ft., $384.80 for 3,001-8,000 sq. ft., and $384.00 plus $0.01/sq. ft. above 8,001 sq. ft.

Lindon does not publish a plan-review timeline for this permit. Contact Lindon City Building Department (Community Development) at (801) 785-7687 for current turnaround.

You'll need: Fire Sprinkler System Plans; Building Permit Application. See the required-documents checklist on this page for details on each.

Lindon requires 4 inspection(s) for a fire sprinkler system permit, in order: Riser Flush, Above Grade / Rough Hydrostatic Pressure Test, Flow Sensors and Tampers, Sprinkler Final. Schedule each through Lindon City Building Department (Community Development) ((801) 785-7687).

Apply through Lindon City Building Department (Community Development) at 100 North State Street, Lindon, UT 84042. Phone: (801) 785-7687, email: building@lindon.gov. Official information: https://www.lindon.gov/251/Building-Inspection.

Lindon, Utah has adopted: 2021 International Residential Code (IRC), as amended by the State of Utah — adopted statewide under Utah Code Title 15A (State Construction and Fire Codes Act), § 15A-2-103. No Lindon-specific code-edition statement was found on lindon.gov's Building & Inspection page, Building Department Forms & Applications page, or in the current Fee Schedule; Lindon has not published a local amendment opting out of the statewide code, so the statutory statewide edition is used here rather than invented city-specific text.; 2024 International Building Code (IBC), as amended by the State of Utah — effective statewide July 1, 2026 per Utah Code § 15A-2-103 (2026 General Session update); no Lindon-specific IBC edition statement found on the city's own site.; 2023 National Electrical Code (NEC) — adopted statewide under Utah Code § 15A-2-103; no Lindon-specific NEC edition statement found on the city's own site.; 2015 International Plumbing Code (IPC), Table 403.1 — cited by name in Lindon City's own current Fee Schedule (Sewer Utility Fee and Water Utility Fee sections: 'Based on Table 403.1 in 2015 International Plumbing Code as currently adopted or as may be amended'), effective 07/01/2026 fee schedule. This is Lindon's own published reference to a specific plumbing-code edition/table used for utility base-rate sizing, distinct from the statewide construction-code IPC edition.; Other 2024 International Codes (IMC, IEBC, IECC) — adopted statewide alongside the 2024 IBC per Utah Code § 15A-2-103, effective July 1, 2026; not individually itemized by name on Lindon's own Building & Inspection page.. Local amendments apply — see the Lindon overview page for the full list.

The Orem City Fire Prevention Division, which serves Orem, Lindon, and Vineyard under Lindon's Fire/EMS and fire-prevention services contract with Orem City. Plans are submitted directly to fireprevention@orem.gov, separate from Lindon's own Building Department plan review of the underlying construction project.