Commercial Building Permit in Lindon, Utah

Required for new commercial and new multi-family construction in Lindon. Unlike residential's flat $500/$100 Building Permit Application Fee, Lindon bills the Building Permit Application Fee for 'New Multi-family and Commercial' as the Full Plan Review Fee, and the Plan Review Fee itself is billed at 65% of the permit fee for commercial (versus 25% for residential). The underlying Building Permit Fee remains valuation-based under the same 1997 Uniform Building Code Table 1-A used for residential construction.

Verified 2026-07-19 · Source

When you need this permit

  • New commercial or new multi-family construction
  • Digitally submitted plans via online application (required since 03/01/2021 per Lindon's Commercial Plan Submittal Checklist)
  • Site plan/title page drawn to scale showing lot dimensions, building footprint, north arrow, easements, building construction type, square footage and height, occupancy use, and occupant load
  • Foundation plan (structural, masonry, footing, piers, and grade beams)
  • Floor plan, exterior elevations, and structural cross sections with wet-signed engineer's stamp and design calculations
  • Prefabricated truss details (roof framing plan, truss ID sheet, manufacturer, gable bracing) where applicable
  • HVAC plan, plumbing layout (water/gas/DWV, gas line sizing calcs, grease/oil/sand interceptor sizing), and electrical plan (panel sizes, outlet/switching layout, energy compliance documents), each wet-signed
  • Complete set of fire sprinkler and alarm plans where applicable
  • ADA-compliant access features per current International Building Codes and ANSI 117; remodeled/improved areas require an accessible route of travel
  • Storm Water Pollution Prevention Plan (SWPPP) if land disturbance area or lot location requires it — verify with Public Works Storm Water Division, (801) 796-7954

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation-based (1997 UBC Table 1-A)Lindon City 2025-2026 Fee Schedule, 'Building Permit' line (last updated 6/03/2024 with Ordinance 2024-8-O): 'Building Permit: Determined using 1997 Uniform Building Code, Table 1-A. Fire sprinklers and fire alarm systems are not included in the Building Permit Fee.' This valuation method is not split by residential/commercial in the fee schedule — same line item applies to both.
Determined using 1997 Uniform Building Code, Table 1-A, applied to project valuation
Building Permit Application Fee (New Multi-family and Commercial)Lindon City 2025-2026 Fee Schedule, 'Building Permit Application Fee' (last updated 6/03/2024 with Ordinance 2024-8-O): 'New Multi-family and Commercial ... Full Plan Review Fee' — distinct from the flat $500 (new SFD/SFTH/duplex) and $100 (other residential) categories.
Full Plan Review Fee — no separate flat dollar amount is published; the application fee equals the Plan Review Fee amount (see below)
Plan Review Fee (Commercial)Lindon City 2025-2026 Fee Schedule, 'Plan Review Fee' (last updated 6/03/2024 with Ordinance 2024-8-O): 'Residential ... 25% of permit fee' / 'Commercial ... 65% of permit fee.'
65% of permit fee
Building Permit State FeeLindon City 2025-2026 Fee Schedule, 'Building Permit State Fee' line item — same statewide surcharge applied to all building permits.
1% of Building Permit Fee
Public Improvement Repair Assurance (refundable, New Multi-family and Commercial)Lindon City 2025-2026 Fee Schedule, 'Public Improvement Repair Assurance' (last updated 6/03/2024 with Ordinance 2024-8-O): 'New Multi-family and Commercial ... As determined by the City Engineer' — distinct from the fixed $5,000/$2,500 residential bond amounts.
As determined by the City Engineer
Additional Plan Review Fee, as neededLindon City 2025-2026 Fee Schedule, 'Plan Review Fee' section, 'Additional Plan Review Fee, as needed' line item.
$85/hour (1-hour minimum)
Reinspection FeeLindon City 2025-2026 Fee Schedule, 'Reinspection Fee' (added 6/03/2024 with Ordinance 2024-8-O).
$85/hour (1-hour minimum)

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Lindon?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footing Inspection

    After footings are dug, formed, and steel is in place, prior to pouring concrete, per standard IBC inspection sequence enforced by the Building Department, (801) 785-7687.

  2. 2

    Framing Inspection (Structural, Rough Electrical/Plumbing/Mechanical)

    After framing, structural connections, and rough MEP are in place, prior to enclosing walls or ceilings.

  3. 3

    Fire Sprinkler and/or Fire Alarm Rough-In

    Required where a fire sprinkler or alarm system is part of the project scope, per the Commercial Plan Submittal Checklist.

  4. 4

    Insulation and Energy Compliance Inspection

    After insulation is installed, prior to drywall/finish, verifying energy compliance documentation submitted with plans.

  5. 5

    Final Building Inspection

    Building Department final sign-off required before occupancy.

See the full Lindon inspection guide — scheduling & re-inspection fees →

Tips

  • New multi-family and commercial construction pays a Plan Review Fee of 65% of the permit fee — well above the 25% rate applied to residential construction — per Lindon's 2025-2026 Fee Schedule.
  • The Building Permit Application Fee for new multi-family/commercial construction isn't a flat dollar figure like residential's $500 SFD fee — it's billed as the 'Full Plan Review Fee' amount, so budget for it as roughly 65% of the eventual Building Permit Fee.
  • The Public Improvement Repair Assurance bond for new multi-family/commercial projects is 'As determined by the City Engineer' rather than a fixed dollar amount like the $5,000/$2,500 residential bonds — confirm the amount with the Building Department before budgeting.

Frequently asked questions

Lindon requires a commercial building permit for: New commercial or new multi-family construction; Digitally submitted plans via online application (required since 03/01/2021 per Lindon's Commercial Plan Submittal Checklist); Site plan/title page drawn to scale showing lot dimensions, building footprint, north arrow, easements, building construction type, square footage and height, occupancy use, and occupant load; Foundation plan (structural, masonry, footing, piers, and grade beams); Floor plan, exterior elevations, and structural cross sections with wet-signed engineer's stamp and design calculations; Prefabricated truss details (roof framing plan, truss ID sheet, manufacturer, gable bracing) where applicable; HVAC plan, plumbing layout (water/gas/DWV, gas line sizing calcs, grease/oil/sand interceptor sizing), and electrical plan (panel sizes, outlet/switching layout, energy compliance documents), each wet-signed; Complete set of fire sprinkler and alarm plans where applicable; ADA-compliant access features per current International Building Codes and ANSI 117; remodeled/improved areas require an accessible route of travel; Storm Water Pollution Prevention Plan (SWPPP) if land disturbance area or lot location requires it — verify with Public Works Storm Water Division, (801) 796-7954. If your project isn't listed, confirm with Lindon City Building Department (Community Development) at (801) 785-7687 before starting work.

Lindon does not publish a flat commercial building-permit fee. The Building Permit Fee is valuation-based under 1997 Uniform Building Code Table 1-A (the same method used for residential permits), the Building Permit Application Fee for new multi-family and commercial construction equals the Full Plan Review Fee, and the Plan Review Fee itself is billed at 65% of the permit fee for commercial projects — versus 25% for residential — per Lindon's 2025-2026 Fee Schedule.

No. Lindon does not publish a commercial-specific plan-review turnaround time. Utah Code § 10-20-909's 14-business-day plan-review requirement (17 business days total including the 3-day screening period) is scoped by statute to one- and two-family dwellings, townhomes, and other residential structures — not commercial or multi-family buildings — so that figure does not apply here.

You'll need: Commercial Plan Submittal Checklist; Building Permit Application. Depending on your project, Lindon may also ask for: Storm Water Pollution Prevention Plan (SWPPP); Complete Set of Fire Sprinkler Plans. See the required-documents checklist on this page for details on each.

Lindon requires 5 inspection(s) for a commercial building permit, in order: Foundation / Footing Inspection, Framing Inspection (Structural, Rough Electrical/Plumbing/Mechanical), Fire Sprinkler and/or Fire Alarm Rough-In, Insulation and Energy Compliance Inspection, Final Building Inspection. Schedule each through Lindon City Building Department (Community Development) ((801) 785-7687).

Apply through Lindon City Building Department (Community Development) at 100 North State Street, Lindon, UT 84042. Phone: (801) 785-7687, email: building@lindon.gov. Official information: https://www.lindon.gov/251/Building-Inspection.

Lindon, Utah has adopted: 2021 International Residential Code (IRC), as amended by the State of Utah — adopted statewide under Utah Code Title 15A (State Construction and Fire Codes Act), § 15A-2-103. No Lindon-specific code-edition statement was found on lindon.gov's Building & Inspection page, Building Department Forms & Applications page, or in the current Fee Schedule; Lindon has not published a local amendment opting out of the statewide code, so the statutory statewide edition is used here rather than invented city-specific text.; 2024 International Building Code (IBC), as amended by the State of Utah — effective statewide July 1, 2026 per Utah Code § 15A-2-103 (2026 General Session update); no Lindon-specific IBC edition statement found on the city's own site.; 2023 National Electrical Code (NEC) — adopted statewide under Utah Code § 15A-2-103; no Lindon-specific NEC edition statement found on the city's own site.; 2015 International Plumbing Code (IPC), Table 403.1 — cited by name in Lindon City's own current Fee Schedule (Sewer Utility Fee and Water Utility Fee sections: 'Based on Table 403.1 in 2015 International Plumbing Code as currently adopted or as may be amended'), effective 07/01/2026 fee schedule. This is Lindon's own published reference to a specific plumbing-code edition/table used for utility base-rate sizing, distinct from the statewide construction-code IPC edition.; Other 2024 International Codes (IMC, IEBC, IECC) — adopted statewide alongside the 2024 IBC per Utah Code § 15A-2-103, effective July 1, 2026; not individually itemized by name on Lindon's own Building & Inspection page.. Local amendments apply — see the Lindon overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lindon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Lindon.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.