Residential Building Permit (New SFD, Townhome, Duplex, ADU) in Lindon, Utah
Required for new single-family dwellings, single-family townhomes, duplexes, and detached accessory dwelling units in Lindon. The Building Permit fee itself is valuation-based (1997 Uniform Building Code, Table 1-A), with valuation determined from the prior February's ICC Building Valuation Data (single-family dwellings, townhomes, and duplexes valued at 95 percent); fire sprinklers and fire alarm systems are excluded from the valuation.
Verified 2026-07-08 · Source
When you need this permit
- New single-family dwelling (SFD), single-family townhome (SFTH), detached accessory dwelling unit (ADU), or duplex construction
- Digitally submitted plans via online application (required since 03/01/2021 per Lindon's Residential Plan Submittal Checklist)
- Site plan drawn to engineering scale on 8.5" x 11" paper showing setbacks, elevations, easements, and existing structures
- Building plans with wet-signed engineer's stamp where required, foundation/framing/roof details, and a Model Energy Code Compliance Report
- Storm Water Pollution Prevention Plan (SWPPP) if land disturbance area or lot location requires it — verify with Public Works Storm Water Division, (801) 796-7954
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Sediment Control
Must pass prior to footing inspection. Administered by Public Works. Per Lindon's official Residential Single-Family Dwelling Building and Site Inspections checklist.
- 2
Building Clearance
After survey property pins are in place; may be completed with the footing inspection. Building Department.
- 3
Temporary Power
Request service from Rocky Mountain Power, (888) 221-7070.
- 4
Footing Inspection
After footings are dug, formed, and steel is in place, prior to pouring concrete. Soil report must be submitted to the Building Department 24 hours prior to inspection.
- 5
Foundation Inspection
After forms and steel are in place, prior to pouring concrete.
- 6
Foundation Drain and Waterproofing
Prior to backfilling.
- 7
Under-Slab Heating and Plumbing / Rebar (suspended slab) / Shear Inspection
Shear inspection can be completed before or with the 4-way rough inspection.
- 8
4-Way Rough Inspection (Framing, Electrical, Mechanical, Plumbing)
May be combined into a single 4-way inspection, per Lindon's official inspection checklist.
- 9
Insulation and Weather Barrier
Weather barrier inspection required prior to installing exterior finishes; stucco lath must be installed with tears and penetrations sealed.
- 10
Drywall Nailing (fire-rated assemblies), Permanent Power, Gas Line/Pressure Test, Gas Meter Mechanical
Permanent power requires separate inspection by Rocky Mountain Power for all underground service. Gas meter requires two inspections (line/pressure test, then mechanical).
- 11
Final Building Inspection
Building Department final sign-off. Public Works also finals Water Service, Sewer Lateral, Drive Approach and Sidewalk, Pressurized Irrigation, Land Drain, and SWPPP as applicable.
See the full Lindon inspection guide — scheduling & re-inspection fees →
Tips
- All plans have been required to be submitted digitally via online application since March 1, 2021, per Lindon's Residential Plan Submittal Checklist.
- The $100 Building Permit Application Deposit is applied toward final building permit fees; if the application is cancelled, the deposit may be refunded depending on how much review work Lindon City has already completed.
- Every required inspection must be scheduled a minimum of 24 hours in advance, per Lindon's official Residential Single-Family Dwelling Building and Site Inspections checklist.
- Temporary and permanent power inspections require direct coordination with Rocky Mountain Power, (888) 221-7070 — this is separate from the city's own inspection line.
- New SFD, SFTH, detached ADU, and duplex applications pay a $500 Building Permit Application Fee; nearly all other residential permit types (pools, additions, detached garages, sheds, retaining walls, solar) pay a flat $100 application fee instead.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lindon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Lindon
Residential Building Permit (New SFD, Townhome, Duplex, ADU) in other cities
Compare residential building permit (new sfd, townhome, duplex, adu) fees across Utah →
Look up this fee in a different city →
Now live
Build your Lindon project checklist
Describe your project once and get every permit, document, and fee it triggers in Lindon — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →