Fire Alarm System Permit — Lindon, Utah · Requirements sheet
Verified 2026-07-21 · Source: https://www.lindon.gov/DocumentCenter/View/199
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Fire Alarm System Permit in Lindon, Utah
Required for installation of a new fire alarm system, or modification/extension of an existing system, for new construction or a tenant improvement in Lindon. As with fire sprinkler systems, Lindon has no fire-prevention plan-review staff or fee schedule of its own for fire alarms: Lindon's 2025-2026 Fee Schedule prices its 'Fire Sprinkler and/or Fire Alarm Plan Review' line item 'As per Orem City Fee Schedule,' reflecting Lindon's partnership with the Orem City Fire Prevention Division (which serves Orem, Lindon, and Vineyard) for plan review, permits, and inspections. Orem's own currently-adopted FY 2025-2026 Adopted Budget Fee Schedule prices Fire Alarm System Inspections (office plan review, 24-hour test, and final inspection) by project square footage — the figure Lindon's own schedule points to.
Verified 2026-07-21 · Source
When you need this permit
- New fire alarm system installation, or modification/extension of coverage to additional floors, for new construction or a tenant improvement in a building located in Lindon
- Fire alarm system plans submitted directly to the Orem City Fire Prevention Division (fireprevention@orem.gov) for plan review, separate from — but coordinated with — the Lindon Building Department's own building-permit plan review
- Third-party code compliance review is required for any new-construction or tenant-improvement alarm project involving 5 or more devices, per Orem Fire Prevention's published Contractor's Corner guidance
- Complete set of fire alarm plans included with the Lindon Commercial Plan Submittal Checklist or Tenant Improvement Checklist submittal where an alarm system is part of the project scope, per this file's commercial-building-permit and commercial-tenant-improvement-permit entries
- For a tenant improvement to a building with an existing fire alarm system, any modification to the existing floor plan requires updated coverage plans submitted to Orem Fire Prevention before work begins
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
24-Hour Battery Test
Battery backup test for the fire alarm system panel.
- 2
Notifier Activation, Flow Switch Test, Tamper Test, Smoke Detector Test
Device-level activation and function testing, per Orem Fire Prevention's Contractor's Corner guidance for new-construction alarm systems.
- 3
Address Verification and Signal Transmission Test
Confirms the monitored alarm signal reaches Metro Dispatch, (801) 854-6211.
- 4
Alarm Final
Performed in conjunction with the sprinkler final inspection where both systems are present — both the alarm and sprinkler contractors should be present, per Orem Fire Prevention's guidance.
See the full Lindon inspection guide — scheduling & re-inspection fees →
Tips
- Lindon has no fire-alarm plan-review staff or fee schedule of its own — plans go directly to the Orem City Fire Prevention Division (fireprevention@orem.gov), which serves Orem, Lindon, and Vineyard, per Orem's official Fire Prevention & Inspections page.
- Projects with 5 or more alarm devices require third-party code compliance review in addition to Orem Fire Prevention's own plan review, per Orem's Contractor's Corner guidance.
- The signal transmission test verifies monitoring through Metro Dispatch, (801) 854-6211 — schedule inspections through Orem's online inspections system (orem.gov/inspections-and-permits/).
- Do not confuse this fire alarm system permit with Lindon's separate $25.00 police-administered 'Alarm Permit' (Lindon Fee Schedule, POLICE section) — that is a burglar/security-alarm registration and false-alarm-response fee, unrelated to a building's fire alarm system.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-21.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lindon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Lindon
Fire Alarm System Permit in other cities
Compare fire alarm system permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Lindon project checklist
Describe your project once and get every permit, document, and fee it triggers in Lindon — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →