Commercial Tenant Improvement / Tenant Finish Permit — Lindon, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://www.lindon.gov/DocumentCenter/View/199
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Tenant Improvement / Tenant Finish Permit in Lindon, Utah
Required for tenant improvement / tenant finish work inside existing commercial buildings in Lindon — interior remodels, buildouts, and occupancy changes for a new or existing tenant space. Lindon's fee schedule bills the Building Permit Application Fee for 'Tenant Improvements' as its own Full Plan Review Fee line item (a separate line from, but the same formula as, new commercial construction), and requires the building owner's signed acknowledgment whenever the applicant is not the building's owner of record.
Verified 2026-07-19 · Source
When you need this permit
- Tenant improvement or tenant finish work in an existing commercial building
- Complete sets of digital plans, wet-stamped and wet-signed by the architect or engineer
- Cover sheet listing allowable floor area, occupancy group (per IBC), type of construction (per IBC), occupant load (per IBC Chapter 10), and sanitation facilities (per IPC and IBC)
- Dimensioned floor plan identifying all occupied spaces, exits (number, width, distance, direction, hardware), corridors, fixed elements of construction, and fire-resistive occupancy separations
- Wall section showing stud size, height, spacing, insulation, wall finish, and structural connections
- Plumbing plan with isometric/schematic (water, gas, waste) and material types
- Mechanical plan with isometric/schematic, duct sizing, return-air duct and fire-damper locations, combustion air method/amount, HVAC unit locations, and kitchen hood details where applicable
- Electrical plan with one-line diagram, panel schedules, outlet/fixture/equipment locations, hazardous electrical locations, and complete load calculations
- Energy compliance calculations (ComCheck or ASHRAE 90.1) as required by Utah State Law
- Sprinkler plan when required by code, and T-bar ceiling details where applicable
- Commercial Building Owner Acknowledgment for a Tenant Improvement when the applicant is not the building owner
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Framing / Structural Rough-In
Walls, partitions, and ceiling-support framing verified against submitted plans before close-in, per standard commercial inspection sequence enforced by the Building Department, (801) 785-7687.
- 2
Plumbing, Mechanical, and Electrical Rough-In
Rough plumbing, mechanical (ductwork, combustion air), and electrical (panel, wiring, outlets) verified prior to enclosing walls or ceilings.
- 3
Fire Sprinkler and/or Fire Alarm Rough-In
Required when a sprinkler or alarm system is part of the project scope, per the Tenant Improvement Checklist's 'additional plans' section.
- 4
Final Building Inspection
Building Department final sign-off required before occupancy of the completed tenant space.
See the full Lindon inspection guide — scheduling & re-inspection fees →
Tips
- Lindon's Tenant Improvement Building Permit Application Fee is its own fee-schedule line (billed as the Full Plan Review Fee) — distinct from, but using the same formula as, the 'New Multi-family and Commercial' line used for ground-up construction.
- A Commercial Building Owner Acknowledgment for a Tenant Improvement is required whenever the applicant (tenant or contractor) is not the building's owner of record — confirm with the Building Department, (801) 785-7687, if unsure whether it applies to your project.
- No separate Tenant Improvement percentage is published for the Plan Review Fee — Lindon's fee schedule lists only 'Residential' (25%) and 'Commercial' (65%) tiers, so tenant improvements are billed at the Commercial rate.
- Lindon City has no standalone Change of Use or Change of Occupancy permit. Per the city's own Business License FAQ, every business license application — new location or otherwise — is routed to the Planning Department for zoning/signage compliance and to the Building Department for ordinance compliance and an on-site inspection (10-14 days total), so an occupancy/use change for an existing building is checked through the standard business-license and building-permit process rather than a distinct fee-bearing permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lindon building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Lindon.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Lindon
Commercial Tenant Improvement / Tenant Finish Permit in other cities
Compare commercial tenant improvement / tenant finish permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your Lindon project checklist
Describe your project once and get every permit, document, and fee it triggers in Lindon — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →