Residential Building Permit (New Single-Family Home) — Farr West, Utah · Requirements sheet
Verified 2026-07-08 · Source: https://farrwestcity.net/building-permit-fees.html
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Single-Family Home) in Farr West, Utah
Required for new single-family residential construction in Farr West, regulated under the adopted IBC/IRC. Farr West's building and plan-check fees are valuation-based and cannot be finalized until the Building Inspector completes plan review; the city separately publishes a fixed set of impact/utility fees that apply to every new home regardless of valuation. Rooftop solar-PV installations are covered by this same general Building Permit — Farr West's official Building Permit Required page lists 'Solar' as one of the project types requiring this permit, with no separate solar-specific application, checklist, or fee published on farrwestcity.net as of 2026-07-19 (farrwestcity.net/building-permit-required.html). Farr West's official Building Permit Required page lists the project types needing a permit (new homes, remodels/additions, furnace/AC replacement, solar, pools, accessory buildings, decks, reroofs, plus 'other projects determined by building inspector') and its Building Permit Fees page has no distinct EV charger/EVSE line item as of 2026-07-19 — a standalone home EV charger installation would fall under the same general Building Permit as other electrical work, at the Building Inspector's determination.
Verified 2026-07-08 · Source
When you need this permit
- New single-family residential construction
- One set of wet-stamped engineered building plans (11x17 preferred)
- Copy of the site plan
- RESCheck energy compliance report
- Completed SWPPP (Storm Water Pollution Prevention Plan) packet, including a UPDES permit number obtained from the Utah Division of Water Quality (secure.utah.gov/stormwater)
- Site plan approval must be obtained prior to building permit submittal for any commercial and/or residential development — site plan applications are submitted separately to the main office, not through the building permit portal
- Proof of payment for both culinary water (Bona Vista Water Improvement District) and secondary water (Pineview Water Systems or Mountain View Irrigation, depending on service area) required before inspections will be scheduled
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Sewer & Water
Required inspection per Farr West's official Building Inspection Information sheet. Contact (801) 731-4187 at least 24 hours in advance to schedule; no Friday inspections.
- 2
Footing/Setbacks
Required inspection per the Building Inspection Information sheet.
- 3
Foundation
Required inspection per the Building Inspection Information sheet.
- 4
Underground Plumbing
Required inspection per the Building Inspection Information sheet.
- 5
4-Way (Framing, Plumbing, Electrical & HVAC) and Gas Clearance
Combined trade inspection plus gas clearance, required per the Building Inspection Information sheet.
- 6
Permanent Power
Required inspection per the Building Inspection Information sheet.
- 7
Final
Final inspection; list of required inspections 'may not be all inclusive for all projects' per the city's own Building Inspection Information sheet. Inspection reports are emailed to the general contractor of record immediately after each inspection.
See the full Farr West inspection guide — scheduling & re-inspection fees →
Tips
- Farr West's Building Official and Combination Inspector is Nate Carver (801-731-4187, nate@farrwestcity.gov) — a single point of contact for both plan review approval and field inspections.
- Inspections run Monday–Thursday 7:30 AM–3:30 PM only; there are NO Friday inspections, and 24 hours' notice is required — plan scheduling accordingly.
- Permits are submitted online via the city's iworq portal (farrwest.portal.iworq.net/portalhome/farrwest); hardcopy drop-off at City Hall is allowed but incurs additional fees.
- Site plan approval is a separate process that must be completed BEFORE building permit submittal — site plan applications cannot be submitted through the online building permit portal and must go to the main office with the appropriate fees.
- Both culinary water (Bona Vista Water Improvement District, 801-621-0474) and secondary water (Pineview Water Systems, 801-621-6555, or Mountain View Irrigation, 801-731-7252, depending on service area) impact fees must be paid directly to those districts, and proof of payment for BOTH is required before any inspections will be scheduled — this is independent of the city's own building permit fee bundle.
- The city's own estimate for total new-home permit costs (building/plan-check fee plus all fixed impact fees) is $10,000-$15,000, but the building and plan-check fee component itself cannot be quoted until the Building Inspector completes plan review.
- Solar panel installations do not have their own permit type in Farr West — 'Solar' is listed alongside remodels, additions, and furnace/AC replacements as a project type requiring this same general Building Permit; budget the same valuation-based building/plan-check fee structure rather than expecting a flat solar fee.
- Farr West's Building Permit Required and Building Permit Fees pages (farrwestcity.net, checked 2026-07-19) list no EV charger/EVSE-specific permit category or fee — electrical work generally falls under the same valuation-based Building Permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Farr West building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Farr West
Residential Building Permit (New Single-Family Home) in other cities
Compare residential building permit (new single-family home) fees across Utah →
Look up this fee in a different city →
Now live
Build your Farr West project checklist
Describe your project once and get every permit, document, and fee it triggers in Farr West — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →