EV Charger / EVSE Permit in Parker, Arizona

The Town of Parker does not publish a dedicated EV charger/EVSE permit. Installation of a dedicated EV charging circuit is checked as 'Electrical' on the Town's single combined Permit Application and billed under the Town's Single-Trade Utility Permit fee structure, governed by the 2017 NEC as adopted by the Town (§ 9-1-1). Work valued up to $5,000 is billed a flat utility rate; work at $5,001 or more (e.g., a service upgrade bundled with the charger) is billed the full valuation-based Building Permit Fee instead.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit required for the EV charging circuit, checked as 'Electrical' on the Town's combined Permit Application
  • Governed by the 2017 NEC as adopted by the Town of Parker (§ 9-1-1)
  • Single-trade electrical work up to $5,000 valuation is billed the flat Utility permit fee; work at $5,001 or more is billed the full Building Permit Fee, Per Valuation (Schedule 7.8)
  • Contractors must list contractor name, Town of Parker license number, ROC license number, and phone on the Permit Application Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Single-Trade Utility Permit (Electrical), up to $5,000 valuationTown of Parker Schedule of Fees and Rates, effective 08/01/2025, Schedule 7.11 (Utilities) — the mechanism a standard EV charger circuit installation is billed under; no EV-specific line item exists
$50.00
Single-Trade Utility Permit (Electrical), $5,001 valuation or moreTown of Parker Schedule of Fees and Rates, effective 08/01/2025, Schedule 7.11 — applies if the EVSE installation involves a service upgrade or other work pushing valuation over $5,000
Building Permit Fee, Per Valuation (Schedule 7.8)

Review timeline

Plan reviewTypical estimate — confirm current times with the Parker building department
~5–7 business days

How long did your EV Charger / EVSE Permit permit actually take in Parker?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Circuit wiring, box placement, and panel connections before walls are closed

  2. 2

    Final

    EVSE installed and panel labeled, per 2017 NEC as adopted by the Town

See the full Parker inspection guide — scheduling & re-inspection fees →

Tips

  • Parker has no dedicated EV charger permit — check 'Electrical' on the Town's single combined Permit Application form.
  • The $5,000 valuation threshold is the key fee break point: below it, a flat $50 utility fee applies; at or above it, the work is billed at full Building Permit valuation rates instead.

Frequently asked questions

Parker requires an ev charger / evse permit for: Electrical permit required for the EV charging circuit, checked as 'Electrical' on the Town's combined Permit Application; Governed by the 2017 NEC as adopted by the Town of Parker (§ 9-1-1); Single-trade electrical work up to $5,000 valuation is billed the flat Utility permit fee; work at $5,001 or more is billed the full Building Permit Fee, Per Valuation (Schedule 7.8); Contractors must list contractor name, Town of Parker license number, ROC license number, and phone on the Permit Application. If your project isn't listed, confirm with Town of Parker Community Development Department — Building Division at 928-669-9265 before starting work.

No. There is no dedicated EV charger permit type. An EV charging circuit is permitted as standard electrical work under the Town's combined Permit Application, billed at a flat $50 Single-Trade Utility Permit fee for work up to $5,000 in valuation, per the Town of Parker Schedule of Fees and Rates (Schedule 7.11).

Plan review for an ev charger / evse permit in Parker typically runs 5–7 business days. This is an estimate, not a published figure — confirm current review times with Town of Parker Community Development Department — Building Division at 928-669-9265.

You'll need: Permit Application. See the required-documents checklist on this page for details on each.

Parker requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In, Final. Schedule each through Town of Parker Community Development Department — Building Division (928-669-9265).

Apply through Town of Parker Community Development Department — Building Division at 1314 11th Street, Parker, AZ 85344. Phone: 928-669-9265, email: topbuilding@townofparkeraz.us. Office hours: Monday - Thursday, 7:00 a.m. - 6:00 p.m. (closed Fridays and holidays). Building/permit questions and inspection scheduling: 928-669-9265 ext. 1019 or topbuilding@townofparkeraz.us; Planning & Zoning: comdev@townofparkeraz.us; Fax 928-669-5247. Permit Applications are submitted directly to the Building Division (in person or by mailing/emailing the completed Permit Application form plus two sets of construction plans) — the Town does NOT use an online eTRAKiT/EnerGov self-service portal for AZ permitting (eTRAKiT and prkc-trk.aspgov.com belong to the unrelated Parker, COLORADO municipal government, parkerco.gov, and must not be confused with this jurisdiction).. Official information: https://www.townofparkeraz.com/page/community-development.

Parker, Arizona has adopted: Arizona has NO statewide mandatory building code for general construction — code adoption is a per-jurisdiction (town/city/county) authority under state enabling statutes (A.R.S. Title 9 for municipalities). The Town of Parker independently adopts and administers its own construction codes through its Community Development Department / Building Division; it does NOT defer to La Paz County for permitting within incorporated town limits. La Paz County separately runs its own Building and Safety Department for unincorporated areas of the county — the two are distinct code-administration regimes sharing the same 1112 Joshua Ave / Parker, AZ area but serving different jurisdictions. Source: Town of Parker Code of Ordinances, Title 9 (Building Regulations), Chapter 1 (Building Code), via American Legal Publishing code library (codelibrary.amlegal.com/codes/parkeraz); La Paz County 'Building, Safety & Permits' page (lapaz.gov/589).; International Building Code (IBC), 2018 edition, adopted by reference (Town of Parker Code of Ordinances § 9-1-1), including Appendices C, I, and J. Source: Town of Parker Code of Ordinances § 9-1-1 (amlegal.com), as amended by Ordinance 02-2025, effective 8-5-2025.; International Residential Code (IRC), 2018 edition, adopted by reference (§ 9-1-1), including Appendices A, B, C, D, G, H, K, N, O, P, Q, and S. Source: Town of Parker Code of Ordinances § 9-1-1 (amlegal.com), as amended by Ordinance 02-2025, effective 8-5-2025.; National Electrical Code (NEC), 2017 edition, adopted by reference (§ 9-1-1). Source: Town of Parker Code of Ordinances § 9-1-1 (amlegal.com), as amended by Ordinance 02-2025, effective 8-5-2025.; International Mechanical Code (IMC), 2018 edition, adopted by reference (§ 9-1-1), including Appendix A. Source: Town of Parker Code of Ordinances § 9-1-1 (amlegal.com), as amended by Ordinance 02-2025, effective 8-5-2025.; International Plumbing Code (IPC), 2018 edition, adopted by reference (§ 9-1-1), including Appendices C and E. Source: Town of Parker Code of Ordinances § 9-1-1 (amlegal.com), as amended by Ordinance 02-2025, effective 8-5-2025.; International Fire Code (IFC), 2018 edition, adopted by reference (§ 9-1-1), including Appendices B through G and I; administered by the Colorado River Fire Department / Town Fire Marshal function for plan review (a $110 Fire Plan Review fee applies per the Town's Schedule of Fees and Rates, Schedule 7.3). Source: Town of Parker Code of Ordinances § 9-1-1 (amlegal.com); Town of Parker Schedule of Fees and Rates, effective 08/01/2025.; International Existing Building Code (IEBC), 2018 edition, adopted by reference (§ 9-1-1). Source: Town of Parker Code of Ordinances § 9-1-1 (amlegal.com), as amended by Ordinance 02-2025, effective 8-5-2025.; International Fuel Gas Code (IFGC), 2018 edition, adopted by reference (§ 9-1-1), including Appendices A and B. Source: Town of Parker Code of Ordinances § 9-1-1 (amlegal.com), as amended by Ordinance 02-2025, effective 8-5-2025.; International Property Maintenance Code, 2012 edition, adopted by reference (§ 9-1-1), including Appendix A. Source: Town of Parker Code of Ordinances § 9-1-1 (amlegal.com), as amended by Ordinance 02-2025, effective 8-5-2025.; International Swimming Pool and Spa Code, 2018 edition, adopted by reference (§ 9-1-1). Source: Town of Parker Code of Ordinances § 9-1-1 (amlegal.com), as amended by Ordinance 02-2025, effective 8-5-2025.; Ordinance 02-2025 (effective 8-5-2025) restructured Title 9 by repealing the Town's previously separate per-trade code chapters (e.g., the standalone Chapter 2 Plumbing Code, confirmed repealed: '(Rep. by Ord. 02-2025, 8-5-2025)') and consolidating all ten adopted model codes into a single Chapter 1 (Building Code) adoption-by-reference section (§ 9-1-1), with local amendments carried in the companion § 9-1-2 (Technical Code Amendments). Source: Town of Parker Code of Ordinances, Title 9, Chapter 2 (repealed) and Chapter 1 §§ 9-1-1/9-1-2 (amlegal.com).; Manufactured homes, modular homes, and park models are subject to a Town of Parker building permit for placement (flat $300.00 fee per unit type, plus a 15% plan review fee), per the Town's Schedule of Fees and Rates, Schedule 7.4. Source: Town of Parker Schedule of Fees and Rates, effective 08/01/2025, Schedule 7.4.. Local amendments apply — see the Parker overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Parker building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.