EV Charger / EVSE Permit — Kingman, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.cityofkingman.gov/home/showdocument?id=9336&t=638868796061530000
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Kingman, Arizona
Electric vehicle charging equipment (EVSE) installation in the City of Kingman is billed under the City's general valuation-based Building Permit Fee — the Development Services Fee Schedule (effective July 1, 2025) has no distinct EV-charger/EVSE line item, unlike its dedicated $220 flat fee for solar energy device systems (per A.R.S. § 9-468). Kingman does not publish a standalone 'Electrical Permit' fee table at all; electrical/trade work of this kind is captured within the graduated Building Permit Fee table (Kingman Municipal Code Ch. 5, Art. I, Sec. 5-2) applied to the applicant-estimated construction valuation, the same mechanism the fee schedule specifies for remodel construction, pools, spas, and signs.
Verified 2026-07-20 · Source
When you need this permit
- Building permit required for EVSE/EV charger installation, submitted through the same permitting channel as other electrical/remodel work (transitioning to the SmartGov portal beginning April 15, 2026)
- No dedicated EVSE application or fee-schedule line item exists; the project valuation is estimated by the permit applicant (per the fee schedule's footnote d, which lists remodel construction, pools, spas, and signs as applicant-estimated valuation categories) and run through the general graduated Building Permit Fee table
- Electrical work must comply with the 2017 NEC as adopted by the City of Kingman with local amendments
- A licensed Arizona electrical contractor is required unless the work qualifies for the A.R.S. § 32-1121(A)(5) owner-builder exemption on a personal owner-occupied residence Owner-builder
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final
EVSE circuit, breaker/disconnect, and NEC Article 625 compliance verified against approved plans
See the full Kingman inspection guide — scheduling & re-inspection fees →
Tips
- Kingman prices EV charger installation the same way it prices a remodel, pool, spa, or sign — the applicant estimates the project's construction valuation, which is then run through the general graduated Building Permit Fee table, rather than paying a flat fee like the $220 solar device fee.
- The City's fee schedule PDF sits behind an Akamai edge WAF that returns HTTP 403 to direct automated fetches; the fee table content above was retrieved via a text-extraction proxy in this session, not assumed from memory.
- Confirm with Development Services (928-753-8130) whether your specific EVSE scope (e.g., a simple circuit addition vs. a service panel upgrade) changes the estimated valuation used for the fee calculation.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kingman building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Kingman
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Arizona →
Look up this fee in a different city →