EV Charger / EVSE Permit in Kingman, Arizona

Electric vehicle charging equipment (EVSE) installation in the City of Kingman is billed under the City's general valuation-based Building Permit Fee — the Development Services Fee Schedule (effective July 1, 2025) has no distinct EV-charger/EVSE line item, unlike its dedicated $220 flat fee for solar energy device systems (per A.R.S. § 9-468). Kingman does not publish a standalone 'Electrical Permit' fee table at all; electrical/trade work of this kind is captured within the graduated Building Permit Fee table (Kingman Municipal Code Ch. 5, Art. I, Sec. 5-2) applied to the applicant-estimated construction valuation, the same mechanism the fee schedule specifies for remodel construction, pools, spas, and signs.

Verified 2026-07-20 · Source

When you need this permit

  • Building permit required for EVSE/EV charger installation, submitted through the same permitting channel as other electrical/remodel work (transitioning to the SmartGov portal beginning April 15, 2026)
  • No dedicated EVSE application or fee-schedule line item exists; the project valuation is estimated by the permit applicant (per the fee schedule's footnote d, which lists remodel construction, pools, spas, and signs as applicant-estimated valuation categories) and run through the general graduated Building Permit Fee table
  • Electrical work must comply with the 2017 NEC as adopted by the City of Kingman with local amendments
  • A licensed Arizona electrical contractor is required unless the work qualifies for the A.R.S. § 32-1121(A)(5) owner-builder exemption on a personal owner-occupied residence Owner-builder

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on Applicant-Estimated ValuationCity of Kingman Development Services Fee Schedule, effective July 1, 2025 — confirmed directly (re-fetched 2026-07-20 via a text-extraction proxy after the live PDF endpoint returned HTTP 403 from Kingman's Akamai WAF to both curl and WebFetch) that the 'Special Permits, Other Inspection Fees, and Appeals' table lists Manufactured Home, Factory-Built Building, and Solar energy device systems as the only flat-fee special permit categories — EV chargers/EVSE are not among them, so the general valuation-based fee table applies, using an applicant-estimated valuation the same way the schedule handles remodels, pools, spas, and signs
$24.68 ($1-$500) up to $5,889.19 + $3.83 per additional $1,000 above $1,000,000, per the same graduated Building Permit Fee table used for all other valuation-based permits
Technology FeeCity of Kingman Development Services Fee Schedule, effective July 1, 2025; applied to all permit applications
0.25% of all Permit Fees

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Kingman?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    EVSE circuit, breaker/disconnect, and NEC Article 625 compliance verified against approved plans

See the full Kingman inspection guide — scheduling & re-inspection fees →

Tips

  • Kingman prices EV charger installation the same way it prices a remodel, pool, spa, or sign — the applicant estimates the project's construction valuation, which is then run through the general graduated Building Permit Fee table, rather than paying a flat fee like the $220 solar device fee.
  • The City's fee schedule PDF sits behind an Akamai edge WAF that returns HTTP 403 to direct automated fetches; the fee table content above was retrieved via a text-extraction proxy in this session, not assumed from memory.
  • Confirm with Development Services (928-753-8130) whether your specific EVSE scope (e.g., a simple circuit addition vs. a service panel upgrade) changes the estimated valuation used for the fee calculation.

Frequently asked questions

Kingman requires an ev charger / evse permit for: Building permit required for EVSE/EV charger installation, submitted through the same permitting channel as other electrical/remodel work (transitioning to the SmartGov portal beginning April 15, 2026); No dedicated EVSE application or fee-schedule line item exists; the project valuation is estimated by the permit applicant (per the fee schedule's footnote d, which lists remodel construction, pools, spas, and signs as applicant-estimated valuation categories) and run through the general graduated Building Permit Fee table; Electrical work must comply with the 2017 NEC as adopted by the City of Kingman with local amendments; A licensed Arizona electrical contractor is required unless the work qualifies for the A.R.S. § 32-1121(A)(5) owner-builder exemption on a personal owner-occupied residence. If your project isn't listed, confirm with City of Kingman Development Services Department — Building Division (Permits and Inspections) at 928-753-8130 before starting work.

No. The Development Services Fee Schedule (effective July 1, 2025) lists a dedicated $220 flat fee only for solar energy device systems under A.R.S. § 9-468. EV chargers/EVSE are not a listed special-permit category, so they are billed under the general valuation-based Building Permit Fee table using an applicant-estimated project valuation.

Kingman does not publish a plan-review timeline for this permit. Contact City of Kingman Development Services Department — Building Division (Permits and Inspections) at 928-753-8130 for current turnaround.

You'll need: Permit Application; Electrical Plans / One-Line Diagram. See the required-documents checklist on this page for details on each.

Kingman requires 1 inspection(s) for an ev charger / evse permit, in order: Final. Schedule each through City of Kingman Development Services Department — Building Division (Permits and Inspections) (928-753-8130).

Apply through City of Kingman Development Services Department — Building Division (Permits and Inspections) at 310 North 4th Street, Kingman, AZ 86401. Phone: 928-753-8130, email: buildingadmin@cityofkingman.gov. Office hours: Main Phone 928-753-8130 (Fax 928-753-8579); Building Inspection Line 928-753-8123 — inspection requests must be called in before 7:00 a.m. on the day of the inspection, providing name, permit number, job site address, inspection type, and contact phone number. All submittals and building-related correspondence go to buildingadmin@cityofkingman.gov. Building Official on record: Sean Osterman, CBO, CFM. The Development Services Department is transitioning building permit applications, plan submittals, and Planning & Zoning applications to the new SmartGov online portal beginning April 15, 2026 (https://ci-kingman-az.smartgovcommunity.com/Public/Home), ahead of a required full transition. Source: City of Kingman Permits and Inspections page and Application Submission page.. Official information: https://www.cityofkingman.gov/government/departments-a-h/development-services/permits-and-inspections.

Kingman, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9, §§ 9-831 through 9-840). The City of Kingman runs its own Development Services Department / Building Division and independently adopts and administers its own construction codes; it does not defer permitting to Mohave County, despite the AZBO statewide building-official directory listing a Fire Department contact for Kingman rather than a distinct Building Official entry — that listing is a directory data-capture artifact, not a sign of non-independence. The City's own Code Information & Design Criteria page and Code Amendment page confirm an actively maintained, independently adopted and amended code suite with a named Building Official (Sean Osterman, CBO, CFM). Source: City of Kingman Code Information & Design Criteria page; City of Kingman Code Amendment page.; 2018 International Building Code (IBC), as published by the International Code Council, adopted with City of Kingman local amendments (adopted appendices: C – Group U Agricultural Buildings, F – Rodent Proofing, I – Patio Covers, J – Grading, N – Replicable Buildings). Source: City of Kingman Code Information & Design Criteria page; Code Amendment page.; 2018 International Residential Code (IRC), adopted with City of Kingman local amendments (adopted appendices: A – Sizing and Capacities of Gas Piping, B – Sizing of Venting Systems, C – Exit Terminals of Mechanical Draft and Direct Venting Systems, H – Patio Covers, J – Existing Buildings and Structures, O – Automatic Vehicular Gates, Q – Tiny Houses (amended definition), R – Light Straw-Clay Construction, S – Strawbale Construction). Source: City of Kingman Code Information & Design Criteria page; Code Amendment page.; 2018 International Fire Code (IFC), adopted with City of Kingman local amendments (adopted appendices B, C, D, E, F, G); administered by the City of Kingman Fire Department. Source: City of Kingman Code Information & Design Criteria page; Code Amendment page.; 2018 International Existing Building Code (IEBC), adopted with local amendments (adopted appendices: C – Guidelines for the Wind Retrofit of Existing Buildings; Resource A – Guidelines on Fire Ratings of Archaic Materials and Assemblies). Source: City of Kingman Code Information & Design Criteria page; Code Amendment page.; 2018 International Plumbing Code (IPC), adopted with City of Kingman local amendments (e.g. amended Section P2902.5.3 Lawn irrigation systems backflow protection). Source: City of Kingman Code Information & Design Criteria page; Code Amendment page.; 2018 International Mechanical Code (IMC), adopted by the City of Kingman. Source: City of Kingman Code Information & Design Criteria page.; 2018 International Fuel Gas Code (IFGC), adopted by the City of Kingman. Source: City of Kingman Code Information & Design Criteria page.; 2018 International Energy Conservation Code (IECC), adopted with a local amendment deleting the Residential Energy Code Provisions (Chapter 1 Section R101.1 through Chapter 4 Section R406.6.5) as part of this code (residential energy provisions instead governed via the IRC Chapter 11 amendments below). Source: City of Kingman Code Information & Design Criteria page; Code Amendment page.; 2018 International Property Maintenance Code (IPMC), adopted by the City of Kingman. Source: City of Kingman Code Information & Design Criteria page.; 2018 International Swimming Pool and Spa Code (ISPSC), adopted by the City of Kingman with local amendments, replacing the prior Kingman Municipal Code Section 5-91 Swimming pools provision (deleted) and amending Section 305.4 item 3 self-closing/self-latching door protection height (54 inches). Referenced alongside Arizona Revised Statute (A.R.S.) § 36-1681. Source: City of Kingman Code Amendment page.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted by the City of Kingman with a local amendment adding an exception to Article 210, Section 210.8(A)(2) permitting a dedicated non-GFCI circuit for a washing machine, freezer, or refrigerator in garages. Source: City of Kingman Code Information & Design Criteria page; Code Amendment page.; 2010 ADA Standards for Accessible Design, together with Title 41, Chapter 9, Article 8, Arizona Revised Statutes (Arizonans with Disabilities Act) and its implementing rules, adopted as the accessibility standard referenced in IBC Chapter 11. Source: City of Kingman Code Amendment page.; Design Engineering by an Arizona-licensed design professional (RDP) is required to seal drawings submitted for development, unless specifically exempt per A.R.S. § 32-144 (e.g. detached single-family dwellings; one-/two-story buildings ≤3,000 sq ft with ≤20 occupants and ≤20-foot structural spans; certain additions/alterations subject to the same limits, with a one-time 1,500 sq ft storage-addition exception). Source: City of Kingman Code Information & Design Criteria page; City of Kingman 'Do I need a Registered Design Pro or General Contractor?' fact sheet.; Manufactured homes and factory-built buildings are separately permitted by the City (fee-schedule line items for Manufactured Home Permit and Residential/Commercial Factory-Built Building permits), consistent with State of Arizona regulation of manufactured-home construction/installation standards under A.R.S. § 41-4001 et seq. Source: City of Kingman Development Services Fee Schedule, effective July 1, 2025.. Local amendments apply — see the Kingman overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kingman building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.