Required for installation of rooftop residential solar photovoltaic systems in the City of Maricopa. Governed by the City's Residential Solar Photovoltaic Installations guide and the currently adopted 2024 IRC / 2023 NEC (the guide's own PDF still cites the prior 2018 IBC/2017 NEC cycle, not yet refreshed after Ordinance 26-01's February 2026 effective date). Applications are submitted via the VIP Portal.

Verified 2026-07-06 · Source

When you need this permit

  • Design Pack required, including spec sheets, electrical panel load calculations (existing service panel preferred), site plan showing panel and main service locations, site/aerial view, exterior elevations, one-line and three-line electrical diagrams, solar equipment notes/specifications/labeling, and a safety plan addressing fire setbacks
  • Mounting specifications and installation instructions must meet City of Maricopa design standards; per the City's adopted Single Family Residential Design Guidelines (Sec. C, 7d), panels are recommended to be placed parallel with the roof pitch so the array appears integral with the roof design
  • Approval of interconnection letter from Electrical District No. 3 (ED3) required as part of the submittal
  • Construction plans (with foundation/framing detail) required only if the array is not roof-mounted
  • Apply via the VIP Portal (ci-maricopa-az.smartgovcommunity.com); only PDF file submissions are accepted, using the City's specified file-naming convention

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential SolarCity of Maricopa Development Services Fee Schedule, Building Safety Fees — Permits, effective 10/02/2025
$300
Residential Permit Issuance FeeCity of Maricopa Development Services Fee Schedule, Building Safety Fees — Permits, effective 10/02/2025
$50

Review timeline

Plan reviewCity of Maricopa’s published plan-review target
20–30 business days

How long did your Residential Solar Photovoltaic (PV) Permit permit actually take in City of Maricopa?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final

    Panel mounting, racking attachment, roof penetration sealing, electrical connections, and interconnection point verified

See the full City of Maricopa inspection guide — scheduling & re-inspection fees →

Tips

  • The City's own Residential Solar Photovoltaic Installations guide (Rev. 11/2024) still instructs applicants to submit a Design Pack 'under 2018 IBC and 2017 NEC' — this predates Ordinance 26-01's February 20, 2026 effective date for the 2024 IRC/2023 NEC. The Maricopa City Code (the legally binding text) is current to Ordinance 26-01; applicants should confirm which code edition Development Services is currently reviewing against, since the guide document has not yet been republished.
  • Solar is not separately itemized on the Plan Review Turnaround Times chart and is understood to fall under the 'Miscellaneous' Building Safety category (8 working days first review / 4 subsequent, 10-day administrative completeness, 20-day substantive review, 30-working-day overall based on 2 review cycles).
  • Only PDF file submissions are accepted through the VIP Portal, using the City's required file-naming convention: (Plan Type) – (Project Name) – (Submittal #).

Frequently asked questions

City of Maricopa requires a residential solar photovoltaic (pv) permit for: Design Pack required, including spec sheets, electrical panel load calculations (existing service panel preferred), site plan showing panel and main service locations, site/aerial view, exterior elevations, one-line and three-line electrical diagrams, solar equipment notes/specifications/labeling, and a safety plan addressing fire setbacks; Mounting specifications and installation instructions must meet City of Maricopa design standards; per the City's adopted Single Family Residential Design Guidelines (Sec. C, 7d), panels are recommended to be placed parallel with the roof pitch so the array appears integral with the roof design; Approval of interconnection letter from Electrical District No. 3 (ED3) required as part of the submittal; Construction plans (with foundation/framing detail) required only if the array is not roof-mounted; Apply via the VIP Portal (ci-maricopa-az.smartgovcommunity.com); only PDF file submissions are accepted, using the City's specified file-naming convention. If your project isn't listed, confirm with City of Maricopa Development Services Department (Permit Center) at (520) 316-6920 before starting work.

$300 for the Residential Solar permit fee, plus the standard $50 Residential Permit Issuance Fee, per the City of Maricopa Development Services Fee Schedule (effective 10/02/2025).

City of Maricopa's published plan-review target for a residential solar photovoltaic (pv) permit is 20–30 business days.

You'll need: Design Pack; Interconnection Authorization (ED3). See the required-documents checklist on this page for details on each.

City of Maricopa requires 2 inspection(s) for a residential solar photovoltaic (pv) permit, in order: Rough Electrical, Final. Schedule each through City of Maricopa Development Services Department (Permit Center) ((520) 316-6920).

Apply through City of Maricopa Development Services Department (Permit Center) at 39700 W Civic Center Plaza, Maricopa, AZ 85138. Phone: (520) 316-6920, email: dsd@maricopa-az.gov. Office hours: Monday through Thursday, 7:00 a.m. to 6:00 p.m. (CLOSED Fridays) — the City of Maricopa operates on a four-day work week. The City has moved to an all-digital application and plan review platform; paper plan submittals are no longer accepted. All permit applications, plan submittals, fee payments, and inspection requests are handled via the VIP Portal (ci-maricopa-az.smartgovcommunity.com), a SmartGov Community platform. Source: City of Maricopa Permit Center page and Plan Review Turnaround Times document (Rev 5/2026).. Official information: https://www.maricopa-az.gov/Departments/Development-Services/Permit-Center.

City of Maricopa, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Maricopa independently adopts and administers its own construction codes through its Development Services Department; it does not defer to Pinal County for permitting within incorporated city limits. Source: Maricopa City Code (MCC) Chapter 15, Building Regulation, Ordinance 26-01.; On January 20, 2026, the City of Maricopa City Council approved adoption of the 2024 International Codes (IBC, IRC, IPMC, IMC, IPC, IFGC, IECC, IFC, International Swimming Pool and Spa Code) plus the 2023 NEC and ICC A117.1-2017 Accessible and Usable Buildings and Facilities Code, codified as Ordinance 26-01 and effective February 20, 2026. Source: City of Maricopa Public Notice — City of Maricopa Building Codes Implementation; Maricopa City Code Chapter 15.05, as codified March 2026.; 2024 International Building Code (IBC), published by the International Code Council, together with appendages, adopted as the building code of the City of Maricopa (MCC 15.05.040), with City amendments. Source: Maricopa City Code 15.05.040, Ordinance 26-01 § 2.; 2024 International Residential Code (IRC), published by the International Code Council, together with appendices (excluding B, BB, NB, NG, NH, and N2), adopted as the residential building code of the City of Maricopa (MCC 15.05.050), with City amendments. Source: Maricopa City Code 15.05.050, Ordinance 26-01 § 2.; 2024 International Property Maintenance Code (IPMC), adopted as the property maintenance code of the City of Maricopa (MCC 15.05.060), with City amendments. Source: Maricopa City Code 15.05.060, Ordinance 26-01 § 2.; 2024 International Mechanical Code (IMC), adopted as the mechanical code of the City of Maricopa (MCC 15.05.070), with City amendments. Source: Maricopa City Code 15.05.070, Ordinance 26-01 § 2.; 2024 International Plumbing Code (IPC), adopted as the plumbing code of the City of Maricopa (MCC 15.05.080), with City amendments. Source: Maricopa City Code 15.05.080, Ordinance 26-01 § 2.; 2024 International Fuel Gas Code (IFGC), adopted as the fuel gas code of the City of Maricopa (MCC 15.05.090), with City amendments. Source: Maricopa City Code 15.05.090, Ordinance 26-01 § 2.; National Electrical Code (NEC), 2023 Edition, published by the National Fire Protection Association, adopted as the electrical code of the City of Maricopa (MCC 15.05.100), with City amendments (electrical code cycle is one edition behind the 2024 ICC set, as is standard practice statewide). Source: Maricopa City Code 15.05.100, Ordinance 26-01 § 2.; 2024 International Energy Conservation Code (IECC), adopted as the energy code of the City of Maricopa (MCC 15.05.110). Source: Maricopa City Code 15.05.110, Ordinance 26-01 § 2.; 2024 International Fire Code (IFC), adopted as the fire code of the City of Maricopa (MCC 15.05.120) with Appendices B, C, D, E, F, G, H, I, J, K, L, M, N, and O adopted and extensive City amendments (sprinkler/alarm thresholds, fire department connection sizing, hazardous materials permitting); administered by the City of Maricopa Fire/Medical Department. Source: Maricopa City Code 15.05.120, Ordinance 26-01 § 2.; International Swimming Pool and Spa Code, adopted by the City of Maricopa (MCC 15.05.130). Source: Maricopa City Code 15.05.130, Ordinance 26-01 § 2 (chapter section list).; ICC A117.1-2017 Accessible and Usable Buildings and Facilities Code, adopted by the City of Maricopa (MCC 15.05.140) as its accessibility standard (the IBC's own referenced-standard section was amended to point to A117.1-2017 rather than an earlier edition). Source: Maricopa City Code 15.05.040(B) and 15.05.140, Ordinance 26-01 § 2.; International Wildland-Urban Interface Code, adopted by the City of Maricopa (MCC 15.05.150). Source: Maricopa City Code 15.05.150, Ordinance 26-01 § 2 (chapter section list).; Building permit and plan review fees are NOT set by the ICC codes' own fee tables — every adopted code's fee schedule section (IBC 109.2, IRC R108.2, IMC 108.2, IPC 106.6.2, IFGC 108.2) is explicitly amended to read: 'Building permit fees shall be assessed in accordance with the City of Maricopa Development Services Fee Schedule as approved by City Council.' The Development Services Fee Schedule (effective 10/02/2025) is the sole authoritative fee source. Source: Maricopa City Code 15.05.040(B), .050(B), .070(B), .080(B), .090(B); City of Maricopa Development Services Fee Schedule, Rev. 10/2025.; Manufactured homes, mobile homes, and factory-built buildings are separately addressed under the City's Manufactured Homes and Recreational Vehicles Process Guide; construction/installation standards for these units are regulated directly by the State of Arizona (A.R.S. § 41-4001 et seq., Arizona Department of Fire, Building and Life Safety / Office of Manufactured Housing), with the City handling on-site placement, foundation/tie-down, and zoning compliance. Source: City of Maricopa Handouts, Checklists & Guidelines page — Manufactured Homes and Recreational Vehicles Process Guide.. Local amendments apply — see the City of Maricopa overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of Maricopa building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.