Residential Building Permit (New Construction) in Silver Cliff, Colorado
Required for new construction of one- and two-family dwellings and townhouses (not more than three stories above grade) in the Town of Silver Cliff. Reviewed under the Town's adopted 2006 International Residential Code (IRC) plus the Town's local design criteria (40 psf ground snow load, 110 mph wind exposure C, 40-inch minimum frost depth) and 2006 Minimum Energy Efficiency Requirements. Issued by the Town of Silver Cliff Building & Zoning Department.
Verified 2026-07-06 · Source
When you need this permit
- Reviewed under the 2006 IRC as adopted by the Town of Silver Cliff
- Structures designed to the Town's residential criteria: 110 mph wind exposure C, 40 psf ground snow load, 40-inch minimum frost line depth
- Energy Analysis required with the application per the Town's 2006 Minimum Energy Efficiency Requirements (R-49 ceiling / R-19 walls / R-10 foundation minimums; U-0.35 windows/doors, U-0.60 skylights maximum; 80% minimum heater and water-heater efficiency); a certificate listing these values must be posted in or on the electrical panel
- Two (2) complete sets of plans and specifications, drawn to scale, each page showing owner's name and site address plus contractor's/engineer's/architect's name and address
- A site visit with the applicant and site plans in hand is required prior to permit issuance to verify property lines and setback distances
- Electrical and plumbing rough/final inspections are performed by the State of Colorado (State Electrical Board / State Plumbing Board), not the Town — confirmed via the Town's own Commercial Permit Requirements document referencing 'State rough electrical and plumbing' inspections, and the absence of Custer County from DORA's list of jurisdictions with their own local electrical/plumbing inspection programs
- Proof of ownership (deed or tax receipt) and property markers (property survey) required at submittal
- Utility documentation required as applicable: Electric (Black Hills Energy), Water and Sewer (Round Mountain Water & Sanitation District), or Well (State of Colorado)
- Contractor must furnish evidence of workers' compensation/employee liability, commercial general liability (minimum $500,000 CSL broad-form property damage including completed operations), commercial auto liability (minimum $1,000,000 CSL), and commercial umbrella liability (minimum $1,000,000 per occurrence) within 10 days of contract signing Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 6 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing and Foundation
After excavation for footings complete and required reinforcing steel in place; forms in place for concrete foundations
- 2
State Rough Electrical and Plumbing
Performed by the State of Colorado (State Electrical Board / State Plumbing Board), not the Town; Ufer ground must be in place
- 3
Framing
After roof deck/sheathing, all framing, fire blocking and bracing in place; rough electrical, plumbing, heating wires, pipes and ducts approved
- 4
Energy Efficiency Inspection
Envelope insulation R/U values, fenestration U value, duct system R value, HVAC and water-heating equipment efficiency per the 2006 Minimum Energy Efficiency Requirements
- 5
Final Inspection
After all work required by the building permit is completed; required before a Certificate of Occupancy is issued
See the full Silver Cliff inspection guide — scheduling & re-inspection fees →
Tips
- Electrical and plumbing work in Silver Cliff is inspected by the State of Colorado, not the Town — coordinate State Electrical Board / State Plumbing Board inspections separately from your Town building-permit inspections; the Town's own commercial permit requirements document explicitly lists 'State rough electrical and plumbing' as a required inspection step.
- No published fee schedule exists for the Building Permit itself (only the Excavation/Driveway fee schedule is itemized publicly) — call the Building & Zoning Office (719-783-3034) directly to get a current fee quote before budgeting your project.
- A site visit with the applicant and site plans in hand is a hard prerequisite to permit issuance — schedule this before expecting your permit to be ready.
- Silver Cliff's residential design criteria (40 psf snow load, 110 mph exposure C, 40" frost depth) are the LOCAL figures for one- and two-family dwellings; commercial structures use a different table (50 psf snow load, 110 mph 3-second gust, Seismic C, Winter Design Temp 10F) — do not mix the two design-criteria sets.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Silver Cliff building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Silver Cliff
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Colorado →
Look up this fee in a different city →
Now live
Build your Silver Cliff project checklist
Describe your project once and get every permit, document, and fee it triggers in Silver Cliff — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →