Commercial Tenant Finish / Remodel / Change of Occupancy Permit (Tenant Improvement) — Parker, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.parkerco.gov/DocumentCenter/View/728/Commercial-Tenant-Finish-Remodel-Plan-Submittal-Checklist
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Tenant Finish / Remodel / Change of Occupancy Permit (Tenant Improvement) in Parker, Colorado
Required for finishing out a commercial space for its first occupant (Tenant Finish), remodeling an already-finished commercial space where the occupancy classification is not changing (Remodel), or converting a commercial space to a new occupancy classification (Change of Occupancy). All three fall under a single COMMERCIAL Tenant Finish/Remodel/Change of Occupancy plan submittal checklist and review track at the Town of Parker Building Division, sharing the same commercial plan-check-deposit and review-timeline treatment as new commercial construction, but without the excise tax charged on new commercial buildings.
Verified 2026-08-02 · Source
When you need this permit
- Tenant Finish: the FIRST TIME the space is being occupied — a Certificate of Occupancy will be issued
- Remodel: the space has been previously finished by a prior tenant and the occupancy classification is not changing; Remodel permits may not require every item on the checklist — contact the Building Division to confirm scope
- Change of Occupancy: the space's occupancy classification is changing — a Certificate of Occupancy will be issued
- All documents must be submitted electronically (PDF only), maximum 50MB per file, filenames with no special characters, and a Description field filled in or plan review will not proceed
- One complete plan set stamped by required engineers: Architectural (floor/roof/schedules/sections), Structural (with calculations if any revisions), Mechanical stamped by engineer, Plumbing stamped by engineer (see C.R.S. 12-4-101)
- A project manual, if used, complete and stamped
- An energy analysis (Com-Check) of both the electrical portion and the mechanical portion is required; if additional HVAC units are being installed, a Mechanical Com-Check is specifically required
- Heating and cooling load design temperatures: Winter -3°F / Summer 90°F outdoor dry bulb, Winter 70°F / Summer 75°F indoor dry bulb
- A plan review deposit fee of 50% of the plan review fee is required
- Applicable codes are the Town's current adopted codes/design criteria/amendments (see the Town of Parker Building Codes page) — do not rely on a fixed code-year list, given the June 30, 2026 transition to the 2024 I-Codes described elsewhere in this file
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Mechanical, electrical, and plumbing rough-in as applicable to the scope of the tenant finish/remodel, per the stamped MEP plan sheets required at submittal
- 2
Final
All work complete per approved plans. A Certificate of Occupancy is issued for Tenant Finish (first-time occupancy) and Change of Occupancy permits; a straight Remodel of an already-finished space where the occupancy classification is not changing does not trigger a new Certificate of Occupancy, per the Town's Building Permit Type & Sub-Type Definitions
See the full Parker inspection guide — scheduling & re-inspection fees →
Tips
- Parker's own checklist explicitly distinguishes Tenant Finish (first-time occupancy, CO issued), Remodel (previously finished space, same occupancy, CO not reissued, and not all checklist items may apply), and Change of Occupancy (occupancy classification changing, CO issued) — confirm which sub-type applies before submitting, since it affects both the document checklist and the Certificate of Occupancy outcome.
- If additional HVAC units are being installed as part of the tenant finish or remodel, a Mechanical Com-Check energy analysis is specifically called out as required, in addition to the electrical Com-Check.
- Parker's EZ Commercial Permits track (referenced on the Town's Building Division page) covers small, non-structural commercial projects under 1,200 sq ft — worth asking about for minor tenant-finish scopes before going through the full commercial plan-review process.
- There is a genuine, unresolved conflict between Town-published documents on the plan review deposit for this permit type: the current (July 2026) checklist and the Building Permit Fees webpage say 50% of the plan review fee, while two older Town PDFs (a 2023 combined checklist and a 2018 Tenant Finish checklist, both still reachable/linked from the Town's own site) say a flat $100.00 — confirm directly with the Building Division rather than assuming either figure.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Parker building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Parker.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Parker
Commercial Tenant Finish / Remodel / Change of Occupancy Permit (Tenant Improvement) in other cities
Look up this fee in a different city →
Now live
Build your Parker project checklist
Describe your project once and get every permit, document, and fee it triggers in Parker — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →