EV Charger / EVSE Permit in Parker, Colorado

The Town of Parker does not publish a dedicated EV charger/EVSE permit; a dedicated EV charging circuit is permitted as standalone electrical work through the Town's standard Electrical Permit, billed under the same formula-based fee structure (Table 3.2) used for all standalone residential electrical permits — no EV-specific line item exists. Parker's population is well above the 10,000-resident municipal threshold that makes it a 'covered municipality' under Colorado HB24-1173, the statewide EV Charging System Permits law requiring covered jurisdictions to notify applicants of an approval/denial decision within 3 business days by a December 31, 2025 compliance deadline; no published record was found confirming which HB24-1173 compliance path (Colorado Energy Office model code, the Town's own standards, or an opt-out resolution keeping the existing process) the Town adopted.

Verified 2026-07-20 · Source

When you need this permit

  • Standalone electrical permit required for a dedicated EV charging circuit, calculated by the Table 3.2 formula rather than the general valuation-based Building Permit Fee Schedule
  • Applications submitted through the Town's eTRAKiT system
  • Contractors must be licensed with the Town of Parker Contractor
  • Governed by the National Electrical Code as locally adopted (2023 NEC in effect through December 31, 2026; 2026 NEC effective January 1, 2027)
  • Under Colorado HB24-1173, Parker (population over the 10,000-resident municipal threshold) is a covered municipality required to notify EV charging permit applicants of a decision within 3 business days of making that determination

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential Electrical Permit — project valuation not more than $2,000.00Town of Parker Homeowner Fee Estimator worksheet, Table 3.2 Electrical Permit Fees — the mechanism a standard EV charger circuit installation is billed under; no EV-specific line item exists
$88.00
Residential Electrical Permit — project valuation $2,000.00 or moreTown of Parker Homeowner Fee Estimator worksheet, Table 3.2 Electrical Permit Fees
$9.00 per $1,000.00 of project valuation (or fraction thereof) plus $88.00
Plan Review FeeTown of Parker Homeowner Fee Estimator worksheet
65% of the Electrical Permit fee
Re-inspection FeeTown of Parker Fee Valuation Schedule, effective June 15, 2020
$75.00

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Parker?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Circuit wiring and conduit installed before walls closed

  2. 2

    Final

    EVSE installed, devices verified, system energized

See the full Parker inspection guide — scheduling & re-inspection fees →

Tips

  • Parker has no dedicated EV charger permit — apply for a standalone Electrical Permit through eTRAKiT, billed under the Table 3.2 formula fee (not the general valuation-based Building Permit schedule).
  • Colorado HB24-1173 legally requires Parker, as a covered municipality (population over 10,000), to decide on an EV charging permit application within 3 business days of making its determination, but no Town-published record confirms its specific implementation of the law.

Frequently asked questions

Parker requires an ev charger / evse permit for: Standalone electrical permit required for a dedicated EV charging circuit, calculated by the Table 3.2 formula rather than the general valuation-based Building Permit Fee Schedule; Applications submitted through the Town's eTRAKiT system; Contractors must be licensed with the Town of Parker; Governed by the National Electrical Code as locally adopted (2023 NEC in effect through December 31, 2026; 2026 NEC effective January 1, 2027); Under Colorado HB24-1173, Parker (population over the 10,000-resident municipal threshold) is a covered municipality required to notify EV charging permit applicants of a decision within 3 business days of making that determination. If your project isn't listed, confirm with Town of Parker Building Division (Community Development Department) at 303-841-1970 before starting work.

No EV-specific fee is published. An EV charging circuit is billed as a standalone Electrical Permit using the Town's Table 3.2 formula: $88.00 flat for project valuation up to $2,000, then $9.00 per additional $1,000 plus $88.00 above that.

Parker does not publish a plan-review timeline for this permit. Contact Town of Parker Building Division (Community Development Department) at 303-841-1970 for current turnaround.

You'll need: Electrical Permit Application (eTRAKiT). See the required-documents checklist on this page for details on each.

Parker requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In, Final. Schedule each through Town of Parker Building Division (Community Development Department) (303-841-1970).

Apply through Town of Parker Building Division (Community Development Department) at 20120 E. Mainstreet, Parker, CO 80138. Phone: 303-841-1970, email: building@parkerco.gov. Office hours: Monday-Friday, 8 a.m.-5 p.m. Inspection requests called in prior to 4 p.m. are performed the following business day; roofing inspections occur 8 a.m.-12 p.m., no same-day requests.. Official information: https://www.parkerco.gov/114/Building-Division.

Parker, Colorado has adopted: Town of Parker is in transition: full enforcement of the 2024 International Codes begins June 30, 2026, in conjunction with the Colorado Model Electric Ready and Solar Ready Code. Source: Town of Parker Building Codes page, https://www.parkerco.gov/445/Building-Codes; 2024 International Building Code (IBC) — effective June 30, 2026; 2024 International Residential Code (IRC) — effective June 30, 2026; 2024 International Plumbing Code (IPC) — effective June 30, 2026 (note: Parker uses the IPC, not the Uniform Plumbing Code); 2024 International Mechanical Code (IMC) — effective June 30, 2026; 2024 International Fuel Gas Code (IFGC) — effective June 30, 2026; 2024 International Fire Code — effective June 30, 2026; 2024 International Energy Conservation Code (IECC) — effective June 30, 2026; 2024 International Existing Building Code — effective June 30, 2026; 2024 Non-Residential Property Maintenance Code — effective June 30, 2026; 2024 International Swimming Pool and Spa Code — effective June 30, 2026; Parker Administrative Code (2024 edition, local amendments to the above) — effective June 30, 2026; 2025 Colorado Wildfire Resiliency Code (CWRC) — adopted per Town of Parker Building Codes page; 2025 Colorado Model Electric Ready and Solar Ready Code — adopted alongside the 2024 I-Codes; 2023 National Electrical Code (NEC) remains in effect through December 31, 2026; the 2026 NEC takes effect January 1, 2027. Source: Town of Parker Building Codes page, https://www.parkerco.gov/445/Building-Codes; Roofing-specific current code reference (per the Town's own Re-Roofing Requirements handout, revised 3/14/2025, which predates the 2024 I-Code transition): 2021 IRC (Residential) and 2021 IBC (Commercial and Multi-Family). Source: https://www.parkerco.gov/DocumentCenter/View/738; Colorado has no statewide mandatory building code for most jurisdictions (home-rule authority). Parker's own adopted codes, amendments, and effective dates as listed above are the governing figures; always confirm current status directly with the Building Division given the June 30, 2026 code-transition date. Source: Colorado Energy Office, Building Energy Codes Toolkit, https://energyoffice.colorado.gov/building-energy-codes-toolkit. Local amendments apply — see the Parker overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Parker building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.