Residential Building Permit (New Construction) in Mount Crested Butte, Colorado

Required for new single-family homes, duplexes, townhomes, and similar residential structures within Town of Mt. Crested Butte limits. Reviewed under the 2021 IRC as locally amended (Town Code Chapter 6, Article III), including the Town's Table R301.2 climatic design criteria (155 psf ground snow load, 105 mph wind design speed, Seismic Design Category B, 9,400 ft Manual J elevation), a stricter automatic fire sprinkler trigger than neighboring Crested Butte, and a concurrent Design Review + Permit Review process administered directly by the Community Development Department.

Verified 2026-07-06 · Source

When you need this permit

  • Design Review and Permit Review are conducted CONCURRENTLY (not sequentially gated); Design Review approval, once granted, is valid for 1 year
  • Must meet Table R301.2 design criteria: 155 psf ground snow load (2016 SEAC Colorado Design Snow Loads), 105 mph wind design speed, Seismic Design Category B, 36-inch minimum frost line depth, mandatory roof ice barrier underlayment, -16 F winter design temperature, 9,400 ft Manual J elevation
  • Automatic residential fire sprinkler system required in all two-family dwellings/townhomes (no size threshold) and in one-family dwellings with gross floor area 4,800 sq ft or more (Town Code Sec. 6-59)
  • Crested Butte Fire Protection District (CBFPD) approval letter required confirming access, gas meter location, and water supply comply with Town Code Chapter 8
  • Construction Management Plan (CMP) required, addressing on-site parking, material staging, trash/toilets, and seasonal right-of-way parking restrictions (no parking in Town rights-of-way November 15-April 15)
  • Soils report required; engineer must address foundation design, driveway design, and retaining walls per the soils report recommendations
  • Site survey/plat prepared by a Colorado-licensed land surveyor required with the permit application (Town Code Sec. 6-49/R105.3)
  • Landscaping point schedule required, tied to Gross Residential Floor Area (GRFA) — minimum 2,000 base points in single-family residential plus 1 additional point per sq ft above 2,500 sq ft GRFA, with minimum tree/evergreen composition thresholds
  • Mt. CB Water & Sanitation District tap fee receipt required prior to permit issuance
  • Contractor must hold a current Mt. CB Business License (BOLF)
  • Design Review Compliance and Cleanup Deposit required for any permit with valuation $1,000 or more, tiered by total valuation (up to 2% of valuation for higher tiers), up to 50% refundable on substantial design-review completion
  • 3% Use Tax on construction/building materials, calculated on 50% of estimated total valuation, reconciled within 90 days of CO issuance or final inspection
  • Radon mitigation plan must be shown on drawings (per the Town's Radon Requirements IRC 2015 policy)
  • Electrical and plumbing work under this permit is NOT reviewed or inspected by the Town — those permits/inspections are obtained separately and directly from the State of Colorado (Colorado Electrical Board and Colorado State Plumbing Board)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 9 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation $1.00 to $500.00Town Code Sec. 6-21 / Table 1-A (IBC) and Sec. 6-52 / Table R1-A (IRC), identical schedules, set directly in Ordinance No. 6, Series 2024
$23.50
Building Permit Fee — valuation $501.00 to $2,000.00
$23.50 for the first $500 plus $3.05 per additional $100 or fraction thereof
Building Permit Fee — valuation $2,001.00 to $25,000.00
$69.25 for the first $2,000 plus $14.00 per additional $1,000 or fraction thereof
Building Permit Fee — valuation $25,001.00 to $50,000.00
$391.75 for the first $25,000 plus $10.10 per additional $1,000 or fraction thereof
Building Permit Fee — valuation $50,001.00 to $100,000.00
$643.75 for the first $50,000 plus $7.00 per additional $1,000 or fraction thereof
Building Permit Fee — valuation $100,001.00 to $500,000.00
$993.75 for the first $100,000 plus $5.60 per additional $1,000 or fraction thereof
Building Permit Fee — valuation $500,001.00 to $1,000,000.00
$3,233.75 for the first $500,000 plus $4.75 per additional $1,000 or fraction thereof
Building Permit Fee — valuation $1,000,001.00 and up
$5,608.75 for the first $1,000,000 plus $3.65 per additional $1,000 or fraction thereof
Plan Check FeeSeparate from and in addition to the permit fee, per Town Code Sec. 109.5/R108.5
65% of the Building Permit Fee
Use TaxReconciled within 90 days of CO issuance or final inspection approval
3% of 50% of total estimated project valuation
Design Review Compliance and Cleanup Deposit — valuation $1,000-$4,999
$500
Design Review Compliance and Cleanup Deposit — valuation $5,000-$9,999
$1,000
Design Review Compliance and Cleanup Deposit — valuation $10,000-$49,999
$2,000, or 2% of total valuation for higher tiers per the Building Official's determination
Work Done without a Building Permit2026 Fee Resolution No. 9, Series 2026, effective May 20, 2026
$100.00 or the permit fee, whichever is greater

Review timeline

Plan reviewTypical estimate — confirm current times with the Mount Crested Butte building department
~Up to 28 business days

How long did your Residential Building Permit (New Construction) permit actually take in Mount Crested Butte?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footer Inspection

  2. 2

    Stem Wall Inspection

  3. 3

    Slab Inspection

  4. 4

    Culvert/Valley Pan Rough-In Inspection

  5. 5

    Flow Fill (Road Cut) Inspection

  6. 6

    Framing Inspection

  7. 7

    Energy & Insulation Inspection

  8. 8

    Drywall Inspection

  9. 9

    Final Inspection

    Required before Certificate of Occupancy issuance; request at least 2 working days in advance per Town Code Sec. 6-22/6-53

See the full Mount Crested Butte inspection guide — scheduling & re-inspection fees →

Tips

  • Mt. Crested Butte's design snow load (155 psf) is meaningfully heavier than neighboring Crested Butte's (100 psf) due to higher elevation (9,400 ft vs 8,921 ft) — don't reuse Crested Butte's structural assumptions for a Mt. Crested Butte project.
  • Unlike Crested Butte, Mt. Crested Butte does NOT issue or inspect electrical or plumbing permits at all — budget separate lead time to work directly with the State of Colorado's Electrical and Plumbing Boards for those trades.
  • The automatic fire sprinkler trigger here is stricter than Crested Butte's: single-family homes are NOT categorically exempt — homes at or above 4,800 sq ft gross floor area require sprinklers, as do all two-family/townhome units regardless of size.
  • Building/residential inspection requests need only 2 working days' notice here (vs. 5 in Crested Butte), but Fire Code inspections still need 5 working days — don't assume a uniform notice period across trades.
  • Budget for the Design Review Compliance and Cleanup Deposit (up to 2% of valuation) and the 65% Plan Check Fee on top of the base valuation-tiered Building Permit Fee — together these can substantially exceed the headline permit fee.

Frequently asked questions

Mount Crested Butte requires a residential building permit (new construction) for: Design Review and Permit Review are conducted CONCURRENTLY (not sequentially gated); Design Review approval, once granted, is valid for 1 year; Must meet Table R301.2 design criteria: 155 psf ground snow load (2016 SEAC Colorado Design Snow Loads), 105 mph wind design speed, Seismic Design Category B, 36-inch minimum frost line depth, mandatory roof ice barrier underlayment, -16 F winter design temperature, 9,400 ft Manual J elevation; Automatic residential fire sprinkler system required in all two-family dwellings/townhomes (no size threshold) and in one-family dwellings with gross floor area 4,800 sq ft or more (Town Code Sec. 6-59); Crested Butte Fire Protection District (CBFPD) approval letter required confirming access, gas meter location, and water supply comply with Town Code Chapter 8; Construction Management Plan (CMP) required, addressing on-site parking, material staging, trash/toilets, and seasonal right-of-way parking restrictions (no parking in Town rights-of-way November 15-April 15); Soils report required; engineer must address foundation design, driveway design, and retaining walls per the soils report recommendations; Site survey/plat prepared by a Colorado-licensed land surveyor required with the permit application (Town Code Sec. 6-49/R105.3); Landscaping point schedule required, tied to Gross Residential Floor Area (GRFA) — minimum 2,000 base points in single-family residential plus 1 additional point per sq ft above 2,500 sq ft GRFA, with minimum tree/evergreen composition thresholds; Mt. CB Water & Sanitation District tap fee receipt required prior to permit issuance; Contractor must hold a current Mt. CB Business License (BOLF); Design Review Compliance and Cleanup Deposit required for any permit with valuation $1,000 or more, tiered by total valuation (up to 2% of valuation for higher tiers), up to 50% refundable on substantial design-review completion; 3% Use Tax on construction/building materials, calculated on 50% of estimated total valuation, reconciled within 90 days of CO issuance or final inspection; Radon mitigation plan must be shown on drawings (per the Town's Radon Requirements IRC 2015 policy); Electrical and plumbing work under this permit is NOT reviewed or inspected by the Town — those permits/inspections are obtained separately and directly from the State of Colorado (Colorado Electrical Board and Colorado State Plumbing Board). If your project isn't listed, confirm with Town of Mt. Crested Butte Community Development Department (Building Division) at (970) 349-6632, ext. 5 (Community Development Department) before starting work.

In Mount Crested Butte, the published Building Permit Fee — valuation $1.00 to $500.00 is: $23.50. Additional published fees: Building Permit Fee — valuation $501.00 to $2,000.00 — $23.50 for the first $500 plus $3.05 per additional $100 or fraction thereof; Building Permit Fee — valuation $2,001.00 to $25,000.00 — $69.25 for the first $2,000 plus $14.00 per additional $1,000 or fraction thereof; Building Permit Fee — valuation $25,001.00 to $50,000.00 — $391.75 for the first $25,000 plus $10.10 per additional $1,000 or fraction thereof; Building Permit Fee — valuation $50,001.00 to $100,000.00 — $643.75 for the first $50,000 plus $7.00 per additional $1,000 or fraction thereof; Building Permit Fee — valuation $100,001.00 to $500,000.00 — $993.75 for the first $100,000 plus $5.60 per additional $1,000 or fraction thereof; Building Permit Fee — valuation $500,001.00 to $1,000,000.00 — $3,233.75 for the first $500,000 plus $4.75 per additional $1,000 or fraction thereof; Building Permit Fee — valuation $1,000,001.00 and up — $5,608.75 for the first $1,000,000 plus $3.65 per additional $1,000 or fraction thereof; Plan Check Fee — 65% of the Building Permit Fee; Use Tax — 3% of 50% of total estimated project valuation; Design Review Compliance and Cleanup Deposit — valuation $1,000-$4,999 — $500; Design Review Compliance and Cleanup Deposit — valuation $5,000-$9,999 — $1,000; Design Review Compliance and Cleanup Deposit — valuation $10,000-$49,999 — $2,000, or 2% of total valuation for higher tiers per the Building Official's determination; Work Done without a Building Permit — $100.00 or the permit fee, whichever is greater. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town's own Design and Permit Review Punch List states the process timeline is up to 4 weeks once payment and application documents are submitted. Design Review approval, once granted, remains valid for 1 year.

You'll need: Design and Permit Review Application (GovWell portal); Building Permit Application (fillable form); Site survey/plat by a Colorado-licensed land surveyor; Crested Butte Fire Protection District approval letter; Construction Management Plan (CMP); Soils/Geotechnical Report; Landscaping Plan with Point Table; Mt. CB Water & Sanitation District Tap Fee Receipt; Mt. CB Business License (BOLF) for General Contractor. Depending on your project, Mount Crested Butte may also ask for: Property Owner Authorization Form. See the required-documents checklist on this page for details on each.

Mount Crested Butte requires 9 inspection(s) for a residential building permit (new construction), in order: Footer Inspection, Stem Wall Inspection, Slab Inspection, Culvert/Valley Pan Rough-In Inspection, Flow Fill (Road Cut) Inspection, Framing Inspection, Energy & Insulation Inspection, Drywall Inspection, Final Inspection. Schedule each through Town of Mt. Crested Butte Community Development Department (Building Division) ((970) 349-6632, ext. 5 (Community Development Department)).

Apply through Town of Mt. Crested Butte Community Development Department (Building Division) at 911 Gothic Rd., PO Box 5800, Mt. Crested Butte, CO 81225. Phone: (970) 349-6632, ext. 5 (Community Development Department), email: mnevinslavtar@mtcb.colorado.gov (Community Development Director). Office hours: Community Development Department Staff (per mtcb.colorado.gov/departments-services/community-development): Maeve Nevins-Lavtar, Community Development Director, ext. 117, mnevinslavtar@mtcb.colorado.gov. Shannon Hessler, Planner II, ext. 119, shessler@mtcb.colorado.gov. Todd Carroll, Community Development Coordinator, ext. 120, tcarroll@mtcb.colorado.gov. Leah Desposato, Community Development Coordinator, ext. 105, ldesposato@mtcb.colorado.gov. Building permit and design-review applications are submitted online via the Town's GovWell portal (app.govwell.com/mtcb).. Official information: https://mtcb.colorado.gov/building.

No. The Town's own Inspections page states plainly that Mt. Crested Butte does not issue electrical permits or perform electrical inspections, and does not perform plumbing inspections — both are handled entirely by the State of Colorado (Colorado Electrical Board and Colorado State Plumbing Board), not the Town Building Division.

Only if the gross floor area is 4,800 sq ft or more (Town Code Sec. 6-59). All two-family dwellings and townhomes require sprinklers regardless of size — a stricter rule than neighboring Crested Butte, which exempts single-family homes from sprinklers entirely.

Compare residential building permit (new construction) fees across Colorado

Look up this fee in a different city →

Embed this data card →

Now live

Build your Mount Crested Butte project checklist

Describe your project once and get every permit, document, and fee it triggers in Mount Crested Butte — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.

Get started →