Solar Photovoltaic (PV) Permit — Mount Crested Butte, Colorado · Requirements sheet
Verified 2026-07-19 · Source: https://mtcb.colorado.gov/building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Photovoltaic (PV) Permit in Mount Crested Butte, Colorado
Required for rooftop or ground-mounted solar photovoltaic installation in the Town of Mt. Crested Butte. The Town's own Building Division does NOT issue or inspect electrical permits at all — electrical work, including PV wiring and utility interconnection, is handled entirely by the Colorado State Electrical Board (Division of Professions and Occupations), capped at $500 for a residential permit and $1,000 for a commercial permit under the statewide solar permit fee cap, C.R.S. § 24-48.5-113 (HB21-1284). The Town's own Building Permit (valuation-based Table 1-A fee, or the Design Review 'no drawings/engineering' $100 fee for simple roof-mounted work) covers only the structural/mounting scope. The Town has adopted the Model Colorado Electric and Solar Ready Code provisions for new construction.
Verified 2026-07-19 · Source
When you need this permit
- Town Building Permit required for the array mounting/structural scope, submitted via the Town's GovWell online portal
- Electrical permit for PV wiring/interconnection must be obtained directly from the Colorado State Electrical Board (dpo.colorado.gov/Electrical), NOT from the Town — the Town's Building Division does not issue or inspect electrical permits
- Colorado State Electrical Board Solar/Alternative Energy System permits may use a SolarApp+ or Symbium expedited plan review pathway per the Board's published process
- State Electrical Board permit is valid for one year from the date of issuance
- Design Review approval required through the Community Development Department; a solar-only installation that does not require drawings/engineering (e.g., a straightforward roof-mount) falls under the $100 Design Review fee tier; installations requiring drawings/engineering are billed at the $200+ tier
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Framing/Structural Inspection (Town)
Roof/mounting attachment verified by the Town's Building Division before panel installation is completed
- 2
Electrical Inspection (State Electrical Board)
Conducted by the Colorado State Electrical Board, not the Town, covering PV wiring and interconnection
- 3
Final Inspection (Town)
Required before Certificate of Occupancy/Compliance sign-off; request at least 2 working days in advance per Town Code Sec. 6-22/6-53
See the full Mount Crested Butte inspection guide — scheduling & re-inspection fees →
Tips
- Do not expect the Town's GovWell portal to cover the electrical trade for a solar installation — the Colorado State Electrical Board handles PV wiring/interconnection permitting and inspection directly, entirely separate from the Town's own Building Permit and Design Review process.
- A simple roof-mounted solar array that does not require drawings/engineering may qualify for the Town's lower $100 Design Review fee tier rather than the $200+ tier that applies to projects requiring structural drawings.
- Both the residential ($500) and commercial ($1,000) Colorado State Electrical Board solar permit fees are hard caps set by state law (HB21-1284/C.R.S. § 24-48.5-113), not Town-set fees.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mount Crested Butte building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Mount Crested Butte
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Colorado →
Look up this fee in a different city →