Solar Photovoltaic (PV) Permit in Erie, Colorado
Required for residential and commercial solar PV installations in Erie. The Town publishes a dedicated Solar Photovoltaic (PV) Permitting and Inspection Checklist with a flat fee, specific design criteria, a photo-based rough inspection option, and published (though non-guaranteed) review timelines.
Verified 2026-07-06 · Source
When you need this permit
- All Solar Permits must have a licensed Electrical Contractor listed on the application; the Town verifies the company holds a State-licensed Electrical Contractor and that the listed Master Electrician is employed by that company Contractor
- PV arrays complying with IRC R324.6 Roof Access and Pathways require no fire service review; others require Mountain View Fire Rescue review
- Site plan showing location of major components (need not be to exact scale)
- Electrical diagram/worksheet showing PV system configuration, wiring, overcurrent protection, inverter, disconnects, required signage, and AC connection to the building
- Specification sheets and installation manuals for all manufactured components (PV modules, inverter(s), combiner box, disconnects, mounting system), where available
- Structural Roof Letter, including snow load and wind speed, stamped by a Colorado Professional Engineer
- Local design criteria per the checklist: Maximum Wind Speed = 142 mph Ultimate; Snow Load = 30 psf (checklist's own codes list cites 2021 IRC/IBC and 2020 NEC, which predate the Town's April 2026 IECC/NEC/IFC update — reconfirm current governing code edition with the Building Division for design work)
- Submitted via the Customer Self-Service Portal (eTRAKiT)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical and Frame Solar
Residential rough solar inspection requires photos submitted by email (building@erieco.gov) rather than an in-person visit in most cases; JPGs or PDF only, 10-15 photos max, no ZIP files or cloud links; photos must show bonding, flashing, junction boxes, and full panel landscapes; typical photo-review turnaround is 2-3 business days
- 2
Final Electrical, Building, and Electrical Service
Final inspection covering electrical service connection and overall installation
See the full Erie inspection guide — scheduling & re-inspection fees →
Tips
- Erie's residential solar rough inspection is typically done by PHOTO SUBMISSION (email to building@erieco.gov), not an in-person site visit — follow the exact photo requirements (10-15 photos, JPG/PDF only, no ZIP/cloud links, showing bonding/flashing/junction boxes) to avoid a resubmission delay.
- The County Use Tax rate the Town applies to solar permits is explicitly the Boulder County rate (0.985%) in its own published checklist, regardless of which county the specific parcel sits in.
- Systems using PV shingles or battery storage require separate Mountain View Fire Rescue approval in addition to the Town's own permit review.
- A solar permit expires 6 months after issuance if work has not commenced, or if more than 6 months pass between inspections.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Erie building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Erie
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Erie project checklist
Describe your project once and get every permit, document, and fee it triggers in Erie — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →