Inspection sequence, scheduling, and re-inspection fees for building permits in Firestone, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
9950 Park Avenue, Firestone, CO 80504
Phone
303-833-3291
Office hours
Monday through Friday, 8 a.m. to 5 p.m. (Town Hall hours); SAFEbuilt Colorado's local office is at 11409 Business Park Circle, Suite 350, Firestone, CO 80504, phone 303-774-1388 (per SAFEbuilt's own site); Firestone-specific SAFEbuilt inspection contact: firestone-building@safebuilt.com / 303-774-0454, and Building Official Tim Moroney, tmoroney@safebuilt.com / 970-545-3555 (per SAFEbuilt/search-indexed contact listing — recommend confirming current staffing directly with the Town before publishing to end users, as this level of detail was not independently re-confirmed on a live SAFEbuilt staff-directory page during this extraction)

Inspection sequence

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation (if new footings)

    Before concrete pour; crawlspace/basement foundation detail per the Town's Building Guide (steel anchor bolts, rebar, vapor barrier)

  2. 2

    Framing

    Framing and connection to existing structure

  3. 3

    Rough Electrical/Plumbing/Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation/Footing

    Before concrete pour

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical/Plumbing/Mechanical

    Trade rough-ins before concealment; complex electrical/mechanical systems may additionally require a registered design professional's Electrical/Mechanical Observation per Ordinance 1029 Sections 1704.7/1704.8 (health-care, >1000V, or hazardous-location scope)

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes; performed by SAFEbuilt Colorado under contract to the Town

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized; performed by SAFEbuilt Colorado

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Equipment

    Equipment installation and ductwork before concealment

  2. 2

    Final Inspection

    Equipment operational; combustion air and venting verified; performed by SAFEbuilt Colorado

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Before concealment — pipe slope, materials, cleanouts

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified; performed by SAFEbuilt Colorado

Applies to: Roofing Permit (Reroof)

  1. 1

    Mid-Roof Inspection

    Required when no more than 25% of the roof is complete; verifies ice & water shield installed 24 inches inside the exterior wall line, drip edge fastened at minimum 12-inch on-center with proper overlap, and underlayment sequencing at eaves/rakes

  2. 2

    Final Roof Inspection

    Completed roof covering verified against approved plans and applicable code; performed by SAFEbuilt Colorado

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical connections verified; performed by SAFEbuilt Colorado

Re-inspection fees

Electrical PermitReinspection Fee
$75.00 progressive (24-hour inspection delay)
Plumbing PermitReinspection Fee
$75.00 progressive (24-hour inspection delay)
Mechanical / HVAC PermitReinspection Fee
$75.00 progressive (24-hour inspection delay)
Roofing Permit (Reroof)Reinspection Fee
$75.00 progressive (24-hour inspection delay)

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Firestone building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Firestone building permits

Get alerts for Firestone

We'll email you when Firestone's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.