Commercial Building Permit (New Construction / Additions) — Firestone, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.firestoneco.gov/425/Building-Permits-Fees
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction / Additions) in Firestone, Colorado
Required for new commercial buildings and additions thereto in Firestone. Reviewed under the 2018 IBC as locally amended by Ordinance No. 1029 (the 'Firestone Building and Construction Code'), with the 2023 NEC for electrical scope. Firestone publishes a dedicated Commercial Permit Submittal Checklist (REV 03.25) distinct from residential submittals, and a separate 2026 Non-Residential Fees sheet covering water tap, impact, and use-tax charges layered on top of the standard valuation-based Building Permit Fee. All plans must be stamped by a Colorado Licensed Architect and Colorado Registered Engineers. Plan review/permit administration is by Town staff; inspections are performed by SAFEbuilt Colorado under contract.
Verified 2026-08-02 · Source
When you need this permit
- All plans, specifications, and calculations must be stamped by their respective design professionals (Colorado Licensed Architect and Colorado Registered Engineers), per the Commercial Permit Submittal Checklist (REV 03.25)
- All General, Mechanical, Plumbing, Electrical, and Sub-Contractors must be listed on the permit application AND licensed with the Town of Firestone as a condition of permit issuance
- Total building valuation must be provided in addition to the total electrical valuation; detailed bids may be required if the Building Official deems valuations inaccurate for the proposed scope
- Site-specific soils report required; structural design criteria must include ALL information required by 2018 IBC 1603 (wind speed/exposure, snow loads, seismic design category, soil-bearing data from a geotechnical engineer, etc.)
- Civil package required: dimensioned site plans, grading and drainage plans, utility plans, and accessibility plans/details
- Architectural code analysis required covering occupancy classification, construction type, sprinkler/fire alarm status, allowable height/stories/area, egress, accessibility (IBC Ch. 11), energy code compliance path, and life safety/egress plans per IBC 107.2.3
- IECC compliance path documentation prepared by the designing Architect
- Separate submittals must be made to the Frederick-Firestone Fire Protection District (Steve Iacino, Asst. Chief of Planning, 303-833-2742 / 720-526-6583) and St. Vrain Sanitation District (303-776-9570) — multi-family and all commercial projects require fire district approval
- Sewer tap receipt from St. Vrain Sanitation required at time of permit submittal for new commercial; receipts from Little Thompson or Left Hand Water District required if the project is in those districts
- Kitchen hoods, woodworking dust-collection systems, and spray/paint booths require additional engineered plans/shop drawings, with paint booth plans submitted to both the Fire Department and Building Department
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 6 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing/Foundation
Before concrete pour; commercial projects may optionally start under a standalone $2,000 Footing/Foundation Permit ahead of full permit issuance
- 2
Framing/Structural
Structural framing complete before cover, per approved stamped plans
- 3
Rough Electrical/Plumbing/Mechanical
Trade rough-ins before concealment; complex electrical/mechanical systems may additionally require a registered design professional's observation per Ordinance 1029 Sections 1704.7/1704.8
- 4
Fire District Inspections
Frederick-Firestone Fire Protection District performs its own inspections under its separate submittal/approval
- 5
Final Inspection / Certificate of Occupancy
All work complete per approved plans; performed by SAFEbuilt Colorado under contract to the Town. A Temporary CO is available for $750 ($400 refundable if the final CO issues before TCO expiration)
See the full Firestone inspection guide — scheduling & re-inspection fees →
Tips
- Budget well beyond the building permit fee itself: new commercial projects also owe impact fees ($2,103.54-$7,994.83 per 1,000 sq ft depending on use category), use tax (2.6% of half the valuation), water tap and meter fees, and a $150 commercial administration fee.
- Three separate submittals are required — Town Building Division, Frederick-Firestone Fire Protection District, and St. Vrain Sanitation District each have their own submittal requirements, and proof of sewer tap purchase must accompany the Town permit submittal.
- Every contractor on the job (general and all subs) must be licensed with the Town of Firestone before the building permit will be issued — start contractor licensing early. Contractor
- A commercial-only Footing/Foundation Permit ($2,000) lets sitework/foundations start ahead of the full permit, but additional fees for the full submittal still apply.
- The 65% plan review fee is due at the time of submittal, not at issuance.
- Incomplete submittals are rejected outright and reviews are strictly first-come-first-served, so a complete stamped package the first time is the fastest path through review.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Firestone building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Firestone.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Firestone
Commercial Building Permit (New Construction / Additions) in other cities
Compare commercial building permit (new construction / additions) fees across Colorado →