Commercial Tenant Finish (Tenant Improvement) Permit — Firestone, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.firestoneco.gov/DocumentCenter/View/11420/TI-permit-submittal-checklist-Updated-4-9-24
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Tenant Finish (Tenant Improvement) Permit in Firestone, Colorado
Required for tenant finishes in existing commercial buildings in Firestone. Genuinely distinct from the new-commercial process: the Town publishes a separate 'Commercial Tenant Finish Permit Submittal Checklist' (REV 04.24) with its own scope — no civil package or soils report required, structural documentation only if applicable, change-of-occupancy analysis when the use changes, and energy code documentation typically only for previously unoccupied shell spaces. Plans must still be stamped by a Colorado Licensed Architect and Colorado Registered Engineers, and separate submittals to the Frederick-Firestone Fire District and St. Vrain Sanitation District are still required. Fees run through the same valuation-based Building Permit Fee Table — there is no distinct TI fee line.
Verified 2026-08-02 · Source
When you need this permit
- Electronic documents required as PDF attachments via the online portal; incomplete submittals will be rejected; all submittals are reviewed in the order received (per the TI checklist, REV 04.24)
- All plans, specifications, and calculations stamped by their respective design professionals (Colorado Licensed Architect and Colorado Registered Engineers)
- All General, Mechanical, Plumbing, and Electrical Contractors listed on the permit application; total building valuation plus total electrical valuation provided (detailed bids may be required if the Building Official deems valuations inaccurate)
- Architectural code analysis including change-of-occupancy analysis (if applicable), occupancy classification, sprinkler/fire alarm status, egress, accessibility (IBC Ch. 11), and life safety/egress plans per IBC 107.2.3
- IECC/energy code compliance documentation only if applicable — typically for a previously unoccupied shell space
- Structural package (IBC 1603 design criteria, foundations, framing) required only IF APPLICABLE to the TI scope
- Electrical one-line diagram required only with a service upgrade or when substantial load is added to the existing system; electrical site plan only if exterior electrical equipment is added, moved, or removed
- Kitchen hoods require manufacturer's shop drawings; spray/paint booths require engineered plans submitted to both the Fire Department and Building Department
- Separate submittals must be made to the Frederick-Firestone Fire District and St. Vrain Sanitation District
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical/Plumbing/Mechanical
Trade rough-ins before concealment, per approved stamped plans
- 2
Framing (if structural scope)
New walls/structural elements before cover, when the TI includes framing or structural work
- 3
Fire District Inspections
Frederick-Firestone Fire Protection District performs its own inspections under its separate submittal/approval
- 4
Final Inspection / Certificate of Occupancy
All work complete per approved plans; performed by SAFEbuilt Colorado under contract to the Town. A Temporary CO is available for $750 ($400 refundable if the final CO issues before TCO expiration)
See the full Firestone inspection guide — scheduling & re-inspection fees →
Tips
- Firestone treats tenant finish as its own permit track with a lighter submittal than new commercial construction — no soils report or civil package, and structural documentation only when the TI scope actually touches structure — but plans still must be stamped by Colorado-licensed design professionals.
- Incomplete submittals are rejected rather than held, and review is strictly first-come-first-served — submit a complete package to avoid losing your place in line.
- If the tenant finish changes the occupancy classification (e.g., office to restaurant), a change-of-occupancy analysis is required in the code analysis.
- Energy code (IECC) documentation typically applies only when finishing a previously unoccupied shell space — first-generation tenant finishes should budget for it.
- Fire district and sanitation district submittals are separate from and in addition to the Town permit — coordinate all three early.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Firestone building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Firestone.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Firestone
Commercial Tenant Finish (Tenant Improvement) Permit in other cities
Compare commercial tenant finish (tenant improvement) permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Firestone project checklist
Describe your project once and get every permit, document, and fee it triggers in Firestone — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →