Roofing Permit (Reroof) — Firestone, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://firestoneco.gov/DocumentCenter/View/9461/Firestone-Reroof-Requirements-2018-IRC-updated-81123
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Roofing Permit (Reroof) in Firestone, Colorado
Required for re-roofing in Firestone. Governed by 2018 IRC roofing provisions with a dedicated Town-published Reroof Requirements guide (REV 8.11.23) covering asphalt shingle re-roofing specifics.
Verified 2026-07-06 · Source
When you need this permit
- Shingle repair or replacement not exceeding 100 sq ft (one square) of covering per building is exempt from permit, per Ordinance No. 1029's amendment to IBC Section 105.2 item 14
- Where the existing roof already has two or more layers of any roof covering, all old material must be removed — roof re-cover (overlay) is NOT allowed in that case (IRC R908.3.1.1)
- Ice barrier is required, extending from the lowest roof edges to at least 24 inches inside the exterior wall line (IRC R905.1.2)
- Asphalt shingles must be fastened to solidly sheathed decks (R905.2.1); minimum 2:12 (17%) slope required for asphalt shingles (R905.2.2)
- Drip edge required on all edges including rakes, minimum 2-inch overlap (R905.2.8.5); double underlayment required for 2:12 up to 4:12 slopes (Table R905.1.1(2))
- Sidewalls must be step-flashed; continuous flashing at sidewalls is not acceptable (R905.2.8.3)
- Roofing material must be rated for 115 mph sustained wind per IRC Table R301.2(1).1 / Table R905.2.4.1
- Homeowners may pull the roof permit without a contractor's license only if the house is their primary residence and no contractor performs the work Owner-builderContractor
- OSHA-approved ladders required for inspection access to the roof; telescoping ladders are NOT acceptable
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Mid-Roof Inspection
Required when no more than 25% of the roof is complete; verifies ice & water shield installed 24 inches inside the exterior wall line, drip edge fastened at minimum 12-inch on-center with proper overlap, and underlayment sequencing at eaves/rakes
- 2
Final Roof Inspection
Completed roof covering verified against approved plans and applicable code; performed by SAFEbuilt Colorado
See the full Firestone inspection guide — scheduling & re-inspection fees →
Tips
- If your existing roof already has two layers of roofing material, Firestone requires full tear-off — a re-cover/overlay is not permitted at that point (IRC R908.3.1.1).
- The Mid-Roof inspection must occur before more than 25% of the roof is complete — schedule it early rather than waiting until the job is mostly done, or you risk having to expose completed sections for the inspector.
- Shingle or siding repairs under 100 sq ft (one square) per building are exempt from a permit entirely, per the Town's own amendment to IBC 105.2 — useful for small patch repairs.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Firestone building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Firestone
Roofing Permit (Reroof) in other cities
Compare roofing permit (reroof) fees across Colorado →
Look up this fee in a different city →