Fire Sprinkler and Fire Alarm System Permit in Firestone, Colorado

Colorado is home-rule with no statewide fire code floor, so which authority governs fire sprinkler/alarm work in Firestone had to be independently confirmed rather than assumed. Firestone has NO Town-run fire department -- fire-code plan review, permitting, and inspection for fire alarm and fire sprinkler systems are handled directly by the Frederick-Firestone Fire Protection District (FFFPD), a special district under Title 32, C.R.S. The localAmendments and commercial-building-permit/commercial-tenant-improvement-permit entries already note that multi-family and all commercial projects require FFFPD approval (303-833-2742), but FFFPD's own direct process had not previously been documented as its own permit type. RESEARCHED 2026-08-13: every fact below was read directly from FFFPD's own 2026 Fee Schedule PDF, Application for Plan Review PDF, and Submittal Requirements for Plan Review PDF (all downloaded and read directly), not inferred or search-summarized. Carries 'verified' confidence on that basis.

Verified 2026-08-13 · Source

When you need this permit

  • Frederick-Firestone Fire Protection District (FFFPD, 8426 Kosmerl Place, Frederick, CO 80504, 303-833-2742, fireprevention@fffd.us) is Firestone's fire-code plan-review and permitting authority for fire alarm and fire sprinkler systems -- consistent with the existing commercial-building-permit entry, which already directs multi-family and commercial submittals to FFFPD
  • FFFPD issues permits for installation of any new fire alarm or fire sprinkler system -- including fire pumps, kitchen hood suppression systems, bi-directional amplification systems, AES Radio systems, and underground fire lines -- and for any modification to an existing system, per FFFPD's own 2026 Fee Schedule
  • Fire Protection System Plan Review, Permit and Inspection Fees are assessed at 0.03 times the project value (materials and labor, as reported by the contractor), with a $300.00 minimum fee. If you are used to budgeting fire-protection review at a 0.025 rate, budget higher for work in Firestone.
  • Submission is electronic only -- thumb drive, PDF by email, or a file-sharing service such as Dropbox or Citrix -- sent directly to fireprevention@fffd.us; required items are a completed and signed FFFPD Application for Plan Review, unlocked stamped Civil/Architectural/MEP drawings, and unlocked Fire Safety System shop drawings with data/cut sheets (fire alarm, fire sprinkler, hazardous materials, kitchen hood suppression, mobile food vehicle, etc.), per FFFPD's own Submittal Requirements for Plan Review document
  • FFFPD does NOT accept deferred submittals except for Kitchen Hood Fire Suppression Systems and Commercial Paint Spray Booths -- all other fire protection systems must be part of the initial complete submittal
  • All submitted documents/drawings must be stamped by an independent Colorado-licensed Engineer, Architect, or NICET Level III designer specializing in fire protection, including a written report on how the design meets the currently adopted International Fire Code and current NFPA Standards
  • All fire suppression contractors and underground fire line installation contractors must be registered with the Colorado Division of Fire Prevention and Control, with current registration copies provided with every submittal
  • No numeric review-timeline figure, minimum or maximum, is published anywhere in FFFPD's own Application for Plan Review form or Submittal Requirements document. If you have worked with a different Front Range fire district that states a minimum review period, do not assume the same applies here.

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet — 0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Fire Protection System Plan Review, Permit, and Inspection FeeFFFPD 2026 Fee Schedule (PDF, downloaded and read directly 2026-08-13)
0.03 x total project value (materials and labor), $300.00 minimum
Additional Service (hourly rate)Frederick-Firestone Fire District 2026 Fee Schedule, Additional Fees
$100.00/hour
Failed InspectionFrederick-Firestone Fire District 2026 Fee Schedule, Additional Fees; failed inspections are billed at the hourly rate for a minimum of two hours
$100.00/hour, two (2)-hour minimum ($200.00 minimum)
Work performed without a permit
Double the original plan review and permit fee

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler and Fire Alarm System Permit permit actually take in Firestone?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire District Plan Review

    FFFPD reviews stamped Civil/Architectural/MEP drawings and fire safety system shop drawings under the currently adopted International Fire Code and NFPA Standards; accepted drawings are stamped and returned, and must be printed and kept on-site during construction

  2. 2

    Final Inspection

    On-site inspection of the installed fire alarm/sprinkler system by FFFPD; failed inspections are billed at the $100.00/hour rate, two-hour minimum

See the full Firestone inspection guide — scheduling & re-inspection fees →

Tips

  • Fire sprinkler/alarm work in Firestone is reviewed entirely outside the Town's own Building Division -- submit plans directly to FFFPD (fireprevention@fffd.us, 303-833-2742), and budget for both that District review and the Town's own Building Permit or Tenant Finish Permit for the underlying construction (already documented in the commercial-building-permit and commercial-tenant-improvement-permit entries).
  • FFFPD charges 0.03 times project value for fire-system permits. Mountain View Fire Rescue, the special district serving Dacono and Erie, uses 0.025 -- don't carry a rate from one district over to the other when estimating.
  • FFFPD does not accept deferred submittals except for Kitchen Hood Fire Suppression Systems and Commercial Paint Spray Booths -- plan for every other fire protection system to be part of the complete initial submittal, not a later add-on.
  • Unlike Mountain View Fire Rescue's published 10-business-day plan-review minimum, FFFPD publishes no comparable floor or ceiling anywhere in its own materials -- budget conservatively and confirm current turnaround directly with the District.

Frequently asked questions

Firestone requires a fire sprinkler and fire alarm system permit for: Frederick-Firestone Fire Protection District (FFFPD, 8426 Kosmerl Place, Frederick, CO 80504, 303-833-2742, fireprevention@fffd.us) is Firestone's fire-code plan-review and permitting authority for fire alarm and fire sprinkler systems -- consistent with the existing commercial-building-permit entry, which already directs multi-family and commercial submittals to FFFPD; FFFPD issues permits for installation of any new fire alarm or fire sprinkler system -- including fire pumps, kitchen hood suppression systems, bi-directional amplification systems, AES Radio systems, and underground fire lines -- and for any modification to an existing system, per FFFPD's own 2026 Fee Schedule; Fire Protection System Plan Review, Permit and Inspection Fees are assessed at 0.03 times the project value (materials and labor, as reported by the contractor), with a $300.00 minimum fee. If you are used to budgeting fire-protection review at a 0.025 rate, budget higher for work in Firestone.; Submission is electronic only -- thumb drive, PDF by email, or a file-sharing service such as Dropbox or Citrix -- sent directly to fireprevention@fffd.us; required items are a completed and signed FFFPD Application for Plan Review, unlocked stamped Civil/Architectural/MEP drawings, and unlocked Fire Safety System shop drawings with data/cut sheets (fire alarm, fire sprinkler, hazardous materials, kitchen hood suppression, mobile food vehicle, etc.), per FFFPD's own Submittal Requirements for Plan Review document; FFFPD does NOT accept deferred submittals except for Kitchen Hood Fire Suppression Systems and Commercial Paint Spray Booths -- all other fire protection systems must be part of the initial complete submittal; All submitted documents/drawings must be stamped by an independent Colorado-licensed Engineer, Architect, or NICET Level III designer specializing in fire protection, including a written report on how the design meets the currently adopted International Fire Code and current NFPA Standards; All fire suppression contractors and underground fire line installation contractors must be registered with the Colorado Division of Fire Prevention and Control, with current registration copies provided with every submittal; No numeric review-timeline figure, minimum or maximum, is published anywhere in FFFPD's own Application for Plan Review form or Submittal Requirements document. If you have worked with a different Front Range fire district that states a minimum review period, do not assume the same applies here.. If your project isn't listed, confirm with Town of Firestone Building Division (plan review/permit administration by Town staff; building inspections contracted to SAFEbuilt Colorado) at 303-833-3291 before starting work.

FFFPD assesses Fire Protection System Plan Review, Permit, and Inspection Fees at 0.03 times the total project value (materials and labor), with a $300.00 minimum, per the District's own 2026 Fee Schedule.

No numeric timeline -- minimum or maximum -- is published anywhere in FFFPD's own Application for Plan Review form or Submittal Requirements document. Contact the District directly (303-833-2742, fireprevention@fffd.us) for a current estimate.

You'll need: Application for Plan Review (Frederick-Firestone Fire Protection District); Stamped Civil, Architectural, and MEP Drawings; Fire Safety System Shop Drawings; Colorado Division of Fire Prevention and Control Contractor Registration. See the required-documents checklist on this page for details on each.

Firestone requires 2 inspection(s) for a fire sprinkler and fire alarm system permit, in order: Fire District Plan Review, Final Inspection. Schedule each through Town of Firestone Building Division (plan review/permit administration by Town staff; building inspections contracted to SAFEbuilt Colorado) (303-833-3291).

Apply through Town of Firestone Building Division (plan review/permit administration by Town staff; building inspections contracted to SAFEbuilt Colorado) at 9950 Park Avenue, Firestone, CO 80504. Phone: 303-833-3291, email: building@firestoneco.gov. Office hours: Monday through Friday, 8 a.m. to 5 p.m. (Town Hall hours). SAFEbuilt Colorado's local office is at 11409 Business Park Circle, Suite 350, Firestone, CO 80504, phone 303-774-1388, per SAFEbuilt's own site. Firestone-specific SAFEbuilt inspection contact: firestone-building@safebuilt.com / 303-774-0454, and Building Official Tim Moroney, tmoroney@safebuilt.com / 970-545-3555. That staffing detail comes from a SAFEbuilt contact listing rather than a live staff directory, so confirm current staffing with the Town before relying on a named contact.. Official information: https://www.firestoneco.gov/425/Building-Permits-Fees.

Firestone, Colorado has adopted: 2018 International Building Code (IBC), adopted by reference and locally amended as the 'Firestone Building and Construction Code' (FBCC) — Town of Firestone Building Guides page, https://firestoneco.gov/294/Building-Guides, and Ordinance No. 1029, https://firestoneco.gov/DocumentCenter/View/9387; 2018 International Residential Code (IRC), adopted by reference and locally amended; 2018 International Plumbing Code (IPC); 2018 International Mechanical Code (IMC); 2018 International Existing Building Code (IEBC); 2018 International Fuel Gas Code (IFGC); 2018 International Property Maintenance Code (IPMC); 2018 International Swimming Pool and Spa Code (ISPSC); 2018 International Energy Conservation Code (IECC); 2018 International Fire Code (IFC), per Ordinance No. 1029 chapter list (Chapter 15.32); 2023 National Electrical Code (NEC), adopted by reference per Ordinance No. 1029 (replacing the previously-adopted 2020 NEC); Ordinance No. 1029 (adopted following a June 21, 2023 public hearing) repealed and reenacted Firestone Municipal Code Chapters 15.04 (IBC), 15.06 (IRC), 15.08 (NEC), 15.10 (IEBC), 15.12 (IFGC), 15.14 (IMC), 15.16 (IPC), 15.18 (IPMC), 15.32 (IFC), 15.20 (ISPSC), and 15.36 (IECC) — source PDF, https://firestoneco.gov/DocumentCenter/View/9387/1029-AN-ORDINANCE-OF-THE-BOARD-OF-TRUSTEES-OF-THE-TOWN-OF-FIRESTONE-COLORADO. Local amendments apply — see the Firestone overview page for the full list.

No. Fire-code plan review, permitting, and inspection for fire alarm and fire sprinkler systems in Firestone are performed directly by the Frederick-Firestone Fire Protection District (FFFPD), not by the Town's Building Division. Firestone's own commercial and tenant-finish submittal checklists require separate FFFPD approval in addition to the Town's Building Permit.

Sources & verification

Verified against official sources. Last reviewed 2026-08-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Firestone building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Firestone's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Firestone yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.