EV Charger / EVSE Permit in Unincorporated San Juan County, New Mexico
San Juan County self-administers electrical permitting directly (not routed through the New Mexico Construction Industries Division) and does not publish a distinct EV charger/EVSE fee line item on its Electrical Permit Application (rev. 04/11/2023) fee table. The application's itemized fee table has no dedicated EV charger/EVSE category. Re-chased 2026-07-20 against the full itemized fee table: the most directly applicable published category for a standalone EVSE circuit added without a new/upgraded electrical service is "FEEDER AND BRANCH CIRCUITS," billed by the structure's heated square footage ($0.03/sq ft residential, $0.06/sq ft commercial); if the installation instead requires a new or upgraded electrical service, the county's tiered "ELECTRIC SERVICE" amperage table applies. (Solar PV and Wind Generator installations use a distinct $25/kW-or-fraction rate, which does not apply to EVSE circuits.) Installation must comply with the adopted 2020 NEC (with 2020 New Mexico Electrical Code amendments).
Verified 2026-07-20 · Source
When you need this permit
- Electrical Permit required for EV charger/EVSE circuit installation in unincorporated San Juan County, using the county's own Electrical Permit Application (rev. 04/11/2023) — not a New Mexico CID permit
- Valid New Mexico electrical contractor license (license number and expiration date required on the application), unless performing work as an exempt homeowner Contractor
- One Line Diagram required if the installation involves a service upgrade of 200 amps or above
- Installation must comply with the adopted 2020 National Electrical Code (NFPA 70) and 2020 New Mexico Electrical Code
- No distinct EV charger/EVSE fee line, expedited timeline, or SolarAPP+-style instant-permitting platform was found published by the county as of this review
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
EVSE circuit, feeders, and raceway complete to termination before covering
- 2
Electrical Final
EVSE panel/breaker labeled, cover plate on, equipment connected and operational
See the full Unincorporated San Juan County inspection guide — scheduling & re-inspection fees →
Tips
- San Juan County's electrical fee table has no dedicated EV charger/EVSE line item -- a standalone circuit addition is billed under "Feeder and Branch Circuits" ($0.03/sq ft of heated residential space), while a new/upgraded service is billed under the tiered "Electric Service" amperage table; call the Building Division at (505) 334-4313 before applying to confirm which category applies to your specific installation.
- Inspection requests require at least 24 hours' notice; a $75.00 reinspection fee applies if work fails inspection.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated San Juan County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated San Juan County
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across New Mexico →
Look up this fee in a different city →
Related guides
Now live
Build your Unincorporated San Juan County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated San Juan County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →