Demolition Permit in Taylorsville, Utah

Required for partial or complete demolition of structures in Taylorsville. A flat-fee permit per the Taylorsville Consolidated Fee Schedule.

Verified 2026-06-30 · Source

When you need this permit

  • Complete demolition of any structure
  • Partial demolition involving structural elements
  • Removal of load-bearing walls

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition (Residential and Commercial) — Flat FeeTaylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 (taylorsvilleut.gov/home/showdocument?id=10939) — listed as 'Demolition (Residential and Commercial)' under the Flat Fee Permits table. Note: the section heading reads 'Flat Fee Permits per Residential Location (Except Demolition)' — the demolition line applies to both residential and commercial regardless.
$60.00

Review timeline

Plan reviewTypical estimate — confirm current times with the Taylorsville building department
~3–10 business days

How long did your Demolition Permit permit actually take in Taylorsville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Pre-Demolition

    Verify utility disconnects are complete and any required asbestos/DAQ clearance is obtained before work begins

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped, site conditions verified

See the full Taylorsville inspection guide — scheduling & re-inspection fees →

Tips

  • Taylorsville's demolition permit is a flat $60 fee for both residential and commercial demolitions.
  • Utilities must be formally disconnected by the respective utility companies before demolition — Taylorsville Building Department will verify.
  • The Taylorsville Helpful Links page directs residents to the Utah Department of Air Quality (deq.utah.gov/Divisions/daq/index.htm) for demolition work and asbestos concerns.
  • Federal NESHAP regulations require asbestos inspection before demolition of structures that may contain asbestos-containing materials.

Frequently asked questions

Yes, for structures that may contain asbestos. Taylorsville's Helpful Links page specifically directs applicants to the Utah Department of Air Quality for demolition-related air quality and asbestos concerns. Federal NESHAP regulations also apply.

In Taylorsville, the published Demolition (Residential and Commercial) — Flat Fee is: $60.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for a demolition permit in Taylorsville typically runs 3–10 business days. This is an estimate, not a published figure — confirm current review times with Taylorsville City Building Department at (801) 955-2030.

You'll need: Permit Application; Utility Disconnect Confirmation. Depending on your project, Taylorsville may also ask for: Asbestos / DAQ Clearance. See the required-documents checklist on this page for details on each.

Taylorsville requires 2 inspection(s) for a demolition permit, in order: Pre-Demolition, Final / Site Clear. Schedule each through Taylorsville City Building Department ((801) 955-2030).

Apply through Taylorsville City Building Department at 2600 Taylorsville Blvd., Taylorsville, UT 84129. Phone: (801) 955-2030, email: mcortez@taylorsvilleut.gov. Office hours: Mon–Fri 8:00 a.m. – 5:00 p.m.; Inspections 9:00 a.m. – 4:00 p.m.. Official information: https://www.taylorsvilleut.gov/government/building-department.

Taylorsville, Utah has adopted: 2024 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); CURRENT as of 7/1/2026. Confirmed live on the Taylorsville Building Department page (taylorsvilleut.gov/government/building-department, re-fetched 2026-07-16), which itself now states the current statewide code table verbatim: '2024 I.B.C., 2021 I.R.C., 2024 I.P.C., 2024 I.M.C., 2024 I.F.G.C., 2024 I.E.C.C., 2023 N.E.C.' Supersedes the 2021 IBC, which governed through 6/30/2026.; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); UNCHANGED by the 7/1/2026 code cycle — confirmed both by the live statute and by Taylorsville's own building page (re-fetched 2026-07-16, listing '2021 I.R.C.').; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); CURRENT as of 7/1/2026, confirmed live on the Taylorsville Building Department page (re-fetched 2026-07-16). Supersedes the 2021 IPC, which governed through 6/30/2026.; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); CURRENT as of 7/1/2026, confirmed live on the Taylorsville Building Department page (re-fetched 2026-07-16). Supersedes the 2021 IMC, which governed through 6/30/2026.; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); CURRENT as of 7/1/2026, confirmed live on the Taylorsville Building Department page (re-fetched 2026-07-16). Supersedes the 2021 IFGC, which governed through 6/30/2026.; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); CURRENT as of 7/1/2026, confirmed live on the Taylorsville Building Department page (re-fetched 2026-07-16). ONE statewide edition — the statute does not split residential/commercial IECC editions. Supersedes the 2021 IECC, which governed through 6/30/2026.; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 code cycle statewide. CORRECTION (2026-07-20, supersedes the 2026-07-16 note below): the 07-16 edit claimed Taylorsville's page had been updated to 'correctly' list 2023 N.E.C. and that the prior 2020-NEC lag was resolved — that was wrong. The page genuinely contradicts itself and still does as of this re-check: a summary table near the top states the statewide-adopted codes verbatim ('2024 I.B.C., 2021 I.R.C., 2024 I.P.C., 2024 I.M.C., 2024 I.F.G.C., 2024 I.E.C.C., 2023 N.E.C.'), but the page's own FAQ section separately answers 'What codes and standards does the building department use?' with: 'Currently we are using the 2021 I-codes with 2017 A.N.S.I. 117.1 as the accessibility standard, and the 2020 National Electrical Code.' Confirmed via a 2026-07-08 Wayback snapshot (predating the 07-16 edit) already showing that exact FAQ text, and independently re-confirmed live 2026-07-20 — the page has not changed; the 07-16 edit simply picked one side of an internal contradiction and declared it resolved. Reported here as-is rather than guessing which statement the department actually enforces in practice.; NOTE (2026-07-20, supersedes the 2026-07-16 corpus-staleness note below): the IBC/IRC/IPC/IMC/IFGC/IECC lines above match the page's top summary table verbatim, independently re-confirmed 2026-07-20. But that table is not the whole story — see the NEC line's correction above for the page's separate, contradicting FAQ answer, which claims the department is 'currently using' the 2021 I-codes generally (not just for NEC). Treat every 'current as of 7/1/2026' framing above as citing the summary table specifically, not as a claim that Taylorsville's practice has been independently confirmed to match it. The International Fire Code (IFC) is not adopted anywhere in §15A-2-103 and is not listed on Taylorsville's page either — that part of the original 07-16 note still holds..

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Taylorsville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.