Residential Building Permit in Taylorsville, Utah

Required for new residential construction, additions, structural alterations, and work requiring plan review in Taylorsville. Permit fees are valuation-based per the Taylorsville City Consolidated Fee Schedule. Valuation for new construction and additions is calculated using Taylorsville's published per-square-foot rates.

Verified 2026-06-30 · Source

When you need this permit

  • New single-family or multi-family residential construction
  • Additions or structural modifications to existing structures
  • Conversion of non-habitable space to habitable space
  • Any work requiring plan review under the adopted building codes

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit — valuation under $2,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 (taylorsvilleut.gov/home/showdocument?id=10939)
$24.00 for the first $500, plus $3.50 for each additional $100 or fraction thereof, to and including $2,000
Building Permit — valuation $2,000 to $25,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$76.50 for the first $2,000, plus $16.50 for each additional $1,000 or fraction thereof, to and including $25,000
Building Permit — valuation $25,000 to $50,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$456.00 for the first $25,000, plus $12.00 for each additional $1,000 or fraction thereof, to and including $50,000
Building Permit — valuation $50,000 to $100,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$765.00 for the first $50,000, plus $8.50 for each additional $1,000 or fraction thereof, to and including $100,000
Building Permit — valuation $100,000 to $500,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$1,181.00 for the first $100,000, plus $6.50 for each additional $1,000 or fraction thereof, to and including $500,000
Building Permit — valuation $500,000 to $1,000,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$3,781.00 for the first $500,000, plus $5.50 for each additional $1,000 or fraction thereof, to and including $1,000,000
Building Permit — valuation over $1,000,000Taylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$6,531.00 for the first $1,000,000, plus $4.50 for each additional $1,000 or fraction thereof
Residential Valuation Rate — Main Floor / Second FloorTaylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026 — used to calculate project valuation before applying the permit fee tiers above
$88.03 per sq. ft.
Residential Valuation Rate — Rough BasementTaylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$36.50 per sq. ft.
Residential Valuation Rate — Finished BasementTaylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$15.00 per sq. ft.
Residential Valuation Rate — Garage / ShedTaylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$34.18 per sq. ft.
Residential Valuation Rate — Carport / Covered DeckTaylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$25.00 per sq. ft.
Residential Valuation Rate — DeckTaylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$20.00 per sq. ft.
Residential Valuation Rate — Converted Garage/Carport to Living SpaceTaylorsville City Consolidated Fee Schedule, Revised & Approved March 19, 2026
$45.00 per sq. ft.

Review timeline

Plan reviewTaylorsville’s published plan-review target
1–10 business days

How long did your Residential Building Permit permit actually take in Taylorsville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footing

    Before concrete pour — forms, rebar, anchor bolts

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation or wall cover

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete, ready for certificate of occupancy

See the full Taylorsville inspection guide — scheduling & re-inspection fees →

Tips

  • Taylorsville's building department states plan review takes at most 10 business days; re-submitting plans resets the review clock.
  • Submit and manage permits through the EnerGov Self-Service portal at portal.taylorsvilleut.gov/EnerGov_Prod/selfservice.
  • Project valuation for new construction is calculated using Taylorsville's published per-square-foot rates (e.g., $88.03/sq ft for main floor living area), then run through the valuation-based fee table.
  • Unified Fire Authority provides fire plan review and inspections for Taylorsville — coordinate fire sprinkler and egress requirements early.
  • Water and sewer in Taylorsville is served by the Taylorsville/Bennion Improvement District (tbid.org) — contact them early for connection requirements.
  • The fee schedule Appendix references the IBC 2008 Building Valuation Table for commercial new construction — use that for commercial projects.

Frequently asked questions

Taylorsville requires a residential building permit for: New single-family or multi-family residential construction; Additions or structural modifications to existing structures; Conversion of non-habitable space to habitable space; Any work requiring plan review under the adopted building codes. If your project isn't listed, confirm with Taylorsville City Building Department at (801) 955-2030 before starting work.

Taylorsville uses a two-step valuation method. First, calculate project valuation using published per-square-foot rates (e.g., $88.03/sq ft for main floor living area, $34.18/sq ft for garage, $20.00/sq ft for deck). Then look up the permit fee: for example, valuation of $30,000 → $456 + (5 × $12) = $516. The Consolidated Fee Schedule was revised and approved March 19, 2026.

Taylorsville's building department states plan review takes at most 10 business days. Re-submitting plans resets this period. The department is open Mon–Fri 8 a.m.–5 p.m.; call (801) 955-2030.

You'll need: Building Permit Application; Construction Plans; Energy Code Compliance Documentation. Depending on your project, Taylorsville may also ask for: Engineered Truss Plans. See the required-documents checklist on this page for details on each.

Taylorsville requires 4 inspection(s) for a residential building permit, in order: Foundation / Footing, Framing, Insulation, Final. Schedule each through Taylorsville City Building Department ((801) 955-2030).

Apply through Taylorsville City Building Department at 2600 Taylorsville Blvd., Taylorsville, UT 84129. Phone: (801) 955-2030, email: mcortez@taylorsvilleut.gov. Office hours: Mon–Fri 8:00 a.m. – 5:00 p.m.; Inspections 9:00 a.m. – 4:00 p.m.. Official information: https://www.taylorsvilleut.gov/government/building-department.

Taylorsville, Utah has adopted: 2024 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); CURRENT as of 7/1/2026. Confirmed live on the Taylorsville Building Department page (taylorsvilleut.gov/government/building-department, re-fetched 2026-07-16), which itself now states the current statewide code table verbatim: '2024 I.B.C., 2021 I.R.C., 2024 I.P.C., 2024 I.M.C., 2024 I.F.G.C., 2024 I.E.C.C., 2023 N.E.C.' Supersedes the 2021 IBC, which governed through 6/30/2026.; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); UNCHANGED by the 7/1/2026 code cycle — confirmed both by the live statute and by Taylorsville's own building page (re-fetched 2026-07-16, listing '2021 I.R.C.').; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); CURRENT as of 7/1/2026, confirmed live on the Taylorsville Building Department page (re-fetched 2026-07-16). Supersedes the 2021 IPC, which governed through 6/30/2026.; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); CURRENT as of 7/1/2026, confirmed live on the Taylorsville Building Department page (re-fetched 2026-07-16). Supersedes the 2021 IMC, which governed through 6/30/2026.; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); CURRENT as of 7/1/2026, confirmed live on the Taylorsville Building Department page (re-fetched 2026-07-16). Supersedes the 2021 IFGC, which governed through 6/30/2026.; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); CURRENT as of 7/1/2026, confirmed live on the Taylorsville Building Department page (re-fetched 2026-07-16). ONE statewide edition — the statute does not split residential/commercial IECC editions. Supersedes the 2021 IECC, which governed through 6/30/2026.; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 code cycle statewide. CORRECTION (2026-07-20, supersedes the 2026-07-16 note below): the 07-16 edit claimed Taylorsville's page had been updated to 'correctly' list 2023 N.E.C. and that the prior 2020-NEC lag was resolved — that was wrong. The page genuinely contradicts itself and still does as of this re-check: a summary table near the top states the statewide-adopted codes verbatim ('2024 I.B.C., 2021 I.R.C., 2024 I.P.C., 2024 I.M.C., 2024 I.F.G.C., 2024 I.E.C.C., 2023 N.E.C.'), but the page's own FAQ section separately answers 'What codes and standards does the building department use?' with: 'Currently we are using the 2021 I-codes with 2017 A.N.S.I. 117.1 as the accessibility standard, and the 2020 National Electrical Code.' Confirmed via a 2026-07-08 Wayback snapshot (predating the 07-16 edit) already showing that exact FAQ text, and independently re-confirmed live 2026-07-20 — the page has not changed; the 07-16 edit simply picked one side of an internal contradiction and declared it resolved. Reported here as-is rather than guessing which statement the department actually enforces in practice.; NOTE (2026-07-20, supersedes the 2026-07-16 corpus-staleness note below): the IBC/IRC/IPC/IMC/IFGC/IECC lines above match the page's top summary table verbatim, independently re-confirmed 2026-07-20. But that table is not the whole story — see the NEC line's correction above for the page's separate, contradicting FAQ answer, which claims the department is 'currently using' the 2021 I-codes generally (not just for NEC). Treat every 'current as of 7/1/2026' framing above as citing the summary table specifically, not as a claim that Taylorsville's practice has been independently confirmed to match it. The International Fire Code (IFC) is not adopted anywhere in §15A-2-103 and is not listed on Taylorsville's page either — that part of the original 07-16 note still holds..

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Taylorsville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.