Fence Permit in West Jordan, Utah

Required for fences over 6 feet in most residential zones in West Jordan (fences 6 feet and under are generally exempt from a building permit; a zoning/setback review may still apply). A fence permit is issued as a building permit and charged on the valuation-based building permit fee schedule — West Jordan publishes no separate fence line item.

Verified 2026-07-01 · Source

When you need this permit

  • New fence construction
  • Replacement of existing fence in a different location or height
  • Fences over 6 feet in most residential zones

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Fence Permit (issued as a building permit; fences over 6 ft)West Jordan FY2026 Consolidated Fee Schedule item 3a — 'Building Permit based on valuation (base fee plus rate)'; valuation per ICC Building Valuation Data. There is no standalone fence fee line because a fence over 6 ft is permitted as a building permit; the $70 miscellaneous-minimum applies only to plumbing/electrical/mechanical permits, not fences.
Assessed on project valuation using West Jordan's building permit fee (base fee plus rate by valuation), per the FY2026 Consolidated Fee Schedule

Review timeline

Plan reviewTypical estimate — confirm current times with the West Jordan building department
~3–10 business days

How long did your Fence Permit permit actually take in West Jordan?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Verify fence matches approved plan and meets height and setback requirements per West Jordan zoning code

See the full West Jordan inspection guide — scheduling & re-inspection fees →

Tips

  • Front yard fences in West Jordan's residential zones are typically limited to 4 feet; side and rear fences to 6 feet — verify with the Planning Department for your specific zone.
  • Call 811 before digging fence post holes to locate underground utilities.
  • Check for utility easements on your property before selecting fence locations.

Frequently asked questions

West Jordan generally requires a permit for new fence construction. The Consolidated Fee Schedule (Ord. 25-48) does not list a standalone fence permit fee — contact the Building & Safety Division at (801) 569-5050 to confirm the applicable fee and whether your specific project requires a permit.

In West Jordan, the published Fence Permit (issued as a building permit; fences over 6 ft) is: Assessed on project valuation using West Jordan's building permit fee (base fee plus rate by valuation), per the FY2026 Consolidated Fee Schedule. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for a fence permit in West Jordan typically runs 3–10 business days. This is an estimate, not a published figure — confirm current review times with West Jordan Building & Safety Division at (801) 569-5050.

You'll need: Building Permit Application (via West Jordan Public Portal). Depending on your project, West Jordan may also ask for: Site Plan. See the required-documents checklist on this page for details on each.

West Jordan requires 1 inspection(s) for a fence permit, in order: Final. Schedule each through West Jordan Building & Safety Division ((801) 569-5050).

Apply through West Jordan Building & Safety Division at 8000 South Redwood Road, West Jordan, UT 84088. Phone: (801) 569-5050, email: wjplanning@westjordan.utah.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.westjordan.utah.gov/community-development/building-and-safety/.

West Jordan, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — currently in effect as of July 1, 2026, superseding the 2021 IBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(a)); West Jordan's own Design Criteria document (rev. 10/2025) predates this transition — see NOTE below; 2021 International Residential Code (IRC), including Appendix AQ — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(b)); 2024 International Plumbing Code (IPC) — currently in effect as of July 1, 2026, superseding the 2021 IPC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(d)); 2024 International Mechanical Code (IMC) — currently in effect as of July 1, 2026, superseding the 2021 IMC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(e)); 2024 International Fuel Gas Code (IFGC) — currently in effect as of July 1, 2026, superseding the 2021 IFGC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(f)); 2024 International Energy Conservation Code (IECC) — currently in effect statewide as of July 1, 2026, a single edition with no residential/commercial split under current law (Utah Code § 15A-2-103(1)(h)); Historical (superseded): West Jordan's Design Criteria document (rev. 10/2025) had cited a 2015 IECC edition for residential and a separate 2021 IECC edition for commercial — both are now superseded by the single 2024 IECC per § 15A-2-103(1)(h); not independently re-fetched on 2026-07-16 (the Design Criteria PDF was not located live this session — West Jordan's Building & Safety page links a 'Codes & Design Criteria' resource but the document content was not directly accessible), so whether the city has updated this document is unconfirmed as of this date; 2024 International Existing Building Code (IEBC) — currently in effect as of July 1, 2026, superseding the 2021 IEBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(i)); 2021 International Fire Code (IFC) — West Jordan Design Criteria (rev. 10/2025) (not adopted under Utah Code § 15A-2-103, which does not list an IFC edition; edition unconfirmed for the current period); 2023 National Electrical Code (NEC) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(g)); 1997 Uniform Code for Abatement of Dangerous Buildings — West Jordan Design Criteria (rev. 10/2025); NOTE (updated 2026-07-16): the July 1, 2026 transition forecast in the prior version of this entry has now occurred — confirmed live against Utah Code § 15A-2-103, current version (effective 7/1/2026, superseded 1/1/2027), read at le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html. West Jordan's Building & Safety Division webpage (westjordan.utah.gov/community-development/building-and-safety/), checked live 2026-07-16, still hosts a downloadable 'Special Inspection Agreement' form labeled '2021 IBC' — consistent with the Design Criteria document (rev. 10/2025) predating the statewide transition; confirm current status with the Building & Safety Division for any project submitted on or after July 1, 2026. Local amendments apply — see the West Jordan overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Jordan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.