Fire Sprinkler Permit in West Jordan, Utah

Required for installation of an automatic fire sprinkler system in West Jordan. Unlike several smaller neighboring cities, West Jordan operates its own city Fire Department (not Unified Fire Authority or a special fire district) — the West Jordan Fire Department's Fire Marshal's Office handles fire sprinkler plan review, permitting, and inspection directly, billed through the same Consolidated Fee Schedule (Ord. 25-48) as other city permits. The City has adopted the 2024 International Fire Code (IFC) and Appendices B, C, and D.

Verified 2026-07-19 · Source

When you need this permit

  • Installation of an automatic fire sprinkler system, commercial or multi-family
  • Permit required under the 2024 International Fire Code and Appendices B, C, D as adopted by West Jordan
  • Fee is tiered by number of sprinkler heads (commercial) or per building (multi-family housing)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Fire Sprinkler Inspection — Commercial, 1-25 sprinkler heads (includes plan review)West Jordan Consolidated Fee Schedule (Ord. 25-48, updated March 6, 2026), 'FIRE INSPECTIONS' section, item 4(a)(i): '1-25 sprinkler heads (includes plan review) — $127.' Confirmed live 2026-07-19.
$127
Fire Sprinkler Inspection — Commercial, 26-99 sprinkler headsWest Jordan Consolidated Fee Schedule (Ord. 25-48), item 4(a)(ii).
$171
Fire Sprinkler Inspection — Commercial, 100-1,000 sprinkler headsWest Jordan Consolidated Fee Schedule (Ord. 25-48), item 4(a)(iii).
$336
Fire Sprinkler Inspection — Commercial, 1,001-4,000 sprinkler headsWest Jordan Consolidated Fee Schedule (Ord. 25-48), item 4(a)(iv).
$420
Fire Sprinkler Inspection — Commercial, 4,000+ sprinkler headsWest Jordan Consolidated Fee Schedule (Ord. 25-48), item 4(a)(v).
$504
Fire Sprinkler Inspection — Multi-Family Housing, 1-99 sprinkler headsWest Jordan Consolidated Fee Schedule (Ord. 25-48), item 4(b)(i).
$171 per building
Fire Sprinkler Inspection — Multi-Family Housing, 100+ sprinkler headsWest Jordan Consolidated Fee Schedule (Ord. 25-48), item 4(b)(ii).
$253 per building
Permit Processing FeeWest Jordan Consolidated Fee Schedule, Ord. 25-48.
$12 per permit issued

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler Permit permit actually take in West Jordan?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire Sprinkler Inspection

    The 1-25 head tier fee explicitly includes plan review; inspection scope for larger tiers is not separately broken out on the published fee schedule.

See the full West Jordan inspection guide — scheduling & re-inspection fees →

Tips

  • West Jordan operates its own Fire Department — unlike several nearby smaller cities served by Unified Fire Authority or a special fire district, West Jordan's own Fire Marshal's Office (Paul Brockbank) handles sprinkler permitting directly, billed through the same Consolidated Fee Schedule as other city permits.
  • West Jordan's fee schedule bills fire sprinkler permits by head count under 'FIRE INSPECTIONS,' not as a separate 'plan review + permit' split like some neighboring fire districts — the 1-25 head tier ($127) explicitly bundles plan review into the fee.
  • Multi-family housing sprinkler fees are billed per building ($171 for 1-99 heads, $253 for 100+ heads), separate from the per-head commercial tiers.

Frequently asked questions

West Jordan requires a fire sprinkler permit for: Installation of an automatic fire sprinkler system, commercial or multi-family; Permit required under the 2024 International Fire Code and Appendices B, C, D as adopted by West Jordan; Fee is tiered by number of sprinkler heads (commercial) or per building (multi-family housing). If your project isn't listed, confirm with West Jordan Building & Safety Division at (801) 569-5050 before starting work.

Per the West Jordan Consolidated Fee Schedule (Ord. 25-48): commercial fire sprinkler fees range from $127 (1-25 heads, includes plan review) to $504 (4,000+ heads). Multi-family housing is billed per building: $171 (1-99 heads) or $253 (100+ heads). A $12 permit processing fee also applies.

West Jordan does not publish a plan-review timeline for this permit. Contact West Jordan Building & Safety Division at (801) 569-5050 for current turnaround.

You'll need: Fire Permit Application; Fire Sprinkler System Plans. See the required-documents checklist on this page for details on each.

West Jordan requires 1 inspection(s) for a fire sprinkler permit, in order: Fire Sprinkler Inspection. Schedule each through West Jordan Building & Safety Division ((801) 569-5050).

Apply through West Jordan Building & Safety Division at 8000 South Redwood Road, West Jordan, UT 84088. Phone: (801) 569-5050, email: wjplanning@westjordan.utah.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.westjordan.utah.gov/community-development/building-and-safety/.

West Jordan, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — currently in effect as of July 1, 2026, superseding the 2021 IBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(a)); West Jordan's own Design Criteria document (rev. 10/2025) predates this transition — see NOTE below; 2021 International Residential Code (IRC), including Appendix AQ — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(b)); 2024 International Plumbing Code (IPC) — currently in effect as of July 1, 2026, superseding the 2021 IPC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(d)); 2024 International Mechanical Code (IMC) — currently in effect as of July 1, 2026, superseding the 2021 IMC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(e)); 2024 International Fuel Gas Code (IFGC) — currently in effect as of July 1, 2026, superseding the 2021 IFGC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(f)); 2024 International Energy Conservation Code (IECC) — currently in effect statewide as of July 1, 2026, a single edition with no residential/commercial split under current law (Utah Code § 15A-2-103(1)(h)); Historical (superseded): West Jordan's Design Criteria document (rev. 10/2025) had cited a 2015 IECC edition for residential and a separate 2021 IECC edition for commercial — both are now superseded by the single 2024 IECC per § 15A-2-103(1)(h); not independently re-fetched on 2026-07-16 (the Design Criteria PDF was not located live this session — West Jordan's Building & Safety page links a 'Codes & Design Criteria' resource but the document content was not directly accessible), so whether the city has updated this document is unconfirmed as of this date; 2024 International Existing Building Code (IEBC) — currently in effect as of July 1, 2026, superseding the 2021 IEBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(i)); 2021 International Fire Code (IFC) — West Jordan Design Criteria (rev. 10/2025) (not adopted under Utah Code § 15A-2-103, which does not list an IFC edition; edition unconfirmed for the current period); 2023 National Electrical Code (NEC) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(g)); 1997 Uniform Code for Abatement of Dangerous Buildings — West Jordan Design Criteria (rev. 10/2025); NOTE (updated 2026-07-16): the July 1, 2026 transition forecast in the prior version of this entry has now occurred — confirmed live against Utah Code § 15A-2-103, current version (effective 7/1/2026, superseded 1/1/2027), read at le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html. West Jordan's Building & Safety Division webpage (westjordan.utah.gov/community-development/building-and-safety/), checked live 2026-07-16, still hosts a downloadable 'Special Inspection Agreement' form labeled '2021 IBC' — consistent with the Design Criteria document (rev. 10/2025) predating the statewide transition; confirm current status with the Building & Safety Division for any project submitted on or after July 1, 2026. Local amendments apply — see the West Jordan overview page for the full list.

No. West Jordan operates its own city Fire Department, separate from Unified Fire Authority (which does not list West Jordan among its member communities). The West Jordan Fire Department's own Fire Marshal's Office handles fire sprinkler plan review and permitting.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Jordan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.