Demolition Permit — West Jordan, Utah · Requirements sheet
Verified 2026-07-01 · Source: https://www.westjordan.utah.gov/community-development/building-and-safety/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in West Jordan, Utah
Required for partial or complete demolition of structures in West Jordan. The demolition permit requires pre-demolition utility disconnections, a Department of Air Quality approval letter, and a Salt Lake County Health Department pre-demolition inspection form.
Verified 2026-07-01 · Source
When you need this permit
- Complete demolition of any structure
- Partial demolition involving structural elements
- Utility disconnection from Rocky Mountain Power (888-221-7070) and Enbridge Gas (800-323-5517) prior to permit
- West Jordan Engineering Department verification of sewer and water disconnection (call 801-569-5070)
- Utah Department of Air Quality approval letter (deq.utah.gov/air-quality/requirements-prior-to-demolition or 801-536-4000)
- Salt Lake County Health Department pre-demolition inspection form from a registered inspector (385-468-4100)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Pre-Demolition
Verify utility disconnects, Air Quality approval, and Health Department pre-demolition inspection are complete before work begins
- 2
Final / Site Clear
Site cleared, foundation removed or capped, erosion control in place
See the full West Jordan inspection guide — scheduling & re-inspection fees →
Tips
- West Jordan's demolition process requires four separate agency steps before the permit is issued — start early with Rocky Mountain Power, Enbridge Gas, and the Engineering Department for sewer/water disconnection.
- The Department of Air Quality must approve the project before applying for the demolition permit — see deq.utah.gov/air-quality/requirements-prior-to-demolition.
- A pre-demolition inspection by a Salt Lake County Health Department registered inspector is required — find inspectors at saltlakecounty.gov/health/construction-contractors/predemolition.
- If the contractor disturbs painted or coated surfaces greater than 6 sq ft interior or 20 sq ft exterior in pre-1978 construction, lead-based paint renovation rules apply — contact Salt Lake County Health at 385-468-4100.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Jordan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in West Jordan
Demolition Permit in other cities
Compare demolition permit fees across Utah →
Look up this fee in a different city →