Demolition Permit — Unincorporated Uintah County, Utah · Requirements sheet
Verified 2026-07-08 · Source: https://cms1files.revize.com/uintahcountyut/document_center/CommissionMeetings/most%20recent%20fee%20schedule.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Unincorporated Uintah County, Utah
Required for demolition of any structure in unincorporated Uintah County. Includes required Fire Marshal and Health Department sign-off, plus a state Division of Air Quality notification.
Verified 2026-07-08 · Source
When you need this permit
- Complete demolition of any structure
- Asbestos inspection prior to demolition (hired-contractor demolitions; owner-performed demolition of a private home is exempt per Utah House Bill 285)
- Division of Air Quality notification at least two weeks prior to demolition (required even if no asbestos is found)
- Fire Marshal and Tri-County Health Department sign-off on the Demolition Application
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Pre-Demolition
Utility disconnects and any required asbestos clearance verified before work begins
- 2
Final / Site Clear
Site cleared; call for inspection after the building is removed
See the full Unincorporated Uintah County inspection guide — scheduling & re-inspection fees →
Tips
- Demolition is a $0.00 (no-charge) permit under the current Uintah County Fee Schedule (Ord. 08-06-2025 O1) — this is a more recent, authoritative source than the county's older standalone Demolition Application PDF, which still prints a $100 fee line.
- Any new structure built to replace a demolished one requires its own separate building permit application.
- Notify the state Division of Air Quality at least two weeks before demolition, even if no asbestos is present — this is a separate state requirement from the county permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Uintah County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Uintah County
Demolition Permit in other cities
Compare demolition permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Uintah County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Uintah County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →