Electrical Permit in Unincorporated Uintah County, Utah

Required for residential electrical service upgrades/replacements, temporary power pedestals, and agricultural electrical service in unincorporated Uintah County. EV charger/EVSE installation is electrical work and falls under this general Electrical Permit; the county's Permit Fee by Activity & Flat Fee table (Ord. 08-06-2025 O1) does not publish an EV-specific line item (checked 2026-07-19).

Verified 2026-07-08 · Source

When you need this permit

  • Residential electrical service upgrade or replacement
  • Temporary construction power pedestal installation
  • Agricultural electrical service
  • Any new electrical work in an otherwise-exempt agricultural building

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential Electrical Service Upgrade or ReplacementUintah County Fee Schedule, Uintah County Code § 3.30.010 (Ord. 08-06-2025 O1, enacted 8/12/2025) — Permit Fee by Activity & Flat Fee table.
$50.00
Temporary Power PedestalsUintah County Fee Schedule, Ord. 08-06-2025 O1.
$50.00
Agricultural Electrical ServiceUintah County Fee Schedule, Ord. 08-06-2025 O1.
$50.00
Commercial/Utility Equipment and Commercial Electrical ServiceUintah County Fee Schedule, Ord. 08-06-2025 O1.
$200.00
Inspection/Re-Inspection FeeUintah County Fee Schedule, Ord. 08-06-2025 O1.
$50.00

Review timeline

Plan reviewTypical estimate — confirm current times with the Unincorporated Uintah County building department
~10–14 business days

How long did your Electrical Permit permit actually take in Unincorporated Uintah County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Construction Power Inspection

    Pedestal or meter base installed with weatherproof GFCI outlets, ready to energize

  2. 2

    Rough-In

    Wiring, boxes, and panel installed before walls are closed

  3. 3

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled

See the full Unincorporated Uintah County inspection guide — scheduling & re-inspection fees →

Tips

  • The 2023 National Electrical Code (statewide) governs all electrical work in unincorporated Uintah County, even though the county's own Building Code page still lists the 2020 NEC.
  • A permanent electric meter will only be set once the structure is built to code, all required inspections are complete, and a Certificate of Occupancy has been issued — per the county's Agreement for Electrical Meter.
  • Temporary construction power may only be used during construction of a code-compliant building; it cannot be used for permanent occupancy.
  • Installing a home EV charger (Level 2 charging station) falls under the same $50 residential electrical service flat fee — Uintah County does not have a separate EV charger permit or fee.

Frequently asked questions

Unincorporated Uintah County requires an electrical permit for: Residential electrical service upgrade or replacement; Temporary construction power pedestal installation; Agricultural electrical service; Any new electrical work in an otherwise-exempt agricultural building. If your project isn't listed, confirm with Uintah County Community Development — Building Division at (435) 781-5336 before starting work.

A residential electrical service upgrade or replacement is a flat $50 fee, per the Uintah County Fee Schedule (Ord. 08-06-2025 O1, enacted 8/12/2025). Commercial/utility electrical service is $200. A re-inspection fee of $50 applies if a scheduled inspection is not ready.

Plan review for an electrical permit in Unincorporated Uintah County typically runs 10–14 business days. This is an estimate, not a published figure — confirm current review times with Uintah County Community Development — Building Division at (435) 781-5336.

You'll need: Electrical, Mechanical and Plumbing Building Permit Application. Depending on your project, Unincorporated Uintah County may also ask for: Electrical Single-Line Diagram / Plan. See the required-documents checklist on this page for details on each.

Unincorporated Uintah County requires 3 inspection(s) for an electrical permit, in order: Construction Power Inspection, Rough-In, Final. Schedule each through Uintah County Community Development — Building Division ((435) 781-5336).

Apply through Uintah County Community Development — Building Division at 152 East 100 North, Vernal, UT 84078. Phone: (435) 781-5336. Official information: https://www.uintah.gov/departments/a_-_e_departments/community_development/building_permits.php.

Unincorporated Uintah County, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a); supersedes the 2021 edition previously listed here. Uintah County's own Building Code page (uintah.gov, live-checked 2026-07-16) is UNCHANGED and still states '2021 International Building Codes Effective July 1, 2023' — the county page has not been updated for either the 2021→2023 language it already had wrong stylistically or the 2024 statewide edition now in force; the statute governs.; 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 statewide transition.; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not itemized on Uintah County's own Building Code page, added here per statute.; 2024 International Plumbing Code (IPC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d); supersedes the 2021 edition previously listed here.; 2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e); supersedes the 2021 edition previously listed here.; 2024 International Fuel Gas Code (IFGC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(f); supersedes the 2021 edition previously listed here.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(h); supersedes the 2021 edition previously listed here.; 2024 International Existing Building Code (IEBC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(i); supersedes the 2021 edition previously listed here. Uintah County's FAQ page ('Do I need a permit for my building? It's portable on a skid?' article, live-checked 2026-07-16) is UNCHANGED and still cites 'Chapter 14 of the 2018 International Existing Building Code (IEBC)' and '2018 International Building Code (IBC)' / '2015 International Residential Code (IRC)' / 'IRC 2015 or IBC 2018' for relocated/moved structures — this is now a much larger lag (2015/2018 editions vs. the current 2024/2021 statewide editions) than previously flagged; the FAQ page's separate 'When are building permits required' article also still cites 'IBC 2015 & IRC 2015' verbatim. The statute governs; Uintah County's FAQ page has not been updated to reflect any statewide code cycle since at least 2015/2018.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(n); supersedes the 2021 edition previously listed here.; 2023 National Electrical Code (NEC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(g) did not change this edition in the 7/1/2026 statewide transition. Uintah County's Building Code Information page (live-checked 2026-07-16) is UNCHANGED and still lists '2020 National Electrical Code (NEC) Effective July 1, 2021' — that page remains not updated; the statewide 2023 NEC is the legally in-force edition per the statute.; NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification — the flip anticipated by this file's prior 'Effective July 1, 2026' note has now occurred and is confirmed live. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Uintah County's own Building Code page and FAQ page were both live-checked 2026-07-16 and remain unchanged/stale exactly as previously found (in the FAQ's case, considerably staler than previously documented — see the IEBC entry above) — the statute is cited directly as governing throughout, per this file's established recovery-avenue policy.. Local amendments apply — see the Unincorporated Uintah County overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Uintah County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.