Residential Building Permit (New Home) — Highland, Utah · Requirements sheet
Verified 2026-07-07 · Source: https://highlandut.gov/DocumentCenter/View/9212/FY2026-Fee-Schedule---Adopted-61725
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Home) in Highland, Utah
Required for new single-family residential construction in Highland. Both the Permit Fee and Plan Check Fee are valuation-based, set 'As Set Forth by the International Code Council' rather than a fixed city table (distinct from Murray's own flat valuation chart) — confirmed identically in both the FY2025 (adopted 3/18/25) and FY2026 (adopted 5/5/26) Highland City Comprehensive Fee Schedules. Highland City's FY2026 Fee Schedule (adopted 6/17/2025) lists Building Permit Bonds, Deposits, and Permit Fees with several flat trade-permit categories (e.g., a $45.00 fee tier covering categories such as accessory structure, addition, basement, and remodel work), but no distinct EV charger/EVSE fee line item was found as of 2026-07-19 — EV charger installation would be handled as standard electrical/trade work under this fee schedule.
Verified 2026-07-07 · Source
When you need this permit
- New single-family residential construction
- Structural modifications to floor, walls, roof, windows, or doors on an existing structure
- Addition or replacement of a building system (e.g. electrical service, furnace)
- $500 non-refundable-until-applied deposit required at plan submittal, credited toward the final permit fee
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Scheduled Inspections (Building/Electrical/Mechanical/Plumbing)
Scheduled Monday through Thursday, 8:00 AM–6:00 PM, via the My City Inspector online portal or by calling (801) 772-4516; all inspections must be scheduled at least 24 hours in advance, per Highland's official Building Inspections FAQ.
See the full Highland inspection guide — scheduling & re-inspection fees →
Tips
- Highland's Building Division is closed Fridays (open Mon–Thu 8:00 AM–5:00 PM); inspections themselves run Mon–Thu 8:00 AM–6:00 PM by appointment only, at least 24 hours in advance.
- Unlike Murray, Highland does not publish its own valuation-based fee table — both the Permit Fee and Plan Check Fee are pegged directly to the International Code Council's fee schedule.
- A signed 'Notice to All Builders and Owners' is required, flagging that fence, retaining wall (over 4 ft), pool, and basement-finish permits are each SEPARATE from the building permit, and that unpermitted work liability transfers to a subsequent homebuyer regardless of their awareness.
- Highland City's FY2026 Fee Schedule (highlandut.gov, adopted 6/17/2025, checked 2026-07-19) has no distinct EV charger/EVSE fee line item among its Building Permit fee categories.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Highland building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Highland
Residential Building Permit (New Home) in other cities
Compare residential building permit (new home) fees across Utah →
Look up this fee in a different city →