Lehi building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Lehi, Utah.
Verified 2026-07-13 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 153 N 100 E, Lehi, UT 84043
- Phone
- (385) 201-1035
- building@lehi-ut.gov
- Office hours
- Mon–Thu 8 a.m.–5 p.m. (office); phone hours Mon–Thu 7:30 a.m.–5 p.m., Fri 8 a.m.–3:30 p.m. — call (385) 201-1035 to confirm
- Website
- Official site
Published scheduling rules
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. Inspections will NOT be scheduled by voicemail, email, or online. (Residential Building Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. Inspections will not be scheduled by voicemail, email, or online. (Electrical Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. Inspections will not be scheduled by voicemail, email, or online. (EV Charger / EVSE Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. Inspections will not be scheduled by voicemail, email, or online. (Plumbing Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. Inspections will not be scheduled by voicemail, email, or online. (Mechanical / HVAC Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. (Roofing Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. (Solar Panel Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. (Retaining Wall Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. (Basement Finish Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. (Deck Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. (Demolition Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. (Commercial Building Permit)
- Schedule inspections at least 24 hours in advance by calling (385) 201-1035. (Commercial Tenant Improvement / Tenant Finish Permit)
- Schedule all inspections at least 24 hours in advance by calling (385) 201-1035. Inspections will not be scheduled by voicemail, email, or online. Reinspection fees ($100) apply when a project is clearly not ready. (General)
Inspection sequence
Applies to: Accessory Dwelling Unit (ADU)
- 1
Foundation
Footings, forms, rebar — before concrete pour
- 2
Framing
Structure, fire separation, egress windows
- 3
MEP Rough-In
Mechanical, electrical, plumbing rough-ins before walls closed
- 4
Insulation
Insulation and vapor barrier before drywall
- 5
Final
All work complete, smoke/CO detectors, address posted, ready for occupancy
Applies to: Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, egress window openings
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Insulation
Insulation on exterior walls, vapor barrier placement
- 4
Final
Drywall, fixtures, smoke/CO detectors, all finishes complete
Applies to: Commercial Building Permit
- 1
Foundation
Before concrete pour — verify forms, rebar, footings, and anchor bolts
- 2
Framing
After framing, sheathing, and roof — before insulation and wall closure
- 3
MEP Rough-In
Mechanical, electrical, and plumbing rough-ins before walls closed
- 4
Final
All work complete, energy envelope and life-safety systems verified, ready for occupancy
Applies to: Residential Building Permit
- 1
Foundation
Before concrete pour — verify forms, rebar, and anchor bolts
- 2
Framing
After framing, sheathing, and roof — before insulation
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete, ready for occupancy
Applies to: Deck Permit
- 1
Footings
Verify footing depth (below 30-inch frost line), diameter, and rebar before concrete pour
- 2
Framing
Posts, beams, joists, ledger connection, and hardware
- 3
Final
Decking, stairs, guards, and railings complete — 36-inch guard height required at 30 inches above grade per IRC
Applies to: Electrical Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support
- 2
Service / Panel
Panel installation, grounding electrode system, service entrance conductors
- 3
Final
All devices installed, GFCI/AFCI protection verified, panel labeled
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support
- 2
Service / Panel
Panel installation, grounding electrode system, service entrance conductors, if the charger requires a service upgrade
- 3
Final
Charger connection, GFCI/breaker protection, panel labeled
Applies to: Plumbing Permit
- 1
Underground / Slab
Before concrete pour — verify pipe slope, materials, and cleanouts
- 2
Rough-In
After pipes installed, before walls closed — pressure test required
- 3
Final
All fixtures connected, water flowing, no leaks, proper venting verified
Applies to: Retaining Wall Permit
- 1
Footing
Footing excavation, rebar, and forms before concrete pour
- 2
Backfill / Drainage
Drainage gravel, pipe, and filter fabric before backfill
- 3
Final
Wall complete, drainage functional, site graded
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Rough-In
Interior framing and MEP rough-in verified per submitted plans before wall closure
- 2
Final
All tenant finish work complete, life-safety and lighting/mechanical compliance verified, ready for occupancy
Applies to: Demolition Permit
- 1
Pre-Demolition
Verify utility disconnects are complete and any required asbestos clearance is obtained before work begins
- 2
Final / Site Clear
Site cleared, foundation removed or capped, erosion control in place
Applies to: Fire Sprinkler System Permit
- 1
Underground Flush
Required acceptance-testing step for new sprinkler system installations, per the Fee Schedule's 'Acceptance Testing' table.
- 2
Final Occupancy — Hydrostatic / Acceptance Test
Required before occupancy; billed at $80.00 per the FY 2026 Fee Schedule (or per additional hour over 2 hours for extended tests).
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances and support
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional
Applies to: Roofing Permit
- 1
Deck / Substrate
After tear-off — verify sheathing condition, replace damaged decking before proceeding
- 2
Final
Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern
Applies to: Solar Panel Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement — before energizing
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, electrical connections, and warning labels verified
Final inspection only: Fire Alarm System Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lehi building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Lehi building permits