When you need this permit

  • New single-family or multi-family residential construction
  • Residential additions requiring structural or MEP work
  • Structural modifications (load-bearing wall removal, foundation work)
  • Conversion of unfinished space to habitable space
  • Any work requiring plan review under Lehi City Code Title 10

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 8 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit — valuation $1.00–$500Lehi City FY 2026 Fee Schedule (approved), Building Inspections section. Valuation based on 90% of ICC Building Valuation Data (August 2024).
$23.50
Building Permit — per $100 increase over $500 (up to $2,000)Lehi City FY 2026 Fee Schedule (approved)
$3.05 per $100
Building Permit — first $2,000 of valuationLehi City FY 2026 Fee Schedule (approved)
$69.25
Building Permit — per $1,000 increase ($2,001–$25,000)Lehi City FY 2026 Fee Schedule (approved)
$14 per $1,000
Building Permit — first $25,000 of valuationLehi City FY 2026 Fee Schedule (approved)
$391.75
Building Permit — per $1,000 increase ($25,001–$50,000)Lehi City FY 2026 Fee Schedule (approved)
$10.10 per $1,000
Building Permit — first $50,000 of valuationLehi City FY 2026 Fee Schedule (approved)
$643.75
Building Permit — per $1,000 increase ($50,001–$100,000)Lehi City FY 2026 Fee Schedule (approved)
$7 per $1,000
Building Permit — first $100,000 of valuationLehi City FY 2026 Fee Schedule (approved)
$993.75
Building Permit — per $1,000 increase ($100,001–$500,000)Lehi City FY 2026 Fee Schedule (approved)
$5.60 per $1,000
Building Permit — first $500,000 of valuationLehi City FY 2026 Fee Schedule (approved)
$3,233.75
Building Permit — per $1,000 increase ($500,001–$1,000,000)Lehi City FY 2026 Fee Schedule (approved)
$4.75 per $1,000
Building Permit — first $1,000,000 of valuationLehi City FY 2026 Fee Schedule (approved)
$5,608.75
Building Permit — per $1,000 increase above $1,000,001Lehi City FY 2026 Fee Schedule (approved)
$3.65 per $1,000
Plan Review Fee — ResidentialLehi City FY 2026 Fee Schedule (approved)
40% of the building permit fee
State SurchargeLehi City FY 2026 Fee Schedule (approved)
1% of the building permit fee
Reinspection FeeLehi City FY 2026 Fee Schedule (approved). Assessed when a project is clearly not ready for inspection.
$100
Building Valuation — Single-Family Residential Main FloorLehi City FY 2026 Fee Schedule (approved), Building Inspections section — used to calculate project valuation for permit fee purposes
$149.47 per sq ft
Building Valuation — Second FloorLehi City FY 2026 Fee Schedule (approved)
$149.47 per sq ft
Building Valuation — Unfinished BasementLehi City FY 2026 Fee Schedule (approved)
$37.37 per sq ft
Building Valuation — Semi-Finished BasementLehi City FY 2026 Fee Schedule (approved)
$37.37 per sq ft
Building Valuation — Finished BasementLehi City FY 2026 Fee Schedule (approved)
$74.74 per sq ft
Building Valuation — Garage (Wood Frame)Lehi City FY 2026 Fee Schedule (approved)
$59.83 per sq ft
Building Valuation — Open CarportsLehi City FY 2026 Fee Schedule (approved)
$47.86 per sq ft

Review timeline

Plan reviewTypical estimate — confirm current times with the Lehi building department
~10–28 business days

How long did your Residential Building Permit permit actually take in Lehi?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Before concrete pour — verify forms, rebar, and anchor bolts

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete, ready for occupancy

See the full Lehi inspection guide — scheduling & re-inspection fees →

Tips

  • All permit applications must be submitted electronically through the Lehi City Building Permit Submittal Portal at lehibuilding.portal.iworq.net.
  • Lehi uses 90% of the ICC Building Valuation Data (August 2024) to calculate project valuation for permit fee purposes. Per-sq-ft rates are published in the FY 2026 Fee Schedule.
  • Schedule inspections at least 24 hours in advance by calling (385) 201-1035. Inspections will NOT be scheduled by voicemail, email, or online.
  • Reinspection fees ($100) are assessed when a project is clearly not ready — ensure work is complete before calling for any inspection.
  • Approved plans are stamped on each page; contractors must print and keep a hard copy on the job site for all inspections.

Frequently asked questions

Lehi requires a residential building permit for: New single-family or multi-family residential construction; Residential additions requiring structural or MEP work; Structural modifications (load-bearing wall removal, foundation work); Conversion of unfinished space to habitable space; Any work requiring plan review under Lehi City Code Title 10. If your project isn't listed, confirm with Lehi City Building and Inspections at (385) 201-1035 before starting work.

Lehi City building permit fees are valuation-based using 90% of the ICC Building Valuation Data (August 2024). For example, a 2,000 sq ft main-floor single-family home is valued at 2,000 x $149.47 x 90% = $269,046; the permit fee is $993.75 (first $100k) + ($169.046 x $5.60) = $1,940.05, plus 40% residential plan review ($776.02) and 1% state surcharge ($19.40). Fees per the Lehi City FY 2026 Fee Schedule (approved).

Plan review for a residential building permit in Lehi typically runs 10–28 business days. This is an estimate, not a published figure — confirm current review times with Lehi City Building and Inspections at (385) 201-1035.

You'll need: Building Permit Application; Construction Plans (electronic, full set); Plot Plan; REScheck Energy Compliance; Manual J and Manual D Load Calculations; Gas Piping Diagram; Hold Harmless Agreement; Contractor License. Depending on your project, Lehi may also ask for: Engineered Truss Plans. See the required-documents checklist on this page for details on each.

Lehi requires 4 inspection(s) for a residential building permit, in order: Foundation, Framing, Insulation, Final. Schedule each through Lehi City Building and Inspections ((385) 201-1035).

Submit all applications electronically through the Lehi City Building Permit Submittal Portal at lehibuilding.portal.iworq.net. Required documents include a complete plan set, plot plan, REScheck, Manual J and D calculations, and a gas piping diagram. Call (385) 201-1035 for questions.

Lehi, Utah has adopted: 2024 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); effective 2026-07-01, superseded the 2021 edition. NOTE (verified 2026-07-16): Lehi's own Building and Inspections page still lists 'Current Codes: 2021 I Codes' — the city's page has not been updated to reflect the 2024 editions that took effect statewide on 2026-07-01.; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); unchanged by the 7/1/2026 code cycle; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); effective 2026-07-01, superseded the 2021 edition; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); effective 2026-07-01, superseded the 2021 edition; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective 2026-07-01, superseded the 2021 edition; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); unchanged by the 7/1/2026 code cycle. NOTE (verified 2026-07-16): Lehi's own Building and Inspections page lists '2020 NEC' — this is stale independent of the 7/1/2026 code cycle; the 2023 NEC has governed statewide since its own adoption (predating this fix and not caused by it).; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); effective 2026-07-01, superseded the 2021 edition; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); effective 2026-07-01, superseded the 2021 edition; 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); effective 2026-07-01, superseded the 2021 edition; ICC/ANSI A117.1-2017 (Accessible and Usable Buildings and Facilities) — Lehi City Building and Inspections page; NOTE (verified 2026-07-16): The 2024 editions of IBC, IPC, IMC, IFGC, IECC, IEBC, and ISPSC took effect 2026-07-01 per Utah Code § 15A-2-103, superseding the 2021 editions that governed through 2026-06-30. The 2021 IRC and 2023 NEC were NOT changed by this cycle. Confirmed directly against the version of § 15A-2-103 effective 7/1/2026 (superseded 1/1/2027) at le.utah.gov. Lehi's own page (lehi-ut.gov/departments/building-and-inspections/) was checked live on 2026-07-16 and still reads 'Current Codes: 2021 I Codes' / '2020 NEC' — it reflects neither the 2024 code cycle nor the separately longer-standing 2023 NEC.. Local amendments apply — see the Lehi overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lehi building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.