EV Charger / EVSE Permit — Santa Clara, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://cdn.santaclarautah.gov/file/scweb-prod/2026/02/Building-Permit-Fees-Effective-Jan-2026.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Santa Clara, Utah
Santa Clara City's Building Permit Fees schedule (effective January 2026) has no standalone "Electrical Permit," "EV Charger," or "EVSE" line item. Building Fees are assessed purely on construction valuation ("Based on Valuation," using current ICC rates), with a Plan Review Fee of 10% of the Building Fee — meaning EV charger/EVSE installation is billed through the same valuation-based Building Fee as any other permitted work, with no distinct electrical or EV carve-out. (The schedule's "Electrical Connect" and "Electrical Impact" entries are utility meter-size connection/impact fees for new water/power service, unrelated to permitting a charger installation.)
Verified 2026-07-20 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in Santa Clara City
- Work performed per Santa Clara City's adopted electrical code
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Santa Clara City Building Permit Fees (Effective January 2026): "Building Fees — Based on Valuation." No standalone Electrical Permit or EV Charger fee line exists anywhere in the schedule (confirmed… Show full citationHide
Santa Clara City Building Permit Fees (Effective January 2026): "Building Fees — Based on Valuation." No standalone Electrical Permit or EV Charger fee line exists anywhere in the schedule (confirmed via full-text search); all trade work including EVSE installation is priced through this single valuation-based Building Fee.Review timeline
Inspection process
- 1
Building Inspection
Inspection of the charger circuit, panel, and grounding by Santa Clara City Building Department.
See the full Santa Clara inspection guide — scheduling & re-inspection fees →
Tips
- Santa Clara has no separate Electrical Permit or EV Charger fee category — the general valuation-based Building Fee applies to every trade, including EVSE installation.
- Don't confuse the schedule's 'Electrical Connect'/'Electrical Impact' entries with a permit fee — those are utility connection/impact charges for new service, not a charger installation permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Santa Clara building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Santa Clara's permit history is searchable by address
14 permits on record for Santa Clara, 1972–2014 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
71% of Santa Clara's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.
Other permits in Santa Clara
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →