Solar PV Permit — Santa Clara, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://cdn.santaclarautah.gov/file/scweb-prod/2025/09/2023-Net-Metering-Packet-Solar-Revised-9-8-25.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Permit in Santa Clara, Utah
Required for residential rooftop, pole-mount, or ground-mount solar photovoltaic (PV) installations up to 12 kW AC that interconnect with Santa Clara City's municipal electric utility. Santa Clara City is its own power provider (not Rocky Mountain Power), so this permit bundles the building permit, a dedicated Solar Permit Application, and a required Renewable Net Metering & Interconnection Agreement into one process administered jointly by the Building Department and City Power Department. Commercial solar systems are not covered under this residential net metering policy and require a separate review/system impact study.
Verified 2026-07-19 · Source
When you need this permit
- Residential system limited to a maximum of 12 kW AC installed capacity under the City's Net Metering Policy (adopted February 24, 2016); commercial customers are reviewed separately and are not eligible under this policy
- All equipment, signage, and installation practices must meet NEC Articles 690 and 705
- Completed Building Permit Application plus the dedicated Solar Permit Application and signed Net Metering Agreement
- One-page site map and system one-line diagram showing solar module locations, inverter, batteries (if any), lockable disconnect switch, and utility point of connection, with installation address and installer's name/phone
- Structural load design and letter from a structural engineer licensed in the State of Utah
- Pre-operation inspection and written City approval required before the Facility may begin parallel operation with the City's electric distribution system
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Santa Clara City Building Permit Fees, effective January 2026, 'Maintenance Deposits' section: 'Solar — $500.00' (confirmed consistent with the $500.00 Maintenance Deposit pre-printed on the Solar… Show full citationHide
Santa Clara City Building Permit Fees, effective January 2026, 'Maintenance Deposits' section: 'Solar — $500.00' (confirmed consistent with the $500.00 Maintenance Deposit pre-printed on the Solar Permit Application form). Refundable after final inspection if the site is kept clean and the inspection is passed.Review timeline
Inspection process
- 1
Pre-Operation / Interconnection Inspection
Per the Renewable Net Metering & Interconnection Agreement, the Facility and all interconnection equipment must be inspected and approved by the City (Building Official and Power Director sign-off required on the Solar Permit Application) before parallel operation with the City's electric distribution system may begin.
See the full Santa Clara inspection guide — scheduling & re-inspection fees →
Tips
- Santa Clara City is its own electric utility (not Rocky Mountain Power) — net metering approval comes from the Santa Clara City Power Department, and the Solar Permit Application requires sign-off from both the Power Director and the Building Official.
- Residential systems are capped at 12 kW AC installed capacity under the City's Net Metering Policy; commercial systems are excluded from this policy and reviewed separately, potentially including a system impact study.
- The $500 Maintenance Deposit is refundable after final inspection if the site is kept clean and the inspection passes.
- All labels must be phenolic (not hand-written marker) with red background and white lettering, at least 3/8" tall, per NEC Articles 690/705 label requirements detailed in the application's Appendix 2.
- Santa Clara charges a Solar Reliability Charge (based on inverter AC nameplate kW capacity) in addition to the Renewable Power Rate credit ($0.04/kWh as of the 2023 packet) for excess energy — budget for this recurring utility charge, not just the one-time permit fees.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fee schedules
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Santa Clara building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Santa Clara's permit history is searchable by address
14 permits on record for Santa Clara, 1972–2014 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
71% of Santa Clara's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.
Other permits in Santa Clara
Solar PV Permit in other cities
Compare solar pv permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Santa Clara project checklist
Describe your project once and get every permit, document, and fee it triggers in Santa Clara — in one checklist. Free, for any city and any number of projects.
Get started →