Demolition Permit in Paradise Valley, Arizona

Required for demolition of any residential or commercial structure, wall, or fence in Paradise Valley whenever more than 12 linear feet of building wall/fence or 12 square feet of roof/structure is removed. Must be obtained before the associated building permit is issued.

Verified 2026-07-06 · Source

When you need this permit

  • Demolition permit required whenever more than 12 linear feet of building wall or fence, or 12 square feet of roof or structure, is to be removed; must be obtained BEFORE issuance of the building permit for any subsequent new construction
  • Site Plan, Dust Control Plan, Right-of-Way Photos, Construction Plans, SWPPP, and Native Plant Preservation Plan required depending on scope
  • Asbestos inspection required for multi-building demolition
  • A Demolition Haul Permit applies separately when more than 100 cubic yards of other materials are removed from the property
  • A final inspection must be performed on every demolition permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition Plan Check — Complete DemolitionTown of Paradise Valley Building Permit Application Information handout, 'Demolition permits' section (current, live) — covers up to two plan reviews; additional reviews at $145/hour
$145
Demolition Plan Check — Partial DemolitionTown of Paradise Valley Building Permit Application Information handout (current, live)
$73
Demolition Permit — Complete Demolition (2021 schedule, likely superseded)Town of Paradise Valley Master Fee Schedule §1.1.7 (archived 03/01/2022 capture, Res. 2021-01 revision); the Town's current live Building Permit Application Information handout confirms the plan-check fee split ($73/$145) is current but does not restate the separate permit-issuance fee, so this permit-issuance figure should be reconfirmed with the Building Safety Department
$260
Expedited Out-Sourced Demolition ReviewTown of Paradise Valley Building Permit Application Information handout (current, live); additional reviews after two at $145/hour
115% of the Building Permit Fee

Review timeline

Plan reviewParadise Valley’s published plan-review target
15–20 business days

How long did your Demolition Permit permit actually take in Paradise Valley?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Pre-Demolition (Right-of-Way/Utility)

    Right-of-way condition and utility termination verified before work begins

  2. 2

    Final

    Required on every demolition permit; confirms complete removal and site condition

See the full Paradise Valley inspection guide — scheduling & re-inspection fees →

Tips

  • The 12-linear-foot wall/fence or 12-square-foot roof/structure threshold for requiring a demolition permit is much lower than in many other Arizona jurisdictions — even removing a modest section of an existing fence to build a new one may trigger this permit.
  • The demolition plan-check fee ($73 partial / $145 complete) confirmed on the Town's current live handout is a plan-review-only fee; it is distinct from the separate demolition permit issuance fee documented in the archived 2021 Master Fee Schedule ($130/$260) — the issuance-fee figure could not be re-confirmed against the current live fee schedule in this review and should be verified directly with the Building Safety Department for a precise total cost.
  • A demolition permit must be fully obtained before the Town will issue the building permit for whatever new construction follows.

Frequently asked questions

Yes, if more than 12 linear feet of building wall/fence or 12 square feet of roof/structure will be removed. This demolition permit must be obtained before the Town will issue a building permit for any new construction that follows.

In Paradise Valley, the published Demolition Plan Check — Complete Demolition is: $145. Additional published fees: Demolition Plan Check — Partial Demolition — $73; Demolition Permit — Complete Demolition (2021 schedule, likely superseded) — $260; Expedited Out-Sourced Demolition Review — 115% of the Building Permit Fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Paradise Valley's published plan-review target for a demolition permit is 15–20 business days.

You'll need: Demolition Permit Application; Site Plan; Right-of-Way Photos. Depending on your project, Paradise Valley may also ask for: SWPPP; Native Plant Preservation Plan. See the required-documents checklist on this page for details on each.

Paradise Valley requires 2 inspection(s) for a demolition permit, in order: Pre-Demolition (Right-of-Way/Utility), Final. Schedule each through Town of Paradise Valley Building Safety Department (Community Development Department) (480-348-3692).

Apply through Town of Paradise Valley Building Safety Department (Community Development Department) at 6401 E. Lincoln Drive, Paradise Valley, AZ 85253-4399. Phone: 480-348-3692, email: PVPermits@paradisevalleyaz.gov. Office hours: Monday - Friday, 7 a.m. - Noon and 1 p.m. - 4 p.m.; closed for lunch 12:00 p.m. - 1:00 p.m. The Town does not accept application submittals, payments, nor release permits after 3:30 p.m. Applications for Building, Banner, Demolition, Electrical, Fence/Site Walls, Mechanical, Plumbing, Pool/Spa, and Short-Term Rental permits are submitted via the Accela Citizen Access online portal (aca-prod.accela.com/PARADISEVLY). Building inspections are scheduled via a 24/7 interactive phone system at 480-348-3581 or the Accela portal; winter (Oct-Apr) inspection hours are 7 a.m.-3 p.m., summer (May-Sept) 6 a.m.-3 p.m., and requests received before 3 p.m. are performed the next business day.. Official information: https://www.paradisevalleyaz.gov/185/Building.

Paradise Valley, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The Town of Paradise Valley operates its own Building Safety Department / Community Development Department and independently adopts and administers its own construction codes. Source: Town of Paradise Valley Building page (paradisevalleyaz.gov/185/Building) and the Town's 'International Codes adopted by Town of Paradise Valley' handout (Community Development Department, updated July 2023).; 2015 International Residential Code (IRC), adopted by the Town of Paradise Valley, with local design-criteria and administrative amendments. Source: 'International Codes adopted by Town of Paradise Valley' (Community Development Department, updated July 2023).; 2015 International Building Code (IBC), adopted by the Town of Paradise Valley, with local amendments. Source: 'International Codes adopted by Town of Paradise Valley' (updated July 2023).; 2015 International Mechanical Code (IMC), adopted by the Town of Paradise Valley. Source: 'International Codes adopted by Town of Paradise Valley' (updated July 2023).; 2015 International Plumbing Code (IPC), adopted by the Town of Paradise Valley. Source: 'International Codes adopted by Town of Paradise Valley' (updated July 2023).; 2015 International Fuel Gas Code (IFGC), adopted by the Town of Paradise Valley. Source: 'International Codes adopted by Town of Paradise Valley' (updated July 2023).; 2021 International Fire Code (IFC), adopted by the Town of Paradise Valley as its uniform fire code — the only 2021-cycle ICC code adopted by the Town, one full code cycle newer than its 2015 building/residential/mechanical/plumbing/fuel-gas set; administered with the Town Fire Marshal (480-348-3631). Source: 'International Codes adopted by Town of Paradise Valley' (updated July 2023).; 2015 International Property Maintenance Code (IPMC), adopted by the Town of Paradise Valley. Source: 'International Codes adopted by Town of Paradise Valley' (updated July 2023).; 2014 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted by the Town of Paradise Valley — one edition behind Buckeye's 2023 NEC and two behind the current 2023 NFPA cycle; this is the edition in force as of the Town's most recently updated codes-adopted handout (July 2023). Source: 'International Codes adopted by Town of Paradise Valley' (updated July 2023).; 2015 International Energy Conservation Code (IECC), adopted by the Town of Paradise Valley. Source: 'International Codes adopted by Town of Paradise Valley' (updated July 2023).; Air Conditioning Contractors of America (ACCA) Manual J (load calculation) and Manual S (equipment selection) compliance is mandatory for all new single-family home applications, using Town-specified outdoor design conditions (Winter Heating 99% DB = 35°F ± 2°F; Summer Cooling 1% DB = 107°F ± 2°F) and indoor design conditions (Heating 70°F at 30% RH; Cooling 75°F at 45% RH). Source: Town of Paradise Valley Building Permit Application Information handout (Building Safety Department).. Local amendments apply — see the Paradise Valley overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Paradise Valley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.