Demolition Permit — Paradise Valley, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.paradisevalleyaz.gov/DocumentCenter/View/10/Building-Permit-Application-Information
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Paradise Valley, Arizona
Required for demolition of any residential or commercial structure, wall, or fence in Paradise Valley whenever more than 12 linear feet of building wall/fence or 12 square feet of roof/structure is removed. Must be obtained before the associated building permit is issued.
Verified 2026-07-06 · Source
When you need this permit
- Demolition permit required whenever more than 12 linear feet of building wall or fence, or 12 square feet of roof or structure, is to be removed; must be obtained BEFORE issuance of the building permit for any subsequent new construction
- Site Plan, Dust Control Plan, Right-of-Way Photos, Construction Plans, SWPPP, and Native Plant Preservation Plan required depending on scope
- Asbestos inspection required for multi-building demolition
- A Demolition Haul Permit applies separately when more than 100 cubic yards of other materials are removed from the property
- A final inspection must be performed on every demolition permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Pre-Demolition (Right-of-Way/Utility)
Right-of-way condition and utility termination verified before work begins
- 2
Final
Required on every demolition permit; confirms complete removal and site condition
See the full Paradise Valley inspection guide — scheduling & re-inspection fees →
Tips
- The 12-linear-foot wall/fence or 12-square-foot roof/structure threshold for requiring a demolition permit is much lower than in many other Arizona jurisdictions — even removing a modest section of an existing fence to build a new one may trigger this permit.
- The demolition plan-check fee ($73 partial / $145 complete) confirmed on the Town's current live handout is a plan-review-only fee; it is distinct from the separate demolition permit issuance fee documented in the archived 2021 Master Fee Schedule ($130/$260) — the issuance-fee figure could not be re-confirmed against the current live fee schedule in this review and should be verified directly with the Building Safety Department for a precise total cost.
- A demolition permit must be fully obtained before the Town will issue the building permit for whatever new construction follows.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Paradise Valley building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Paradise Valley
Demolition Permit in other cities
Compare demolition permit fees across Arizona →
Look up this fee in a different city →