Commercial / Residential Demolition Permit — Sedona, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.sedonaaz.gov/your-government/departments/community-development/permits
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial / Residential Demolition Permit in Sedona, Arizona
Required for demolition of any residential or commercial structure in Sedona. Structures over 50 years old require additional documentation under Land Development Code § 8.7.F(3) (historic preservation review).
Verified 2026-07-06 · Source
When you need this permit
- Building permit required before demolishing a residential or commercial structure within Sedona city limits
- If the structure is more than 50 years old, documentation pursuant to Land Development Code § 8.7.F(3) must be provided (historic preservation review)
- 4 sets of a plat of survey or site plan identifying all structures on the property, specifically what is to be demolished, protective site fencing and gate locations, spoils locations/types, and erosion control measures
- Utility disconnection letters/approvals required for all applicable utilities (electric, water, sewer, septic, gas) before demolition
- A description of the post-demolition site condition and any proposed redevelopment (with anticipated start date) must be provided
- Demolishing a legal nonconforming structure or use may remove the property's legal nonconforming status — applicants are advised to meet with staff to discuss potential effects before proceeding
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final
Verifies utility termination, site condition per submitted description, and erosion-control/tree-protection measures maintained through completion
See the full Sedona inspection guide — scheduling & re-inspection fees →
Tips
- Structures over 50 years old trigger a Land Development Code § 8.7.F(3) historic-documentation requirement before a demolition permit can be issued — budget extra lead time for this review step.
- The $50 application fee is a flat charge stated on the form itself, distinct from the valuation-based building permit fee structure used for new construction.
- Per the City of Sedona's standard packet time-frame table format used across its permit types (authorized under City Code Title 15), demolition permits are processed on the same 21 business days Administrative Completeness + 21 business days Substantive Review = 42 business days overall time frame as other core building permit types; no permit-specific alternate time frame was published in the Structure Demolition Checklist or application itself.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sedona building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Sedona
Commercial / Residential Demolition Permit in other cities
Compare commercial / residential demolition permit fees across Arizona →
Look up this fee in a different city →