EV Charger / Electric Vehicle Charging Station Permit in Sedona, Arizona

Sedona does not publish a standalone electrical permit type or a distinct EV-charger/EVSE fee line. Per the City's own Permits page and the Residential Remodel/Addition Building Permit Packet (which this file already documents as covering all electrical work in the City, including 'relocation/installation of electrical outlets, lighting, wiring, panels, or services'), installing a new circuit for an EV charging station is processed as electrical work under the Residential Remodel/Addition Building Permit -- the same permit type used for panel upgrades, new circuits, and other electrical alterations to one- and two-family dwellings. No City of Sedona Consolidated Fee Schedule line item, permit packet, or press material naming 'EV charger,' 'EVSE,' or 'electric vehicle charging station' as a distinct permit type or fee could be found; the City is not a listed SolarAPP+ (gosolarapp.org) participating jurisdiction.

Verified 2026-07-20 · Source

When you need this permit

  • A building permit is required for installation of a new dedicated circuit or panel work for an EV charger, processed under the Residential Remodel/Addition Building Permit (Sedona does not publish a distinct 'electrical permit' or 'EV charger permit' type)
  • If the EV charger is a UL-listed unit plugging into an existing 120V receptacle with no new wiring, industry-standard practice (and the City's general work-exemption pattern for cosmetic/no-new-circuit work) suggests no permit would be triggered -- confirm directly with Community Development for any specific installation
  • Unless exempt under A.R.S. § 32-1121 (owner-occupied, not for sale/rent), the electrical work must be performed by an Arizona-licensed contractor Owner-builderContractor
  • If the installation includes new structural work (e.g., a carport to house the charger), the Single-Family Residential Building Permit or Remodel/Addition process applies to that structural scope as well

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (Based on Valuation)Sedona City Code § 15.05.060 -- no separately itemized flat fee for EV charger/EVSE installation was found distinct from the general valuation-based building permit fee structure that governs other electrical alteration work processed under the Residential Remodel/Addition Building Permit
Per City of Sedona Consolidated Fee Schedule, Valuation/Permit Fee Schedule
Plan Review FeeSedona City Code § 15.05.060
65% of the calculated Building Permit Fee

Review timeline

Plan reviewTypical estimate — confirm current times with the Sedona building department
~42–42 business days

How long did your EV Charger / Electric Vehicle Charging Station Permit permit actually take in Sedona?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In / Electrical

    New circuit wiring, breaker, and disconnect verified before concealment, per 2017 NEC as adopted by the City

  2. 2

    Final

    Completed installation verified against approved plans

See the full Sedona inspection guide — scheduling & re-inspection fees →

Tips

  • Sedona does not publish a standalone 'electrical permit' or 'EV charger permit' -- EV charging station circuit work is processed through the same Residential Remodel/Addition Building Permit used for other electrical alterations (panel upgrades, new circuits, wiring).
  • The City is not a listed SolarAPP+ (gosolarapp.org) participating jurisdiction, so no instant-issuance path is available for the electrical scope of an EV charger installation.
  • If your installation only involves plugging a UL-listed charger into an existing outlet with no new wiring, confirm with Community Development (928-282-1154) whether a permit is triggered at all.

Frequently asked questions

Sedona requires an ev charger / electric vehicle charging station permit for: A building permit is required for installation of a new dedicated circuit or panel work for an EV charger, processed under the Residential Remodel/Addition Building Permit (Sedona does not publish a distinct 'electrical permit' or 'EV charger permit' type); If the EV charger is a UL-listed unit plugging into an existing 120V receptacle with no new wiring, industry-standard practice (and the City's general work-exemption pattern for cosmetic/no-new-circuit work) suggests no permit would be triggered -- confirm directly with Community Development for any specific installation; Unless exempt under A.R.S. § 32-1121 (owner-occupied, not for sale/rent), the electrical work must be performed by an Arizona-licensed contractor; If the installation includes new structural work (e.g., a carport to house the charger), the Single-Family Residential Building Permit or Remodel/Addition process applies to that structural scope as well. If your project isn't listed, confirm with City of Sedona Community Development Department — Building Safety Division at 928-282-1154 before starting work.

There is no distinct EV charger fee line. It is billed as a valuation-based Building Permit Fee per the City of Sedona Consolidated Fee Schedule, plus a Plan Review Fee equal to 65% of the building permit fee, under Sedona City Code § 15.05.060 -- the same fee mechanism used for other electrical alteration work.

Plan review for an ev charger / electric vehicle charging station permit in Sedona typically runs 42–42 business days. This is an estimate, not a published figure — confirm current review times with City of Sedona Community Development Department — Building Safety Division at 928-282-1154.

You'll need: Residential Building Permit Application (Remodel/Addition); Electrical Circuit / Load Calculation. See the required-documents checklist on this page for details on each.

Sedona requires 2 inspection(s) for an ev charger / electric vehicle charging station permit, in order: Rough-In / Electrical, Final. Schedule each through City of Sedona Community Development Department — Building Safety Division (928-282-1154).

Apply through City of Sedona Community Development Department — Building Safety Division at 102 Roadrunner Drive, Sedona, AZ 86336-3710 (Community Development front counter address also published as 104 Roadrunner Drive in some permit packets). Phone: 928-282-1154, email: Permittechs@sedonaaz.gov. Office hours: Community Development Department phone hours Monday - Thursday, 7:00 a.m. - 6:00 p.m. (4-day, 10-hour City workweek); lobby/front counter hours Monday - Thursday, 7:30 a.m. - 5:00 p.m. Construction Inspection Hotline: 928-282-3268 (call by 3:00 p.m. the business day before to request a next-day inspection). Staff: Steve Mertes, Chief Building Official/Community Development Director, 928-203-5097, smertes@sedonaaz.gov; Becky Oium, Plans Examiner, 928-203-5093; Patty Lewis, Permit Technician, 928-203-5118; Andrew Vaughn, Building Inspector, 928-204-7115, avaughn@sedonaaz.gov.. Official information: https://www.sedonaaz.gov/your-government/departments/community-development/permits.

Sedona, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Sedona runs its own Community Development Department / Building Safety Division and independently adopts and administers its own construction codes as City Code Title 15 (Buildings and Construction); it does not defer permitting to Yavapai County or Coconino County for parcels within Sedona city limits, even though the city itself straddles both counties. Source: Sedona City Code Chapter 15.05 (sedona.municipal.codes/SCC/15.05); City of Sedona Permits and Building Safety webpages.; 2018 International Building Code (IBC), as amended and codified, published by the International Code Council, adopted as the building code of the City of Sedona (Sedona City Code § 15.05.010), with City of Sedona amendments (§ 15.05.020). Adopted by City Council on September 24, 2019 (Ordinance 2019-05, Resolution 2019-18 Exh. A); effective for all permits submitted on or after October 25, 2019. Source: Sedona City Code § 15.05.010/.020; City of Sedona Building Safety and Permits pages ('Building Codes' section).; 2018 International Residential Code (IRC), adopted with City of Sedona amendments (§ 15.05.030/.040), effective October 25, 2019, including the City's amended IRC Table R301.2(1) Climatic and Geographic Design Criteria. Source: Sedona City Code § 15.05.030/.040.; 2018 International Plumbing Code (IPC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage, 'Building Codes' list.; 2018 International Energy Conservation Code (IECC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Mechanical Code (IMC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Existing Building Code (IEBC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Fuel Gas Code (IFGC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Swimming Pool and Spa Code (ISPSC), adopted with City of Sedona amendments, effective October 25, 2019 (referenced in the Swimming Pool, Spa and Hot Tub Building Permit Packet's '2019 Amendments to Sedona City Code' insert). Source: City of Sedona Building Safety webpage; City of Sedona Swimming Pool and Spa Building Permit Packet.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted with City of Sedona amendments, effective October 25, 2019 (one edition behind the 2018 ICC I-Codes set, consistent with the City's own stated rationale of aligning with 'surrounding communities and counties'). Source: City of Sedona Building Safety webpage.; Manufactured homes, mobile homes, and factory-built buildings are separately defined and regulated under Sedona City Code § 15.05.090 (adopting the Arizona Office of Manufactured Housing construction/installation standards per A.R.S. Title 41, Chapter 16), with the City issuing its own 'Manufactured or factory built home permit' packet for placement, foundation, and site-related requirements. Source: Sedona City Code § 15.05.090; City of Sedona Permits page.; Building permit fees and valuation are governed by Sedona City Code § 15.05.060, which cross-references the City of Sedona Consolidated Fee Schedule (Valuation/Permit Fee Schedule and Unit Permit Fees) as the authoritative fee source rather than the ICC codes' own fee tables; the plan review fee is set at 65 percent of the calculated building permit fee when the permit fee is valuation-based. Source: Sedona City Code § 15.05.060 (sedona.municipal.codes/SCC/15.05.060).. Local amendments apply — see the Sedona overview page for the full list.

No. Sedona does not publish a standalone electrical, EV charger, or EVSE permit type. Installing a new circuit for an EV charging station is processed under the same Residential Remodel/Addition Building Permit used for other electrical alteration work, per the City's Permits page and permit packets.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sedona building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.