Solar / Photovoltaic Permit in Sedona, Arizona

Required for installation of Photovoltaic Electrical Power Systems in Sedona. Governed by the 2017 NEC as adopted and amended by the City of Sedona, with Sedona-specific aesthetic requirements (panel frame color, light-reflectance limits) tied to the City's scenic-beauty provisions.

Verified 2026-07-06 · Source

When you need this permit

  • Photovoltaic permit required for all rooftop or ground-mount solar PV installations
  • 2 full sets of plans plus 2 additional site plans required
  • Site plan must show locations of array, inverter, DC disconnect, PV system utility disconnect, and battery banks (if used)
  • One-line and three-line electrical diagrams required
  • Roof plan required showing panel layout, wiring method, make/model of panels, panel wattage and total array wattage
  • Roof load information (weight of rooftop equipment per sq ft) and mounting/attachment details required
  • Solar panel frames must be black matte finish (or natural aluminum/silver with perimeter frames painted black); all hardware, brackets, and support structures must meet a Light Reflectance Value (LRV) of 38% or less; conduit and panel boxes must be painted to match the adjacent wall/roof surface

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 5 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Photovoltaic Permit FeeCity of Sedona Solar/Photovoltaic Permit Packet, fee schedule stated directly on the application form
$75.00 for the first 10 kW, plus $5.00 for each additional kW over 10 kW

Review timeline

Plan reviewSedona’s published plan-review target
42–42 business days

How long did your Solar / Photovoltaic Permit permit actually take in Sedona?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing, per 2017 NEC as adopted by the City

  2. 2

    Final

    Panel mounting, racking attachment, roof penetration sealing, electrical connections, and utility interconnection point verified

See the full Sedona inspection guide — scheduling & re-inspection fees →

Tips

  • Per the City of Sedona Solar/Photovoltaic Permit Packet, the published A.R.S. § 9-836 time frame is 21 business days Administrative Completeness + 21 business days Substantive Review = 42 business days overall, authorized under City Code Title 15.
  • Sedona imposes aesthetic/scenic-beauty requirements on solar installations not commonly found elsewhere: panel frames must be black matte (or silver with black-painted perimeter), and all mounting hardware/conduit must meet a 38% LRV cap or be painted to match the adjacent surface.
  • The PV fee schedule is flat-rate by system size ($75 base + $5/kW over 10kW), not valuation-based like the general building permit fee.

Frequently asked questions

Sedona requires a solar / photovoltaic permit for: Photovoltaic permit required for all rooftop or ground-mount solar PV installations; 2 full sets of plans plus 2 additional site plans required; Site plan must show locations of array, inverter, DC disconnect, PV system utility disconnect, and battery banks (if used); One-line and three-line electrical diagrams required; Roof plan required showing panel layout, wiring method, make/model of panels, panel wattage and total array wattage; Roof load information (weight of rooftop equipment per sq ft) and mounting/attachment details required; Solar panel frames must be black matte finish (or natural aluminum/silver with perimeter frames painted black); all hardware, brackets, and support structures must meet a Light Reflectance Value (LRV) of 38% or less; conduit and panel boxes must be painted to match the adjacent wall/roof surface. If your project isn't listed, confirm with City of Sedona Community Development Department — Building Safety Division at 928-282-1154 before starting work.

$75.00 for the first 10 kW of system capacity, plus $5.00 for each additional kW above 10 kW, per the City of Sedona Solar/Photovoltaic Permit Packet fee schedule.

Per the City of Sedona Solar/Photovoltaic Permit Packet's published A.R.S. § 9-836 time frame, Administrative Completeness review takes 21 business days and Substantive Review takes 21 business days, for an overall 42 business days.

You'll need: Photovoltaic Permit Application; Site Plan; One-Line and Three-Line Diagrams; Inverter and Module Cut Sheets; Roof Plan and Elevations. See the required-documents checklist on this page for details on each.

Sedona requires 2 inspection(s) for a solar / photovoltaic permit, in order: Rough Electrical, Final. Schedule each through City of Sedona Community Development Department — Building Safety Division (928-282-1154).

Apply through City of Sedona Community Development Department — Building Safety Division at 102 Roadrunner Drive, Sedona, AZ 86336-3710 (Community Development front counter address also published as 104 Roadrunner Drive in some permit packets). Phone: 928-282-1154, email: Permittechs@sedonaaz.gov. Office hours: Community Development Department phone hours Monday - Thursday, 7:00 a.m. - 6:00 p.m. (4-day, 10-hour City workweek); lobby/front counter hours Monday - Thursday, 7:30 a.m. - 5:00 p.m. Construction Inspection Hotline: 928-282-3268 (call by 3:00 p.m. the business day before to request a next-day inspection). Staff: Steve Mertes, Chief Building Official/Community Development Director, 928-203-5097, smertes@sedonaaz.gov; Becky Oium, Plans Examiner, 928-203-5093; Patty Lewis, Permit Technician, 928-203-5118; Andrew Vaughn, Building Inspector, 928-204-7115, avaughn@sedonaaz.gov.. Official information: https://www.sedonaaz.gov/your-government/departments/community-development/permits.

Sedona, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Sedona runs its own Community Development Department / Building Safety Division and independently adopts and administers its own construction codes as City Code Title 15 (Buildings and Construction); it does not defer permitting to Yavapai County or Coconino County for parcels within Sedona city limits, even though the city itself straddles both counties. Source: Sedona City Code Chapter 15.05 (sedona.municipal.codes/SCC/15.05); City of Sedona Permits and Building Safety webpages.; 2018 International Building Code (IBC), as amended and codified, published by the International Code Council, adopted as the building code of the City of Sedona (Sedona City Code § 15.05.010), with City of Sedona amendments (§ 15.05.020). Adopted by City Council on September 24, 2019 (Ordinance 2019-05, Resolution 2019-18 Exh. A); effective for all permits submitted on or after October 25, 2019. Source: Sedona City Code § 15.05.010/.020; City of Sedona Building Safety and Permits pages ('Building Codes' section).; 2018 International Residential Code (IRC), adopted with City of Sedona amendments (§ 15.05.030/.040), effective October 25, 2019, including the City's amended IRC Table R301.2(1) Climatic and Geographic Design Criteria. Source: Sedona City Code § 15.05.030/.040.; 2018 International Plumbing Code (IPC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage, 'Building Codes' list.; 2018 International Energy Conservation Code (IECC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Mechanical Code (IMC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Existing Building Code (IEBC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Fuel Gas Code (IFGC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Swimming Pool and Spa Code (ISPSC), adopted with City of Sedona amendments, effective October 25, 2019 (referenced in the Swimming Pool, Spa and Hot Tub Building Permit Packet's '2019 Amendments to Sedona City Code' insert). Source: City of Sedona Building Safety webpage; City of Sedona Swimming Pool and Spa Building Permit Packet.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted with City of Sedona amendments, effective October 25, 2019 (one edition behind the 2018 ICC I-Codes set, consistent with the City's own stated rationale of aligning with 'surrounding communities and counties'). Source: City of Sedona Building Safety webpage.; Manufactured homes, mobile homes, and factory-built buildings are separately defined and regulated under Sedona City Code § 15.05.090 (adopting the Arizona Office of Manufactured Housing construction/installation standards per A.R.S. Title 41, Chapter 16), with the City issuing its own 'Manufactured or factory built home permit' packet for placement, foundation, and site-related requirements. Source: Sedona City Code § 15.05.090; City of Sedona Permits page.; Building permit fees and valuation are governed by Sedona City Code § 15.05.060, which cross-references the City of Sedona Consolidated Fee Schedule (Valuation/Permit Fee Schedule and Unit Permit Fees) as the authoritative fee source rather than the ICC codes' own fee tables; the plan review fee is set at 65 percent of the calculated building permit fee when the permit fee is valuation-based. Source: Sedona City Code § 15.05.060 (sedona.municipal.codes/SCC/15.05.060).. Local amendments apply — see the Sedona overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sedona building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.