Residential Remodel / Addition Building Permit in Sedona, Arizona

Required for room additions, remodels, and structural/plumbing/electrical/mechanical alteration work to existing one- and two-family dwellings in Sedona, including installation or relocation of water heaters, furnaces, evaporative coolers, air conditioners, electrical outlets, lighting, wiring, panels, or services, and replacement of a wood/asphalt shingle roof with a tile roof. Reviewed against the 2018 IRC as adopted and amended by the City of Sedona.

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required for remodels or additions involving structural, plumbing, electrical, or mechanical work
  • Specifically required for: installation/relocation of water heaters, furnaces, evaporative coolers, air conditioners; relocation/installation of electrical outlets, lighting, wiring, panels, or services; and replacement of a wood or asphalt shingle roof with a tile roof
  • Exempt work includes: interior painting/paneling/finish work; repair/replacement of non-structural glass, doors, hardware, cabinets, carpeting, or flooring; portable shelves/cases/partitions under 5'-9" high; one-story detached sheds/playhouses under 120 sq ft and 7 ft high with no electrical/plumbing; fences/walls not over 30 inches high outside flood hazard areas
  • Construction Envelope Fence (CEF) required to protect native vegetation during construction
  • Plans must comply with City of Sedona Climatic/Geographic Design Criteria (115 mph Vult wind, Seismic Design Category C)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (Based on Valuation)Sedona City Code § 15.05.060 — remodel/addition fees are calculated on construction valuation the same as new construction
Per City of Sedona Consolidated Fee Schedule, Valuation/Permit Fee Schedule
Plan Review FeeSedona City Code § 15.05.060
65% of the calculated Building Permit Fee

Review timeline

Plan reviewSedona’s published plan-review target
42–42 business days

How long did your Residential Remodel / Addition Building Permit permit actually take in Sedona?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In (Structural/Electrical/Plumbing/Mechanical)

    Before walls are closed, per scope of work

  2. 2

    Final

    Completed work verified against approved plans; required before occupancy of the addition/remodeled space

See the full Sedona inspection guide — scheduling & re-inspection fees →

Tips

  • Per the City of Sedona Residential Remodel/Addition Building Permit Packet, the published A.R.S. § 9-836 time frame is identical to new construction: 21 business days Administrative Completeness + 21 business days Substantive Review = 42 business days overall, authorized under City Code Title 15.
  • Sedona does not publish separate standalone 'electrical permit,' 'plumbing permit,' or 'mechanical/HVAC permit' packets — this scope of work (water heater/furnace/AC installation or relocation, electrical panel/wiring work) is processed through the Residential Remodel/Addition Building Permit rather than a distinct trade-specific permit type.
  • A Construction Envelope Fence (CEF) is required to protect existing native vegetation on the site during construction — this is a Sedona-specific requirement tied to the City's scenic-beauty/community-character provisions.

Frequently asked questions

Yes — a building permit is required for remodels or additions involving structural, plumbing, electrical, or mechanical work, including installation/relocation of water heaters, furnaces, air conditioners, or electrical panels/wiring, and for replacing a wood or asphalt shingle roof with tile. Purely cosmetic work (paint, flooring, cabinets) is exempt.

In Sedona, the published Building Permit Fee (Based on Valuation) is: Per City of Sedona Consolidated Fee Schedule, Valuation/Permit Fee Schedule. Additional published fees: Plan Review Fee — 65% of the calculated Building Permit Fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Sedona's published plan-review target for a residential remodel / addition building permit is 42–42 business days.

You'll need: Residential Building Permit Application; Construction Envelope Fence (CEF) Instructions; Color and Materials Sample Sheet; Stormwater Pollution Prevention Guidelines. See the required-documents checklist on this page for details on each.

Sedona requires 2 inspection(s) for a residential remodel / addition building permit, in order: Rough-In (Structural/Electrical/Plumbing/Mechanical), Final. Schedule each through City of Sedona Community Development Department — Building Safety Division (928-282-1154).

Apply through City of Sedona Community Development Department — Building Safety Division at 102 Roadrunner Drive, Sedona, AZ 86336-3710 (Community Development front counter address also published as 104 Roadrunner Drive in some permit packets). Phone: 928-282-1154, email: Permittechs@sedonaaz.gov. Office hours: Community Development Department phone hours Monday - Thursday, 7:00 a.m. - 6:00 p.m. (4-day, 10-hour City workweek); lobby/front counter hours Monday - Thursday, 7:30 a.m. - 5:00 p.m. Construction Inspection Hotline: 928-282-3268 (call by 3:00 p.m. the business day before to request a next-day inspection). Staff: Steve Mertes, Chief Building Official/Community Development Director, 928-203-5097, smertes@sedonaaz.gov; Becky Oium, Plans Examiner, 928-203-5093; Patty Lewis, Permit Technician, 928-203-5118; Andrew Vaughn, Building Inspector, 928-204-7115, avaughn@sedonaaz.gov.. Official information: https://www.sedonaaz.gov/your-government/departments/community-development/permits.

Sedona, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Sedona runs its own Community Development Department / Building Safety Division and independently adopts and administers its own construction codes as City Code Title 15 (Buildings and Construction); it does not defer permitting to Yavapai County or Coconino County for parcels within Sedona city limits, even though the city itself straddles both counties. Source: Sedona City Code Chapter 15.05 (sedona.municipal.codes/SCC/15.05); City of Sedona Permits and Building Safety webpages.; 2018 International Building Code (IBC), as amended and codified, published by the International Code Council, adopted as the building code of the City of Sedona (Sedona City Code § 15.05.010), with City of Sedona amendments (§ 15.05.020). Adopted by City Council on September 24, 2019 (Ordinance 2019-05, Resolution 2019-18 Exh. A); effective for all permits submitted on or after October 25, 2019. Source: Sedona City Code § 15.05.010/.020; City of Sedona Building Safety and Permits pages ('Building Codes' section).; 2018 International Residential Code (IRC), adopted with City of Sedona amendments (§ 15.05.030/.040), effective October 25, 2019, including the City's amended IRC Table R301.2(1) Climatic and Geographic Design Criteria. Source: Sedona City Code § 15.05.030/.040.; 2018 International Plumbing Code (IPC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage, 'Building Codes' list.; 2018 International Energy Conservation Code (IECC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Mechanical Code (IMC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Existing Building Code (IEBC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Fuel Gas Code (IFGC), adopted with City of Sedona amendments, effective October 25, 2019. Source: City of Sedona Building Safety webpage.; 2018 International Swimming Pool and Spa Code (ISPSC), adopted with City of Sedona amendments, effective October 25, 2019 (referenced in the Swimming Pool, Spa and Hot Tub Building Permit Packet's '2019 Amendments to Sedona City Code' insert). Source: City of Sedona Building Safety webpage; City of Sedona Swimming Pool and Spa Building Permit Packet.; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted with City of Sedona amendments, effective October 25, 2019 (one edition behind the 2018 ICC I-Codes set, consistent with the City's own stated rationale of aligning with 'surrounding communities and counties'). Source: City of Sedona Building Safety webpage.; Manufactured homes, mobile homes, and factory-built buildings are separately defined and regulated under Sedona City Code § 15.05.090 (adopting the Arizona Office of Manufactured Housing construction/installation standards per A.R.S. Title 41, Chapter 16), with the City issuing its own 'Manufactured or factory built home permit' packet for placement, foundation, and site-related requirements. Source: Sedona City Code § 15.05.090; City of Sedona Permits page.; Building permit fees and valuation are governed by Sedona City Code § 15.05.060, which cross-references the City of Sedona Consolidated Fee Schedule (Valuation/Permit Fee Schedule and Unit Permit Fees) as the authoritative fee source rather than the ICC codes' own fee tables; the plan review fee is set at 65 percent of the calculated building permit fee when the permit fee is valuation-based. Source: Sedona City Code § 15.05.060 (sedona.municipal.codes/SCC/15.05.060).. Local amendments apply — see the Sedona overview page for the full list.

No — Sedona's published permit list does not include standalone electrical, plumbing, or mechanical/HVAC permit types. This work is processed under the Residential Remodel/Addition Building Permit using the same application and the same 21/21/42 business-day A.R.S. § 9-836 review time frame.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sedona building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.