EV Charger / EVSE Permit (Billed as General Electrical Work) — Edgewater, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.edgewaterco.gov/city-services/building-planning/applicable-codes-and-design-criteria
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit (Billed as General Electrical Work) in Edgewater, Colorado
Required for installation of a Level 2 (or higher) electric vehicle charger/EVSE in Edgewater. The City has no dedicated EV-charger fee line item, application form, or ordinance — Edgewater's own population (approx. 4,900 per recent Census-based estimates) is below the 10,000-population threshold that makes a municipality a 'covered municipality' under Colorado HB24-1173 (Electric Vehicle Charging System Permits Act, effective Aug. 7, 2024), so the City is not required to adopt the Colorado Energy Office's model EV-charger permitting code or a dedicated objective-standards ordinance. An EV charger circuit is billed under the City's own 'All Other Electrical Fee' (installation-valuation-based) schedule, the same non-living-area electrical fee table the City's own Fee Surcharge Schedule explicitly applies to 'garage, shop, photovoltaic, etc.' work, and reviewed under the 2023 NEC (NFPA 70) Article 625 as adopted by Edgewater Municipal Code Sec. 18-4-10.
Verified 2026-07-20 · Source
When you need this permit
- Electrical Permit Application submitted via the CommunityCore online portal
- Contractors must hold a current Colorado State Electrical Board (DORA) license plus a City of Edgewater Contractor's License; homeowner permits available for work on an owner's own non-rental, non-resale dwelling per CRS 12-23-111(2) Contractor
- Fee calculated under the 'All Other Electrical Fee' (installation-valuation-based) schedule, since an EV charger is non-living-area equipment, not a square-footage-based residential fee item
- No dedicated EV-charger checklist, model-code adoption, or 3-business-day HB24-1173 notification commitment was found published by the City — Edgewater is below the 10,000-population 'covered municipality' threshold that triggers HB24-1173's requirements
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Charger circuit wiring and breaker sizing before concealment
- 2
Final Inspection
EVSE installed, GFCI/disconnect verified, system energized
See the full Edgewater inspection guide — scheduling & re-inspection fees →
Tips
- Edgewater has no EV-charger-specific permit, form, or fee line — a home EV charger/EVSE is billed under the City's 'All Other Electrical Fee' (installation-valuation-based) schedule, which the City's own Fee Surcharge Schedule expressly names for non-living-area work like 'garage, shop, photovoltaic, etc.'
- Colorado's HB24-1173 (EV Charging System Permits Act) requires 'covered municipalities' (population 10,000+) to adopt streamlined EV-charger permitting standards by Dec. 31, 2025 — Edgewater, at roughly 4,900 residents, falls below that threshold and is not bound by the Act's model-code-or-ordinance mandate or its 3-business-day decision-notification clock.
- Homeowner permits require a signed Homeowner Electrical and Plumbing Waiver certifying the property is not for immediate resale and is not tenant-occupied rental property.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Edgewater building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Edgewater
EV Charger / EVSE Permit (Billed as General Electrical Work) in other cities
Compare ev charger / evse permit (billed as general electrical work) fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Edgewater project checklist
Describe your project once and get every permit, document, and fee it triggers in Edgewater — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →