Inspection sequence, scheduling, and re-inspection fees for building permits in Dacono, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
512 Cherry Avenue, Dacono, CO 80514
Phone
303-833-2317
Office hours
City Hall main line 303-833-2317. Building/code questions directed to SAFEbuilt at 970-545-3512. Inspection scheduling via SAFEbuilt Colorado inspection line 1-888-774-0454, or by emailing windsor@safebuilt.com per the Re-Roof building guide. Primary Community Development contact: Raquel Chavez, Community Development Permit Technician (rchavez@daconoco.gov, 303-833-2317 ext. 128). Community Development Director: Marc Kurbansade, AICP, Deputy City Manager (mkurbansade@daconoco.gov, 303-833-2317).

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation / Framing / Rough Trades

    Standard residential construction inspection sequence, as applicable to the ADU's scope (new detached structure vs. conversion of existing space)

  2. 2

    ADU Certification of Exception Inspection

    A distinct, separately fee'd inspection type per the 2026 Fee Schedule; the specific compliance standard it certifies against was not located in the publicly posted materials reviewed

  3. 3

    Final Inspection

    All work complete per approved plans

Applies to: Deck / Covered Patio / Carport Permit

  1. 1

    Footing/Foundation

    Before concrete pour, for decks/carports with new footings

  2. 2

    Framing

    Structural framing and ledger-board attachment (for decks) before cover

  3. 3

    Final Inspection

    All work complete per approved plans

Applies to: Residential Addition / Basement Finish / Remodel Permit

  1. 1

    Foundation (additions with new footings only)

    Before concrete pour

  2. 2

    Rough Frame / Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  3. 3

    Final Inspection

    All work complete per approved plans

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Rough Trades (Electrical/Plumbing/Mechanical)

    Trade rough-ins before concealment

  2. 2

    Final Inspection / Certificate of Occupancy Inspection

    Includes the two inspections bundled into the Certificate of Occupancy fee

Applies to: Electric Vehicle Charging Station Permit

  1. 1

    Rough Electrical

    New circuit/wiring for the charger installed before concealment (if applicable)

  2. 2

    Final Inspection

    Charger installed and connected, circuit verified, system energized; inspector may verify electrician identity/licensure at their discretion

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified; inspector may verify electrician identity/licensure at their discretion

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: Rooftop Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof/ground penetrations, and electrical connections verified

Re-inspection fees

Residential Building Permit (New Construction)Reinspection Fee
$50.00 per inspection
Electrical PermitConstruction Meter or Re-Inspection
$57.50
Electric Vehicle Charging Station PermitConstruction Meter or Re-Inspection
$57.50

Dacono building permits

Get alerts for Dacono

We'll email you when Dacono's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.