Dacono building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Dacono, Colorado.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 512 Cherry Avenue, Dacono, CO 80514
- Phone
- 303-833-2317
- rchavez@daconoco.gov
- Office hours
- City Hall main line 303-833-2317. Building/code questions directed to SAFEbuilt at 970-545-3512. Inspection scheduling via SAFEbuilt Colorado inspection line 1-888-774-0454, or by emailing windsor@safebuilt.com per the Re-Roof building guide. Primary Community Development contact: Raquel Chavez, Community Development Permit Technician (rchavez@daconoco.gov, 303-833-2317 ext. 128). Community Development Director: Marc Kurbansade, AICP, Deputy City Manager (mkurbansade@daconoco.gov, 303-833-2317).
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour
- 2
Framing
Structural framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans and applicable codes
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation / Framing / Rough Trades
Standard residential construction inspection sequence, as applicable to the ADU's scope (new detached structure vs. conversion of existing space)
- 2
ADU Certification of Exception Inspection
A distinct, separately fee'd inspection type per the 2026 Fee Schedule; the specific compliance standard it certifies against was not located in the publicly posted materials reviewed
- 3
Final Inspection
All work complete per approved plans
Applies to: Deck / Covered Patio / Carport Permit
- 1
Footing/Foundation
Before concrete pour, for decks/carports with new footings
- 2
Framing
Structural framing and ledger-board attachment (for decks) before cover
- 3
Final Inspection
All work complete per approved plans
Applies to: Residential Addition / Basement Finish / Remodel Permit
- 1
Foundation (additions with new footings only)
Before concrete pour
- 2
Rough Frame / Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 3
Final Inspection
All work complete per approved plans
Applies to: Commercial Tenant Improvement Permit
- 1
Rough Trades (Electrical/Plumbing/Mechanical)
Trade rough-ins before concealment
- 2
Final Inspection / Certificate of Occupancy Inspection
Includes the two inspections bundled into the Certificate of Occupancy fee
Applies to: Electric Vehicle Charging Station Permit
- 1
Rough Electrical
New circuit/wiring for the charger installed before concealment (if applicable)
- 2
Final Inspection
Charger installed and connected, circuit verified, system energized; inspector may verify electrician identity/licensure at their discretion
Applies to: Electrical Permit
- 1
Rough Electrical
Wiring and panel installed before concealment
- 2
Final Inspection
Devices installed, panel labeled, system energized and verified; inspector may verify electrician identity/licensure at their discretion
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Applies to: Rooftop Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before cover
- 2
Final Inspection
Racking, roof/ground penetrations, and electrical connections verified
Final inspection only: Demolition Permit (Mobile/Modular Home Removal), Re-Roof Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Dacono building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Dacono building permits
Get alerts for Dacono
We'll email you when Dacono's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.