When you need this permit

  • Plans reviewed under the 2024 IRC as locally adopted
  • Site plan, floor plan, and construction details required per SAFEbuilt's Home Additions Guide for additions
  • Basement Finish scope has its own dedicated SAFEbuilt guide (egress, smoke/CO alarms, ceiling height, and ventilation requirements per the 2024 IRC)
  • Owner-builder permits: as owner-builder, the property owner is the responsible party of record; if work is performed by a contractor, the contractor must hold the applicable City contractor license (Category A/B/C) and Colorado state trade licenses as applicable Owner-builderContractor
  • Eligible for the City's 'Almost Free Building Permit' June promotional fee reduction if owner-applied (not contractor-applied) and the project is an alteration/repair/improvement of an existing structure

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee2026 Fee Schedule
Computed from ICC Building Valuation Data based on project valuation
Plan Review Fee
65% of Building Permit Fee
Construction Use Tax
1.5% of total project cost (materials)
Almost Free Building Permit Month discount (June, owner-applicant only)Excludes new residential construction and non-residential projects; work must be completed and inspected by September 30, 2026 for the 2026 cycle; contractor-submitted applications are charged full fees
Temporarily reduced building permit, plan review, and inspection fees

Review timeline

Plan review
Not published — contact the department

How long did your Residential Addition / Basement Finish / Remodel Permit permit actually take in Dacono?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation (additions with new footings only)

    Before concrete pour

  2. 2

    Rough Frame / Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  3. 3

    Final Inspection

    All work complete per approved plans

See the full Dacono inspection guide — scheduling & re-inspection fees →

Tips

  • If you are the homeowner applying yourself (not through a contractor), your project may qualify for reduced fees during the City's 'Almost Free Building Permit Month' each June — but new residential construction and non-residential projects are excluded, and contractor-submitted applications are charged full fees regardless of timing.
  • As an owner-builder, you become the responsible party of record on the permit — confirm you understand the liability implications before pulling a permit yourself instead of through a licensed contractor. Owner-builderContractor

Frequently asked questions

Dacono requires a residential addition / basement finish / remodel permit for: Plans reviewed under the 2024 IRC as locally adopted; Site plan, floor plan, and construction details required per SAFEbuilt's Home Additions Guide for additions; Basement Finish scope has its own dedicated SAFEbuilt guide (egress, smoke/CO alarms, ceiling height, and ventilation requirements per the 2024 IRC); Owner-builder permits: as owner-builder, the property owner is the responsible party of record; if work is performed by a contractor, the contractor must hold the applicable City contractor license (Category A/B/C) and Colorado state trade licenses as applicable; Eligible for the City's 'Almost Free Building Permit' June promotional fee reduction if owner-applied (not contractor-applied) and the project is an alteration/repair/improvement of an existing structure. If your project isn't listed, confirm with City of Dacono Community Development Department (building permitting/inspections administered by SAFEbuilt, Inc., the City's contracted third-party building department partner) at 303-833-2317 before starting work.

In Dacono, the published Building Permit Fee is: Computed from ICC Building Valuation Data based on project valuation. Additional published fees: Plan Review Fee — 65% of Building Permit Fee; Construction Use Tax — 1.5% of total project cost (materials); Almost Free Building Permit Month discount (June, owner-applicant only) — Temporarily reduced building permit, plan review, and inspection fees. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Dacono does not publish a plan-review timeline for this permit. Contact City of Dacono Community Development Department (building permitting/inspections administered by SAFEbuilt, Inc., the City's contracted third-party building department partner) at 303-833-2317 for current turnaround.

You'll need: Building Permit Application; Site Plan and Floor Plan. See the required-documents checklist on this page for details on each.

Dacono requires 3 inspection(s) for a residential addition / basement finish / remodel permit, in order: Foundation (additions with new footings only), Rough Frame / Rough Electrical / Plumbing / Mechanical, Final Inspection. Schedule each through City of Dacono Community Development Department (building permitting/inspections administered by SAFEbuilt, Inc., the City's contracted third-party building department partner) (303-833-2317).

Apply through City of Dacono Community Development Department (building permitting/inspections administered by SAFEbuilt, Inc., the City's contracted third-party building department partner) at 512 Cherry Avenue, Dacono, CO 80514. Phone: 303-833-2317, email: rchavez@daconoco.gov. Office hours: City Hall main line 303-833-2317. Building/code questions directed to SAFEbuilt at 970-545-3512. Inspection scheduling via SAFEbuilt Colorado inspection line 1-888-774-0454, or by emailing windsor@safebuilt.com per the Re-Roof building guide. Primary Community Development contact: Raquel Chavez, Community Development Permit Technician (rchavez@daconoco.gov, 303-833-2317 ext. 128). Community Development Director: Marc Kurbansade, AICP, Deputy City Manager (mkurbansade@daconoco.gov, 303-833-2317).. Official information: https://www.daconoco.gov/875/Building-Codes-Permits.

Dacono, Colorado has adopted: 2024 International Building Code (IBC) — City of Dacono Building Codes page, adopted for all new permit submittals; 2024 International Residential Code (IRC); 2024 International Fuel Gas Code (IFGC); 2024 International Plumbing Code (IPC); 2024 International Mechanical Code (IMC); 2024 International Existing Building Code (IEBC); 2024 International Property Maintenance Code (IPMC); 2024 International Swimming Pool and Spa Code (ISPSC); 2024 International Energy Conservation Code (IECC); 2024 International Fire Code (IFC); 2023 National Electrical Code (NEC); Adopted via Ordinance 1002 (December 17, 2025, effective date of the 2024 code cycle) and subsequently amended by Ordinance 1010 (March 23, 2026); prior code cycle was adopted under Ordinance 949 (October 9, 2023). The City's live Building Codes webpage lists these three ordinances directly beneath the Adopted Codes list.; Colorado HB 1091 (Lofgren & Johnson Families Carbon Monoxide Safety Act) is separately cross-referenced on the City's Building Codes page as an applicable state law requiring carbon monoxide alarms under specified conditions — this is a state statute the City flags for awareness, not a City-adopted model code edition.; HB22-1362 (Colorado statewide energy code/electric- and solar-ready standard, applicable window July 2023-July 2026): Dacono's adoption of the 2024 IECC (effective December 17, 2025, per Ordinance 1002) falls within this window. The City's Building Codes page does not itself cite HB22-1362 or describe the 2024 IECC adoption as an HB22-1362 compliance action — this connection is inferred from the timing and code edition, not confirmed by an explicit City statement, so it is not asserted as a settled fact for any permit-level requirement in this file.. Local amendments apply — see the Dacono overview page for the full list.

Yes, if you apply as the homeowner (not through a contractor) during the City's 'Almost Free Building Permit Month' each June, for an alteration, repair, or improvement of an existing residential structure or associated accessory structure. New residential construction and non-residential projects do not qualify, and use tax still applies.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Dacono building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.