Electric Vehicle Charging Station Permit — Dacono, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.daconoco.gov/DocumentCenter/View/3684/Electrical-License-Contemporaneous-Review-pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle Charging Station Permit in Dacono, Colorado
The City of Dacono does not publish a standalone EV charger/EVSE permit application or fee line -- checked the Building Codes & Permits page, the 2026 Fee Schedule, and the Electrical License Contemporaneous Review Guidelines directly; none name electric vehicle charging stations, EV chargers, or EVSE. Because Dacono runs its own local electrical permitting program (unlike jurisdictions that defer entirely to the state), an EV charger installation is processed as a standard Electrical Permit under the 2023 NEC as adopted, billed on the City's 'All Other Electrical Fee' valuation-based schedule (the same table used for any non-new-construction electrical work), with contemporaneous Colorado State Electrical Board license verification for the installing electrician per this file's electrical-permit entry.
Verified 2026-07-20 · Source
When you need this permit
- Governed by the 2023 NEC as locally adopted, including NEC Article 625 (Electric Vehicle Power Transfer System)
- Electrician must be registered with the City (registration form emailed to Raquel Chavez) and must hold a current Colorado State Electrical Board license, contemporaneously verified by the City via the DORA online lookup before permit issuance, per CRS 12-23-105/116(10)
- No City of Dacono EV-charger-specific permit application exists; use the standard Electrical Permit Application via the Community Core online portal
- A standalone EV charger installation (new circuit/outlet or hardwired unit, not part of new-construction square footage) is billed under the 'All Other Electrical Fee' valuation-based line items rather than the residential square-footage table
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
New circuit/wiring for the charger installed before concealment (if applicable)
- 2
Final Inspection
Charger installed and connected, circuit verified, system energized; inspector may verify electrician identity/licensure at their discretion
See the full Dacono inspection guide — scheduling & re-inspection fees →
Tips
- There is no separate 'EV charger permit' in Dacono -- it is processed as a standard Electrical Permit, billed under the 'All Other Electrical Fee' valuation table ($115.00 flat up to $2,000 valuation) rather than the residential square-footage table used for new-construction electrical work.
- The City rejects 'electrical only' permit applications outright if the listed electrician's state license cannot be verified as active -- confirm your electrician's DORA license status before submitting for an EV charger installation.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Dacono building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Dacono
Electric Vehicle Charging Station Permit in other cities
Compare electric vehicle charging station permit fees across Colorado →
Look up this fee in a different city →