Dacono's published demolition-related fee is specific to mobile/modular home removal or demolition; no separate general structure-demolition fee line item distinct from this was located in the 2026 Fee Schedule. A bond is required to ensure debris removal and site safety.

Reviewed 2026-07-06 · Source

When you need this permit

  • A $2,000.00 bond is required before a removal/demolition permit for a mobile or modular home will be issued, conditioned on compliance with debris/trash/rubbish removal requirements and covering/fencing of the foundation or footing
  • Cash may be accepted in lieu of a bond, but checks and money orders are not accepted for the bond itself

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Removal or Demolition of Mobile or Modular HomePlus required $2,000 bond (or cash in lieu); 2026 Fee Schedule, Building Permit Fees section
$50.00

Review timeline

Plan review
Not published — contact the department

How long did your Demolition Permit (Mobile/Modular Home Removal) permit actually take in Dacono?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Site Inspection

    Verifies debris removal and foundation/footing covering or fencing per bond conditions

See the full Dacono inspection guide — scheduling & re-inspection fees →

Tips

  • The only demolition-specific fee item published in Dacono's 2026 Fee Schedule applies to mobile/modular home removal ($50 fee plus a required $2,000 bond); general structure demolition (e.g., a stick-built house or accessory structure) is not separately broken out and would likely be billed under the general Building Valuation Data method — confirm with the Building Department for non-mobile-home demolition scopes.

Frequently asked questions

Dacono requires a demolition permit (mobile/modular home removal) for: A $2,000.00 bond is required before a removal/demolition permit for a mobile or modular home will be issued, conditioned on compliance with debris/trash/rubbish removal requirements and covering/fencing of the foundation or footing; Cash may be accepted in lieu of a bond, but checks and money orders are not accepted for the bond itself. If your project isn't listed, confirm with City of Dacono Community Development Department (building permitting/inspections administered by SAFEbuilt, Inc., the City's contracted third-party building department partner) at 303-833-2317 before starting work.

In Dacono, the published Removal or Demolition of Mobile or Modular Home is: $50.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Dacono does not publish a plan-review timeline for this permit. Contact City of Dacono Community Development Department (building permitting/inspections administered by SAFEbuilt, Inc., the City's contracted third-party building department partner) at 303-833-2317 for current turnaround.

You'll need: Demolition Permit Application; $2,000 Bond (or cash in lieu). See the required-documents checklist on this page for details on each.

Dacono requires 1 inspection(s) for a demolition permit (mobile/modular home removal), in order: Final Site Inspection. Schedule each through City of Dacono Community Development Department (building permitting/inspections administered by SAFEbuilt, Inc., the City's contracted third-party building department partner) (303-833-2317).

Apply through City of Dacono Community Development Department (building permitting/inspections administered by SAFEbuilt, Inc., the City's contracted third-party building department partner) at 512 Cherry Avenue, Dacono, CO 80514. Phone: 303-833-2317, email: rchavez@daconoco.gov. Office hours: City Hall main line 303-833-2317. Building/code questions directed to SAFEbuilt at 970-545-3512. Inspection scheduling via SAFEbuilt Colorado inspection line 1-888-774-0454, or by emailing windsor@safebuilt.com per the Re-Roof building guide. Primary Community Development contact: Raquel Chavez, Community Development Permit Technician (rchavez@daconoco.gov, 303-833-2317 ext. 128). Community Development Director: Marc Kurbansade, AICP, Deputy City Manager (mkurbansade@daconoco.gov, 303-833-2317).. Official information: https://www.daconoco.gov/875/Building-Codes-Permits.

Dacono, Colorado has adopted: 2024 International Building Code (IBC) — City of Dacono Building Codes page, adopted for all new permit submittals; 2024 International Residential Code (IRC); 2024 International Fuel Gas Code (IFGC); 2024 International Plumbing Code (IPC); 2024 International Mechanical Code (IMC); 2024 International Existing Building Code (IEBC); 2024 International Property Maintenance Code (IPMC); 2024 International Swimming Pool and Spa Code (ISPSC); 2024 International Energy Conservation Code (IECC); 2024 International Fire Code (IFC); 2023 National Electrical Code (NEC); Adopted via Ordinance 1002 (December 17, 2025, effective date of the 2024 code cycle) and subsequently amended by Ordinance 1010 (March 23, 2026); prior code cycle was adopted under Ordinance 949 (October 9, 2023). The City's live Building Codes webpage lists these three ordinances directly beneath the Adopted Codes list.; Colorado HB 1091 (Lofgren & Johnson Families Carbon Monoxide Safety Act) is separately cross-referenced on the City's Building Codes page as an applicable state law requiring carbon monoxide alarms under specified conditions — this is a state statute the City flags for awareness, not a City-adopted model code edition.; HB22-1362 (Colorado statewide energy code/electric- and solar-ready standard, applicable window July 2023-July 2026): Dacono's adoption of the 2024 IECC (effective December 17, 2025, per Ordinance 1002) falls within this window. The City's Building Codes page does not itself cite HB22-1362 or describe the 2024 IECC adoption as an HB22-1362 compliance action — this connection is inferred from the timing and code edition, not confirmed by an explicit City statement, so it is not asserted as a settled fact for any permit-level requirement in this file.. Local amendments apply — see the Dacono overview page for the full list.

Yes. A $2,000 bond (or cash in lieu, no checks/money orders) is required before the City will issue a permit for removal or demolition of a mobile or modular home, in addition to the $50 permit fee.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Dacono building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.