Mechanical / HVAC Permit in Nunn, Colorado

Required for furnace, boiler, and gas piping installation or replacement in Nunn. Governed by the 2018 International Mechanical Code and 2018 International Fuel Gas Code as locally amended (e.g., 18-inch minimum plastic fuel gas pipe burial depth, 10 psig test pressure, 15-minute test duration for small-volume/single-family systems).

Verified 2026-07-23 · Source

When you need this permit

  • Furnace installations/replacements, boiler installations/replacements, and gas piping over 10 feet in length all explicitly require a permit per the Town's own building-permit-needed list
  • Governed by the 2018 IMC and 2018 IFGC as locally amended
  • Gas piping test requirements per IFGC 406.4.1/406.4.2 as amended: 10 psig test pressure, minimum 15-minute test duration for systems under 10 cubic feet or single-family dwellings
  • Plastic fuel gas piping must be buried at least 18 inches below grade per IFGC 404.12 as amended

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Town Admin Fee (Building Permit) + Use TaxCLOSED (water heater/furnace/boiler REPLACEMENT scope) / PARTIALLY CLOSED (other mechanical scopes) 2026-07-23 on a live primary source: the Town of Nunn's 'Fee Schedule, Effective January 22nd, 2026' (PDF, linked live from the Town homepage — not located in the prior 2026-07-06 chase) explicitly lists 'Admin Fee (One Stop permits-re-roof, hot water heater etc.) $50.00' — a direct, named match to this permit type's own water-heater/furnace-replacement scope — alongside 'Admin Fee (permits requiring plan review) $75.00' and 'Use Tax on all Building Permits 2%'. New-installation or larger mechanical scopes (e.g. gas piping runs over 10 feet) are not explicitly classified by the Town as 'One Stop,' so the plan-review tier may instead apply; both real figures are reported. This is the Town Clerk's own flat component only — charged in addition to SAFEbuilt's separate valuation-based fee, which remains unpublished as a table.
$50.00 flat Admin Fee for water heater/furnace/boiler replacement processed as a 'One Stop' permit (explicitly named by the Town); $75.00 for scopes requiring SAFEbuilt plan review (e.g. new furnace/boiler installation, gas piping runs); plus 2% Use Tax on all Building Permits

Review timeline

Plan review
Not published — contact the department

How long did your Mechanical / HVAC Permit permit actually take in Nunn?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Mechanical / Gas Piping Pressure Test

    Ductwork, flues, equipment placement, and gas piping pressure test before concealment; scheduled with SAFEbuilt

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

See the full Nunn inspection guide — scheduling & re-inspection fees →

Tips

  • Furnace/boiler/water heater REPLACEMENTS require a permit in Nunn just like new installations — the Town's own project list explicitly names 'Furnace installations or replacement,' 'Boiler installation or replacement,' and 'Water heater installations or replacement' as permit-required items, so don't assume a like-for-like swap is exempt.
  • Gas piping runs over 10 feet trigger a permit requirement per the Town's own published project list.

Frequently asked questions

Nunn requires a mechanical / hvac permit for: Furnace installations/replacements, boiler installations/replacements, and gas piping over 10 feet in length all explicitly require a permit per the Town's own building-permit-needed list; Governed by the 2018 IMC and 2018 IFGC as locally amended; Gas piping test requirements per IFGC 406.4.1/406.4.2 as amended: 10 psig test pressure, minimum 15-minute test duration for systems under 10 cubic feet or single-family dwellings; Plastic fuel gas piping must be buried at least 18 inches below grade per IFGC 404.12 as amended. If your project isn't listed, confirm with Town of Nunn Town Clerk's Office (Building/Planning) at 970-897-2385 before starting work.

In Nunn, the published Town Admin Fee (Building Permit) + Use Tax is: $50.00 flat Admin Fee for water heater/furnace/boiler replacement processed as a 'One Stop' permit (explicitly named by the Town); $75.00 for scopes requiring SAFEbuilt plan review (e.g. new furnace/boiler installation, gas piping runs); plus 2% Use Tax on all Building Permits. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Nunn does not publish a plan-review timeline for this permit. Contact Town of Nunn Town Clerk's Office (Building/Planning) at 970-897-2385 for current turnaround.

You'll need: Building Permit Application (Mechanical/HVAC scope). See the required-documents checklist on this page for details on each.

Nunn requires 2 inspection(s) for a mechanical / hvac permit, in order: Rough Mechanical / Gas Piping Pressure Test, Final Inspection. Schedule each through Town of Nunn Town Clerk's Office (Building/Planning) (970-897-2385).

Apply through Town of Nunn Town Clerk's Office (Building/Planning) at 185 Lincoln Ave / P.O. Box 171, Nunn, CO 80648. Phone: 970-897-2385, email: kendra.minch@townofnunnco.gov. Office hours: Town of Nunn does not publish standing office hours on the Building/Planning page or Town Clerk page; general contact is 970-897-2385 / town.clerk@townofnunnco.gov. Nunn has no dedicated Building Department staff — the Town Clerk's Office intakes all building permit applications and coordinates with the Planning Board (for structures over 120 sq ft) and SAFEbuilt (contracted plan review and inspections).. Official information: https://townofnunn.colorado.gov/departments/building/planning.

Nunn, Colorado has adopted: 2018 International Building Code (IBC), chapters 1-33 and appendix chapter 1, adopted by reference — Nunn Municipal Code (NMC) 15.04.020, as amended (Ord. No. 237 12-18-2003; Ord. No. 263 5-3-2007; Ord. No. 317 6-20-2019); 2018 International Residential Code (IRC), chapters 1-43 and appendix chapters H and M, adopted by reference — NMC 15.04.120, as amended (Ord. No. 237, 263, 317); 2018 International Mechanical Code (IMC), chapters 1-15, adopted by reference — NMC 15.04.030 (Ord. No. 237, 263, 317); 2018 International Plumbing Code (IPC), chapters 1-13, adopted by reference — NMC 15.04.050 (Ord. No. 237, 12-18-2003); 2018 International Fuel Gas Code (IFGC), chapters 1-8, adopted by reference — NMC 15.04.090 (Ord. No. 237, 263, 317); 2018 International Existing Building Code (IEBC), chapters 1-16, adopted by reference — NMC 15.04.130 (Ord. No. 263 5-3-2007; Ord. No. 317 6-20-2019); 2018 International Property Maintenance Code (IPMC), chapters 1-8, adopted by reference — NMC 15.04.150 (Ord. No. 317 6-20-2019); 2018 International Swimming Pool and Spa Code (ISPSC), chapters 1-11, adopted by reference — NMC 15.04.160 (Ord. No. 317 6-20-2019); 2012 International Energy Conservation Code (IECC), chapters 1-5, adopted by reference as the town energy conservation code — NMC 15.04.140 (Ord. No. 317 6-20-2019); IBC section 1301.1.1/101.4.6 and IRC chapter 11 are both explicitly amended to substitute the 2012 IECC as well; National Electrical Code, 2002 edition, adopted by reference — NMC 15.04.040 (codified text, unamended since original Code 2002 codification). NOTE: this is the currently codified NEC edition in the 2024 Nunn Municipal Code as republished by Ordinance No. 326 (adopted 6-20-2024, adopting/enacting the Municipal Code by reference). However, SAFEbuilt's own current 'Photovoltaic System Submittal Requirements' handout (the Town's contracted plan-review/inspection agency) states 'Applicable current codes are the 2020 NEC, 2018 International Codes' — a direct discrepancy between the codified 2002 NEC text and SAFEbuilt's operational reference. Flagged honestly rather than resolved by assumption; the governing citation is the codified 2002 NEC per NMC 15.04.040 pending confirmation from the Town.; Chapter 15.16 (Energy Efficiency Construction) of the Nunn Municipal Code additionally references the 1977/1978 Colorado Model Energy Efficiency Construction and Renovation Standards for Nonresidential Buildings and the companion Colorado Recommended Energy Conservation 'Performance' Code for Residential Buildings — these appear to be vestigial/superseded provisions retained from the original 2002 code codification and predate the town's adoption of the 2012 IECC at NMC 15.04.140 (2019); not applied as the governing energy standard in this file.. Local amendments apply — see the Nunn overview page for the full list.

Yes. The Town of Nunn's Building/Planning page explicitly lists furnace installations or replacement, boiler installation or replacement, and water heater installations or replacement as projects requiring a building permit.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nunn building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.