Plumbing Permit — Nunn, Colorado · Requirements sheet
Reviewed 2026-07-23 · Source: https://townofnunn.colorado.gov/departments/building/planning
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Plumbing Permit in Nunn, Colorado
Required for plumbing system installation, alteration, or repair in Nunn. Governed by the 2018 International Plumbing Code as locally amended. Like electrical work, Nunn defers plumber licensure entirely to the Colorado State Plumbing Board (DORA) rather than running its own local plumbing contractor licensing program, with contemporaneous license verification required by the Town per HB19-1086.
Reviewed 2026-07-23 · Source
When you need this permit
- Plumbing-only permit applications must list the plumber's Colorado DORA state plumbing license number
- The Town verifies the listed plumber's license is active via the Colorado DORA online license lookup before accepting the application
- If the plumber performing/overseeing the work changes before final inspection, the Town must be notified and will re-verify the new plumber's license; unverified changes require work to stop
- Governed by the 2018 IPC as locally amended (e.g., 12-inch minimum sewer depth per IPC 305.4.1/903.1 as amended, reclaimed water systems provision deleted)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment; scheduled with SAFEbuilt
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
See the full Nunn inspection guide — scheduling & re-inspection fees →
Tips
- Confirm your plumber's Colorado DORA license is active before submitting — the same contemporaneous-verification process applies as for electrical permits.
- Nunn's IPC amendment sets minimum sewer depth at 12 inches (rather than the unamended IPC default) — confirm your plumbing plan reflects this local figure.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nunn building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Nunn
Plumbing Permit in other cities
Compare plumbing permit fees across Colorado →
Look up this fee in a different city →