Rooftop / Ground-Mounted Solar Photovoltaic Permit in Nunn, Colorado
Required for solar panel installation or replacement in Nunn. SAFEbuilt (the Town's contracted plan-review/inspection agency) publishes a dedicated Photovoltaic System Submittal Requirements packet specifying current applicable codes as the 2020 NEC and 2018 International Codes, plus structural engineering letter requirements for roof-mounted and ground-mounted systems.
Verified 2026-07-20 · Source
When you need this permit
- Permit application (emailed to the Town or submitted online) must fully describe the work, with valuation based on total cost to the customer (contract price) including materials and labor regardless of who supplies them
- A separate plan review — and potentially a separate permit — is required for each building/address on a property
- Per SAFEbuilt's Photovoltaic System Submittal Requirements packet, applicable current codes are the 2020 NEC and 2018 International Codes (this is SAFEbuilt's own stated reference and differs from the 2002 NEC edition still shown in the codified Nunn Municipal Code text at NMC 15.04.040 — see localAmendments note)
- Roof-mounted systems require a structural engineer's stamped letter addressing added roof weight and additional wind load from the panels, designed to a minimum ground snow load of 30 psf, wind speed of 115 mph Vult, Exposure C, and Seismic Design Category B, including roof connection/embedment type
- Ground-mounted systems require an engineer-stamped letter for system support and wind load, using the same 30 psf snow load / 115 mph Vult / Exposure C / Seismic Design Category B design basis
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before cover; scheduled with SAFEbuilt
- 2
Final Inspection
Racking, roof/ground penetrations, and electrical connections verified
See the full Nunn inspection guide — scheduling & re-inspection fees →
Tips
- A separate structural engineer's stamped letter is required for BOTH roof-mounted and ground-mounted systems in Nunn — budget for this cost and lead time before submitting.
- SAFEbuilt cites the 2020 NEC as the applicable current electrical code for solar work, which is newer than the 2002 NEC edition still shown in the codified Nunn Municipal Code text — confirm directly with SAFEbuilt/the Town Clerk which edition will actually govern your specific inspection.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nunn building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Nunn
Rooftop / Ground-Mounted Solar Photovoltaic Permit in other cities
Compare rooftop / ground-mounted solar photovoltaic permit fees across Colorado →