EV Charger / EVSE Permit — Nunn, Colorado · Requirements sheet
Reviewed 2026-07-23 · Source: https://townofnunn.colorado.gov/departments/building/planning
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Nunn, Colorado
The Town of Nunn does not publish a dedicated EV charger/EVSE permit type. Installation of a Level 2 EV charger is permitted under the Town's standard Electrical Permit, administered on the Town's behalf by its contracted plan-review/inspection provider, SAFEbuilt. As with all electrical work in Nunn, the Town verifies the installing electrician's Colorado DORA state electrical license before accepting the application (per C.R.S. 12-115-120(1)/(10), HB19-1086) — Nunn has no local electrical contractor licensing program of its own. The Town's 2026 Fee Schedule publishes a general two-tier Building Permit Admin Fee ($75 plan-review / $50 One Stop) plus a 2% Use Tax, but names no EV-specific line item, so no EV-specific dollar figure can be verified.
Reviewed 2026-07-23 · Source
When you need this permit
- Electrical permit application must list the electrician's Colorado DORA state electrical license number; the Town verifies it is active before accepting the application
- Governed by the National Electrical Code as adopted by reference in Nunn Municipal Code 15.04.040 (codified as the 2002 edition, though SAFEbuilt's current operational submittal guidance references the 2020 NEC — an unresolved discrepancy)
- If the electrician performing the work changes before final inspection, the Town must be notified and will re-verify the new electrician's license
- No EV-specific permit category, application, or dedicated fee line item is published by the Town of Nunn as of 2026-07-23 (the Town's general two-tier Building Permit Admin Fee structure applies instead — see fees below)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
The Town of Nunn's 'Fee Schedule, Effective January 22nd, 2026' (PDF, linked from the Town homepage) establishes exactly two Building-Permit Admin Fee tiers Town-wide: 'Admin Fee (permits requiring… Show full citationHide
The Town of Nunn's 'Fee Schedule, Effective January 22nd, 2026' (PDF, linked from the Town homepage) establishes exactly two Building-Permit Admin Fee tiers Town-wide: 'Admin Fee (permits requiring plan review) $75.00' and 'Admin Fee (One Stop permits-re-roof, hot water heater etc.) $50.00', plus 'Use Tax on all Building Permits 2%'. The schedule does not name EV chargers or a generic 'electrical permit' under either tier, so which flat fee applies is not Town-published; both real figures are given here. This is the Town Clerk's own flat component only — charged in addition to SAFEbuilt's separate valuation-based fee, which is not published as a table.Review timeline
Inspection process
- 1
Rough Electrical
Circuit wiring and panel connection installed before concealment; scheduled with SAFEbuilt
- 2
Final Inspection
EVSE installed, devices verified, electrician identity may be re-verified at inspector's discretion
See the full Nunn inspection guide — scheduling & re-inspection fees →
Tips
- Confirm your electrician's Colorado DORA license is active BEFORE submitting — the Town rejects applications where the license cannot be verified online.
- Nunn has no dedicated EV charger permit or EV-specific fee line item; the installation is billed and processed as a standard Electrical Permit through the Town's contracted provider, SAFEbuilt, under the Town's general $75/$50 Building Permit Admin Fee structure plus 2% Use Tax.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-23.
Fee schedules
Checklists & handouts
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Nunn building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Nunn's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Nunn yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Nunn lands. Privacy.
Other permits in Nunn
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Colorado →
Look up this fee in a different city →